Abstract: Software projects are well known for their high overruns in terms of budget and time. As they grow larger,
project monitoring becomes harder. In such a context, forecasting becomes a critical “ability”, helping the
project manager to understand where the project is heading, in terms of required budged and
implementation time. In this paper, we present a forecasting method that we developed, which makes use of
a distinct representation of the observed behavior of project team members towards work that is Work
Behavior. Moreover, we present the first results from experiments on real-world software project
development data that show that our method is more accurate than a very popular prediction method,
implemented by most ALM tools.
1 INTRODUCTION AND
BACKGROUND
Many popular ALM (Application Lifecycle
Management) tool providers consider that, in certain
application conditions, the forecasting capability is a
must for such tools. Many ALM tools offer this
capability, despite critics like those in (DeMarco,
2009) and (Wysocki, 2010).
Considering the existing project management
prediction methods, we can state there are many
methods destined to forecast the resources required
by a project, also known as estimation methods
(Project Management Institute, 2008), which are
used at the beginning of the project, and which
resulted from documented research. An example is
the COCOMO suite of models (Boehm et al., 2005).
In the same time, there are just a few prediction
methods that can be used during project
development to support decision making. One is the
Velocity Trend prediction which is part of the
popular Scrum Agile framework (Deemer and
Benefield, 2007), and which is offered in most ALM
tools, such as CollabNet Team Forge (CollabNet,
n.d.) and IBM Rational Team Concert (IBM, n.d.).
In this context, we are developing a monitoring
framework for large-scale software projects, the
Behavioral Monitoring Framework that has a
prediction dedicated component model. We
portrayed the monitoring framework and a part of its
component models in (Stanciu et al., 2009), (Stanciu
et al., 2010), and (Stanciu et al., 2010). A very
interesting approach to historical information
characterization that inspired us in the development
of the Work Behavior Prediction method is
presented in (Gîrba, 2005).
In this paper, we present the Work Behavior
Prediction method, which is part of our Behavioral
Monitoring Framework. The paper is organized as
follows: section 2 describes the prediction method
that we propose; section 3 presents the methodology
used in the evaluation of our forecasting method; in
section 4, the evaluation results are showed and
discussed; finally, section 5 presents the conclusions
of this paper.
2 WORK BEHAVIOR
PREDICTION
The Work Behavior Prediction is a forecasting
methodology that uses historical information in
order to predict, at any time during project
development, the remaining effort for a task at a
chosen time in the future.
2.1 Definitions
Definition 1 (Remaining Effort). Remaining Effort.
47
Stanciu C..
WORK BEHAVIOR PREDICTION DURING SOFTWARE PROJECTS DEVELOPMENT.
DOI: 10.5220/0003505000470052
In Proceedings of the 6th International Conference on Software and Database Technologies (ICSOFT-2011), pages 47-52
ISBN: 978-989-8425-76-8
Copyright
c
2011 SCITEPRESS (Science and Technology Publications, Lda.)
for a task is an amount of work considered necessary
to be spent for completing that task.
Definition 2 (History). History (H) for a task is an
chronologically ordered set of Remaining Effort
reports, covering a subinterval of or the entire period
of time between task start and task completion.
Definition 3 (Stagnation). Stagnation (ST) is the
probability that, given a History for a task, two
consecutive History elements show the same
Remaining Effort.
Equation (1) shows the Stagnation computed on
a History H.
 =
(
)

(

)
(1)
Definition 4 (Diversification). Diversification (DV)
is the probability that, given a History for a task,
exactly two of three consecutive History elements
show the same Remaining Effort.
Equation (2) shows the Diversification computed
on a History H.
 =
(
)

(

)

(

)
+
(
)

(

)

(

)
.
(2)
Definition 5 (Velocity). Given a History for a task,
Velocity (VL) is the mean difference between
consecutive History elements’ Remaining Effort.
Equation (3) shows the Velocity computed on a
History H.
 = ()( + 1)
.
(3)
Definition 6 (Work Behavior). Given a History for a
task, Work Behavior (WB) is a triplet of Stagnation,
Diversification, and Velocity values computed for
the given History.
Equation (4) shows the meaning of Work
Behavior.
 = (,,).
(4)
Definition 7 (Implementation Moment). Given a
History for an in-work task, the Implementation
Moment (IM) is the number of History elements
divided by the first History element’s Remaining
Effort.
Equation (5) shows the Implementation Moment
computed on a History H. Please note that a first
History element, H(0), of value 0 (meaning an initial
Remaining Effort of 0 effort units) makes no sense.
 =
(0)
, –  .
(5)
Definition 8 (Virtual Present). Given a History for a
completed task and an Implementation Moment of
an in-work task, Virtual Present (VP) is the first
History element’s Remaining Effort multiplied by
the given Implementation Moment.
In other words, Virtual Present is the position of
a given in-work task’s present in the History of a
completed task. Equation (6) shows a Virtual
Present computed on a History H of a completed
task and for a given Implementation Moment IM of
an in-work task.
 =
(
0
)
×.
(6)
2.2 Methodology
The Work Behavior Prediction methodology is
presented in Figure 1 and described next.
The prediction process starts with the selection of
a project task to be the subject of prediction. This is
the target task in Figure 1.
The tasks are represented as Histories, as defined
in the previous subsection. This is why a time axis is
shown for each task in Figure 1.
The target task has a History, named Known
history in Figure 1. Based on this History, the target
Work Behavior (WB
target
) is computed.
As shown in Figure 1, completed tasks are used
in the prediction process. These tasks actually
represent a selection of completed tasks that have
their assignee in common with the target task. Their
histories characterize the behavior towards work of
their assignee, this being a good reason for using
their histories in the forecasting process.
For the target task, the Implementation Moment
IM is computed. By using IM, the Virtual Present is
computed for all the completed tasks selected for
prediction (by using the definition of Virtual Present
from the previous subsection, a VP is computed for
each completed task in Figure 1). This way, the
Histories of the completed tasks are split into two
parts, so that the History for a task contains a
History before the Virtual Present of that task, and a
History after this Virtual Present. In case the History
after the Virtual Present for a task contains no
element (this is a possibility), that task is ignored in
the prediction process.
For each History before VP in Figure 1, a Work
Behavior is computed resulting a WB
before
. In the
same time, for each History after VP in Figure 1, a
Work Behavior is computed resulting a WB
after
.
The WB
before
elements are than compared with
WB
target
producing a weight for each WB
after
element,
which will be further used in the prediction process.
The Work Behavior elements are compared by
using Euclidean distance, considering the Work
Behavior component metrics (ST, DV, and VL)
ICSOFT 2011 - 6th International Conference on Software and Data Technologies
48
Figure 1: Work Behavior Prediction methodology.
as dimensions. The closest WB
before
to WB
target
produces the biggest weight for its twin, WB
after
.
Next, the WB
after
elements are weighted and
combined for computing the predicted Work
Behavior (WB
predicted
in Figure 1). A weighted mean
is used in this process.
The Known history in Figure 1 is used along
with WB
predicted
to build a History structure that
corresponds to the predicted progress for the target
task (Predicted history in Figure 1).
Ideally, the Histories used in the forecasting
process should contain elements for equally
distanced moments in time. If this is not the case, an
extrapolation method on the existing data is used
beforehand.
3 FORECASTS EVALUATION
METHODOLOGY
This section presents the results of applying the
Work Behavior Prediction method on real-world
commercial software projects development data.
3.1 Competing Prediction Method
In this evaluation, the Work Behavior Prediction
competes with Velocity Trend prediction, which is
part of the Scrum management framework (Scrum
Alliance, 2007).
3.2 Data used in Evaluation
In the forecasts evaluation, data retrieved from the
development of two real-world software projects are
used. These projects are not related and were
developed by two different software development
companies.
We refer to these projects as project X and
project Y. Project X was developed by a project
team of 23 members, while project Y (smaller than
X), by a team of only 6 members. Further
information cannot be provided at the moment due
to confidentiality.
3.3 Metrics and Tools
We use several error metrics to assess the prediction
quality. These metrics, along with their strengths and
weaknesses are presented in (Zivelin, n.d.). In the
following equations, D represents an observation, F
is a forecast, and n is the number of (D, F) pairs.
The simplest metric is MFE (Mean Forecasting
Error). Equation (6) shows how this metric is
computed.
WORK BEHAVIOR PREDICTION DURING SOFTWARE PROJECTS DEVELOPMENT
49
 =
( − )
.
(6)
Another metric used in this evaluation is MAD
(Mean Absolute Deviation). Equation (7) shows how
this metric is computed.
 =
| − |
.
(7)
The third metric used in this evaluation is MAPE
(Mean Absolute Percentage Error). Equation (8)
shows how this metric is computed. Although
MAPE, also known as MMRE, is the most common
measurement of forecast accuracy, it has an
important weakness that is shown in (Foss, Stensrud,
Kitchenham, and Myrtveit, 2002).
 =
 − 

× 100.
(8)
The last metric used in this evaluation is
WMAPE (Weighted Mean Absolute Percentage
Error). Equation (9) shows how WMAPE is
computed.
 =
 − 

×

.
(9)
For analyzing the available project data, we
developed a software prototype of our Behavioral
Project Monitoring Framework. This software
prototype has a forecasting module, implementing
the Work Behavior Prediction method.
The project data is provided in the form of
Microsoft Project Plan files which are available on a
monthly basis for several months in the case of
project X, and on a weekly basis for several weeks
in the case of project Y.
The software prototype automatically computes
the four metrics for all the project tasks for which
data is available, so that an index i of D and F from
equations (6), (7), (8), and (9) refers to one task.
4 RESULTS AND DISCUSSION
The forecasts evaluation results are presented in
Table 1, for project X, and Table 2, for project Y.
Table 1 and Table 2 show the prediction time span,
which is measured in months, in the case of project
X, and weeks in the case of the smaller project Y.
The main reason for making predictions on such
time spans was that project development data is
available on a monthly-basis, in the case of project
X, and on a weekly-basis, in the case of project Y.
Consequently, forecasts at the end of the prediction
time span can be compared to existing information
regarding project progress.
The four metrics used in evaluation that were
presented in the previous section, are computed for
Velocity Trend prediction (VPT in Table 1 and
Table 2) and for our prediction method, Work
Behavior Prediction (WBP in Table 1 and Table 2).
A prediction method is considered better than the
other for a case if at least half plus one of the
available metric values are lower for the first method
(considering, of course, the metrics that are used for
this evaluation for which lower means better).
In Table 1 and Table 2, the cases in which our
prediction method (WBP) is better than Velocity
Trend prediction (VTP) are shaded.
Analyzing the results presented in Table 1 and
considering all the available 24 presented cases, our
prediction method (WBP) proves to be
systematically better than Scrum’s Velocity Trend
prediction (VTP). The 1 month prediction time span
shows the lowest differences between the two
prediction methods. Even so, in 7 of the 8 cases our
prediction method has a lower MFE, meaning that is
more “on target” than the competing Velocity Trend
method. The 2 month prediction time span shows
better results for our prediction method in 6 of the 9
cases. For 3 month time span prediction, according
to the metrics values, our prediction method is better
in 6 of the 7 cases. The results presented in Table 1
suggest that, for long term prediction, considering
the available information, our method is more
appropriate to be used for decision support than the
popular Velocity Trend prediction. For example, for
case 17 (Table 1), using Work Behavior Prediction,
the project manager knows two months ahead of
time where project tasks will be in terms of work
progress with an average absolute prediction error
per task of only 10 working days (see MAD for case
17 in Table 1) meaning 2 calendar weeks. Applying
Velocity Trend Prediction on the same data and for
the same time span, the average absolute error per
task is 35 working days, meaning one calendar
month and a half, which almost equals the prediction
time span.
Analyzing the results shown in Table 2 and
considering all the available 10 cases, we conclude
than our prediction method is better than Velocity
Trend prediction for project Y also. For 1 week
prediction time span, our method shows better
results in 3 of the 4 cases. For the other prediction
time spans (2, 3, and 4 weeks), our prediction
method is better in all the cases.
Just like for project X, the results for project Y,
which are presented in Table 2, suggest that, for long
ICSOFT 2011 - 6th International Conference on Software and Data Technologies
50
Table 1: Evaluation results for project X (VTP – Velocity Trend Prediction; WBP – Work Behaviour Prediction).
Prediction time
span
Case
no.
WMAPE MAPE MAD [days] MFE [days]
VTP WBP VTP WBP VTP WBP VTP WBP
1 month 1 0.579 1.149 3.003 25.000 8.530 16.936 7.579 -6.302
2 0.673 0.583 123.150 44.741 8.480 7.352 7.887 -3.229
3 0.665 0.276 44.117 40.149 5.425 2.249 1.312 -0.796
4 0.458 0.769 5.228 14.662 3.043 5.108 1.736 0.990
5 0.577 0.616 20.224 21.754 13.170 14.073 4.409 -5.245
6 0.683 0.692 27.281 25.658 11.560 11.711 8.635 -3.166
7 0.501 0.305 40.469 7.843 10.199 6.212 5.614 0.040
8 1.094 0.919 40.014 29.534 16.322 13.709 13.647 0.777
2 months 9 0.822 1.402 21.579 30.357 8.315 14.180 7.897 -1.670
10 3.350 1.146 94.713 97.422 12.462 4.264 12.026 2.087
11 1.669 1.026 10.881 7.491 6.964 4.282 3.180 1.079
12 1.512 1.180 10.281 6.799 6.864 5.358 2.064 2.242
13 0.752 1.047 25.561 26.972 13.892 19.357 7.562 -7.988
14 1.481 1.079 65.402 17.527 16.919 12.246 15.022 -1.330
15 2.345 1.563 7.584 9.833 19.276 12.845 18.667 7.138
16 0.673 0.873 42.902 56.699 24.956 32.393 -8.456 -30.890
17 10.932 2.928 521.888 170.305 34.393 9.211 34.393 7.843
3 months 18 9.714 5.027 84.660 25.755 12.993 6.723 12.993 6.323
19 - - - - 9.995 4.533 9.995 4.533
20 2.122 1.358 13.808 9.539 8.169 5.229 2.229 0.008
21 1.527 1.366 11.404 4.649 5.561 4.973 2.594 2.885
22 1.014 1.103 66.473 30.956 16.589 18.048 10.192 -7.120
23 4.971 2.231 6.492 5.106 23.575 10.583 23.575 3.268
24 0.903 0.800 14.429 15.622 17.103 15.152 7.837 -7.315
Table 2: Evaluation results for project Y (VTP – Velocity Trend Prediction; WBP – Work Behavior Prediction).
Prediction time
span
Case
no.
WMAPE MAPE MAD [days] MFE [days]
VTP WBP VTP WBP VTP WBP VTP WBP
1 week 1 0.333 0.083 33.333 12.500 0.750 0.188 -0.250 -0.188
2 0.250 0.000 25.000 0.000 0.750 0.000 -0.750 0.000
3 0.657 0.791 98.886 221.694 1.557 1.876 -1.107 -0.676
4 0.318 0.070 72.727 27.895 0.382 0.084 -0.382 -0.084
2 weeks 5 0.500 0.083 41.667 12.500 1.125 0.188 -0.875 -0.188
6 0.375 0.000 37.5 0.000 1.125 0.000 -1.125 0.000
7 0.393 0.382 63.750 127.323 0.412 0.401 -0.337 0.326
3 weeks 8 1.159 0.250 262.500 137.500 1.912 0.413 -0.587 0.413
9 0.625 0.000 62.500 0.000 1.875 0.000 -1.875 0.000
4 weeks 10 1.235 0.407 229.167 146.139 2.038 0.672 -0.962 0.153
term prediction, our method is more appropriate
to be used for decision support than the popular
Velocity Trend prediction. For example, for case 5
(Table 2), using Work Behavior Prediction, the
project manager knows two weeks ahead of time
where project tasks will be in terms of work progress
with an average absolute prediction error per task of
only 0.2 working days (see MAD for case 5 in Table
2) meaning less than 2 working hours, considering
that a full working day consists in 8 working hours.
Applying Velocity Trend Prediction on the same
data and for the same time span, the average
absolute error per task is 1.2 working days, meaning
almost 10 working hours.
Although we evaluated our prediction method,
Work Behavior Prediction, only on two real-world
software project development data, we believe the
results are valuable in the context in which such
project data is very hard to get, considering its
confidential nature. Even for those two projects,
according to Table 1 and Table 2, our method shows
an evident superiority to a very popular prediction
method, which is implemented by most ALM tools,
Velocity Trend prediction.
5 CONCLUSIONS AND FUTURE
WORK
In this paper, we have presented a prediction method
that we developed, named Work Behavior
WORK BEHAVIOR PREDICTION DURING SOFTWARE PROJECTS DEVELOPMENT
51
Prediction.
This method is evaluated against a set of error
metrics and the results are compared to those
obtained for a very popular prediction method,
Velocity Trend prediction. Real-world commercial
software projects development data are used in the
evaluation process.
As future work, we intend to enhance our
prediction method by using it for more real-world
software projects and by evaluating the obtained
results. Furthermore, we will analyze the
applicability of our prediction method for other
types of projects (e.g. construction projects).
ACKNOWLEDGEMENTS
This work was supported by QuarterMill
Technologies. This work was partially supported by
the strategic grant POSDRU 6/1.5/S/13, (2008) of
the Ministry of Labour, Family and Social
Protection, Romania, co-financed by the European
Social Fund – Investing in People.
REFERENCES
Boehm, B., Valerdi, R., Lane, J., and Brown, W. (2005).
COCOMO Suite Methodology and Evolution. In:
Crosstalk, Vol.18 i4, pp. 20-25.
CollabNet (n.d). CollabNet. Retrieved January 4, 2011
from http://www.open.collab.net.
Deemer, P. and Benefield, G. (2007). An Introduction to
Agile Project Management with Scrum. Retrieved
November 20, 2010 from http://www.rallydev.com/
documents/scrumprimer.pdf.
DeMarco, T. (2009). Software Engineering: An Idea
Whose Time Has Come and Gone? In IEEE Software.
Viewpoints, pp 94-95.
Foss, T., Stensrud, E., Kitchenham, B., Myrtveit, I. (2002).
A Simulation Study of the Model Evaluation Criterion
MMRE. Discussion paper. Norwegian School of
Management BI. ISSN: 0807-3406.
Gîrba, T. (2005). Modeling History to Understand
Software Evolution. PhD. thesis, University of Bern.
IBM (n.d). IBM Rational Team Concert. Retrieved
January 4, 2011 from http://www.ibm.com.
Project Management Institute (2008). A Guide to
theProject Management Body of Knowledge
(PMBOK® Guide) - Fourth Edition. Project
Management Institute, ISBN13:9781933890517.
Scrum Alliance (2007). Glossary of Terms. Retrieved
November 30, 2010 from http://www.scrumalliance.
org/articles/39-glossary-of-scrum-terms.
Stanciu, C., Tudor, D. and Creţu V.I. (2009). Towards an
adaptable large scale project execution monitoring. 5th
International Symposium on Applied Computational
Intelligence and Informatics, pp. 503 - 508, Romania.
Stanciu, C., Creţu, V.I. and Cireş-Marinescu, R. (2010).
Monitoring Framework for Large-Scale Software
Projects. Proceeding of the IEEE International Joint
Conferences on Computational Cybernetics and
Technical Informatics 2010, pp. 333-338, Timisoara,
Romania.
Stanciu, C., Tudor, D. and Creţu V.I. (2010). Towards
Modeling Large Scale Project Execution Monitoring:
Project Status Model. Proceedings: 5th International
Conference on Software and Data Technologies,
ICSOFT 2010, Athens, Greece, ISBN 978-989-8425-
22-5, Volume 1, pp. 36-41. Portugal: SciTePress.
Wysocki, R. K. (2010). Adaptive Project Framework:
Managing Complexity in the Face of Uncertainty.
Addison-Wesley Professional.
Zivelin, N. (n.d). Forecast Metrics and Evaluation. Oracle.
Retrieved on December 27, 2010 from
http://demantrasig.oaug.org.
ICSOFT 2011 - 6th International Conference on Software and Data Technologies
52