Authors: Sena Senses and Mustafa Kumral

Affiliation: Mining and Materials Engineering Department, McGill University, 3450 Rue University, Montréal, QC H3A 2A7, Canada

Keyword(s): Project Management, Time-Cost Trade-off, Electrical Substation Construction, Discrete-Event Simulation.

Abstract: Project Management is a key activity in engineering and business entities to achieve specific objectives (e.g., construction, expansion, supply chain, and replacement). Effective project management includes a detailed investigation of the project’s costs and benefits and examining the short- and long-term effects of project design and implementation. In the mining industry, due to the operations’ inherent complexity and uncertainty associated with geological and financial inaccuracies, there is a substantial risk that the project may run over budget and schedule. It is vital to consider the project’s uncertainties to meet the project’s goals. This paper proposes a combined simulation and optimization model for time-cost trade-off project scheduling problems under uncertainty. A numerical example is conducted to demonstrate the effectiveness of the developed model through an electrical substation construction project conducted in a mine. By introducing numerous crashing scenarios to q uantify the impact of uncertainty on the entire project and to assess the risks, the trade-off between time and cost is achieved under the project budget and deadline constraints. The proposed research has a significant potential to improve the management of construction projects considering a detailed project management methodology. (More)

CC BY-NC-ND 4.0

Sign In Guest: Register as new SciTePress user now for free.

Sign In SciTePress user: please login.

PDF ImageMy Papers

You are not signed in, therefore limits apply to your IP address 3.128.226.128

In the current month:
Recent papers: 100 available of 100 total
2+ years older papers: 200 available of 200 total

Paper citation in several formats:
Senses, S. and Kumral, M. (2023). Managing Trade-off Between Cost and Time in Project Scheduling Problems Using Discrete Event Simulation. In Proceedings of the 13th International Conference on Simulation and Modeling Methodologies, Technologies and Applications - SIMULTECH; ISBN 978-989-758-668-2; ISSN 2184-2841, SciTePress, pages 178-185. DOI: 10.5220/0012004900003546

@conference{simultech23,
author={Sena Senses. and Mustafa Kumral.},
title={Managing Trade-off Between Cost and Time in Project Scheduling Problems Using Discrete Event Simulation},
booktitle={Proceedings of the 13th International Conference on Simulation and Modeling Methodologies, Technologies and Applications - SIMULTECH},
year={2023},
pages={178-185},
publisher={SciTePress},
organization={INSTICC},
doi={10.5220/0012004900003546},
isbn={978-989-758-668-2},
issn={2184-2841},
}

TY - CONF

JO - Proceedings of the 13th International Conference on Simulation and Modeling Methodologies, Technologies and Applications - SIMULTECH
TI - Managing Trade-off Between Cost and Time in Project Scheduling Problems Using Discrete Event Simulation
SN - 978-989-758-668-2
IS - 2184-2841
AU - Senses, S.
AU - Kumral, M.
PY - 2023
SP - 178
EP - 185
DO - 10.5220/0012004900003546
PB - SciTePress