THE INFLUENCE ANALYSIS OF OPENING PROJECTS
ON PROJECT PERFORMANCE
Miao-Ling Wang, Jia-Ru Li
Department of Industrial Engineering and Management, Minghsin University of Science and Technology
1, Hsinhsin RD, Hsin-Chu County, Taiwan 304, ROC
Sheng-Hung Chang*
Department of Industrial Engineering and Management, Minghsin University of Science and Technology
1, Hsinhsin RD, Hsin-Chu County, Taiwan 304, ROC
Keywords: Open Projects, Bad Multi-Tasking, Multi-Project Environment, Throughput, Delivery Performance.
Abstract: Critical chain project management (CCPM), proposed by Goldratt (1997), has been proved to be very
prominent in overcoming the weaknesses of human nature in order to achieve a more effective project
management. Goldratt suggested that, in order to reduce the impact of bad multi-tasking on project delivery
in the multi-project environment, the density of open projects (BN Closeness) should be reduced at least to
75% and below the generally recognized load (Goldratt, 2006). On the other hand, to get better use of
resources in practice, the resource loading assignment tends to higher and evener. The above two viewpoints
are all considerably related to the use and allocation of project resources. However, both perspectives have
no support of actual data. In this study, we employ the @Risk for project simulation software for evaluation
and verification of the appropriate density of open projects. The research findings suggest, in general, the
density of open projects should be in the range of 75%~100% of the load in multi-project environments of
different risks.
1 RESEARCH BACKGROUND
AND MOTIVES
There are many factors of influence relating to
project delivery and throughput. For example,
number of open projects, resource workload, risk
degree of projects and time uncertainty, or the
evenness of resource allocation (Castro et al., 2008;
Herroelen and Leus, 2005). Dr. Goldratt (2006)
suggested that, profit-making goals rely not on the
number of projects to start but on how many projects
can be finished. When too many projects are open,
there will be pressure on resource. Therefore, more
tasks will be assigned to same resource, and thus
lengthen the delivery time of each project. He
proposed that the company has to reduce by at least
25% of open projects to avoid unnecessary delay in
project delivery.
On the other hand, Anavi-Isakow and Golany
(2003) proposed that, in the multi-project
environmental organization, it is very important to
allow projects to arrive into the system at
predetermined time intervals. The main purpose is to
prevent the great sum of waiting time resulting from
the concurrent arrival of a number of projects at the
system. However, the optimal value cannot be
accurately defined, as there is no accurate answer
from the simulation experiment. Adler et al. (1995)
proposed that an organization should take fewer
projects at one time. Dietrich and Lehtonen (2005)
investigated methods applied to the management of
development projects by 288 organizations, and
concluded that the number of projects is not the
successful factor for the multi-project management.
In addition, time uncertainty is also one of the
factors affecting the delay of project. Cates and
Mollaghasemi (2007) indicated that there are many
project-related uncertain factors including the
estimation of activity time or unexpected accident as
well as the use of key resources. Moreover, such
impact would cause project delay and reduce the
interests of stakeholders.
401
Wang M., Li J. and Chang S..
THE INFLUENCE ANALYSIS OF OPENING PROJECTS ON PROJECT PERFORMANCE.
DOI: 10.5220/0003570504010404
In Proceedings of 1st International Conference on Simulation and Modeling Methodologies, Technologies and Applications (SIMULTECH-2011), pages
401-404
ISBN: 978-989-8425-78-2
Copyright
c
2011 SCITEPRESS (Science and Technology Publications, Lda.)
However, it is not sure whether reduced number
of open projects can shorten project time or not and
how the application of resource loading impacts on
project throughput. This study is going to make
situational simulation analysis of the above topics to
discuss the number of open projects on 6 delivery
time-related performance indicators as the
verification targets in the following sections.
2 DEVELOPMENT OF
SIMULATION MODEL
The number of open projects as described in this
study refers to the number of projects that have been
started at any given time after planned scheduling in
a multi-project environment. The “Bottleneck (BN)”
refers to the resources of average load and other
resources within 10% of the maximum load among
all the projects. The rest resources are termed as
“Non-Bottleneck (NBN)”. “Bottleneck closeness”,
denoting as “BN Closeness”, means the closeness
between the bottleneck duration and the bottleneck
duration of the last project. Note that, the density of
open projects in this study is equivalent to
bottleneck closeness.
The resources of the projects are seven shared
ones. The project network structure is designed by
Anavi-Isakow and Golany (2003) as shown in
Figure 1. With the three types of projects as the
priorities of the multi-project scheduling, we repeat
the scheduling processes for three years. Then, the
scheduling time of project opening is planned based
on bottleneck closeness at 100% and non-bottleneck
workload at 70% as the basis. The average duration
of various resources are determined by β distribution
with 50% work completion probability, the
preliminary scheduling throughput can be obtained
as illustrated in Table 1.
This study designs the transformed risk degree of
project proposed by Shou et al. (2000) as illustrated
in Table 2. The estimated task time used in this
study is computed according to different risk degrees
and β distribution.
The number of projects can affect the overall
operation of the enterprises and will result in bad
multi-tasking of resources. Goldratt (2006) proposed
that the density of open projects (BN closeness)
should be limited below 75% of the original number
of projects to reduce bad multi-tasking situations. In
this way, the delivery time of all projects can be
shortened. Suppose each project has only one task
without considering the bottlenecks, the working
duration for each bottleneck is 10 days and the total
working time is 60 days. Therefore, 100% of BN
closeness indicates that the bottlenecks of all the
projects in the multi-project scheduling are closely
connected. Thus, the number of open projects is 6; if
BN closeness is reduced to 50%, the number of open
projects will be 3. To find the most appropriate BN
closeness, this experiment sets the levels of BN
closeness from 50% to 200% to test the impact of
number of open projects on the project throughput
rate.
Start
Start
Start
En
d
End
End
Type 1
Type 2
Type 3
1/10 2/10
#/##: resource No. #/duration ##
3/15
3/10
3/10
1/15
1/10
2/10
2/15
4/10
4/15
4/10
5/10
5/15
5/15
6/10
6/10
6/15
7/15
7/20
7/15
Figure 1: Multi-project network.
Table 1: The Expected Throughputs.
BN closeness(%)
50 60 70 75 80 90 100 125 150 175 200
Expected throughputs 17 19 21 24 25 27 34 41 45 54 61
SIMULTECH 2011 - 1st International Conference on Simulation and Modeling Methodologies, Technologies and
Applications
402
Table 2: Transformed risk degree of project.
project degree
of risk
Probabilit
y
error ran
g
e
Low
b
oun
d
High bound
low -5% +20%
medium -12.5% +35%
hi
g
h -20% +50%
3 ANALYSIS OF THE
APPROPRIATE BN
CLOSENESS
The performance evaluation of the experimental
simulation results are summarized as follows:
Throughput: representing the total throughput
of the all the completed projects during the
simulation period. As shown in Figure 2; when
the BN closeness rises at 75%, the project
throughput starts to rise considerably while it
significantly drops when the BN closeness is at
100%. In case of BN closeness at 100% and
low risks, the project throughputs (26) are
optimal, indicating that the throughputs are not
as high as expected (34) to fulfil our original
commitments. In general, in case of different
risk degrees, the BN closeness should be
controlled within 75%~100% to get the most
appropriate results.
Delivery rate: representing the responsiveness
to meet the delivery time as designated by
customers. According to Figure 3 that the
delivery rate in case of different risks is better
when the BN closeness is lower than 75%,
indicating that the delivery responsiveness is
very poor when the BN closeness is higher than
75%.
Complete rate: representing the percentage of
completed projects in a multi-project
environment. As shown in Figure 4, in case of
different risks, the throughput rate will decrease
along with increasing BN closeness. When the
BN closeness accounting for more than 75%,
the complete rate declines, and the expected
number of completed projects will be
decreasing.
Mean tardiness: tardiness refers to the delay
between the project completion time and
delivery time. The average value of the
tardiness of all projects is termed as the mean
tardiness. According to Figure 5, the mean
tardiness will rise along with increasing BN
closeness. In particular, the mean tardiness
starts to rise considerably when the BN
closeness accounting for more than 100%. This
indicates the project completion time cannot
satisfy demands on delivery accuracy and
become more serious when the BN closeness
accounting for more than 100%
Mean lateness: lateness refers to the period that
the project completion time later than the due
delivery time. As seen in Figure 6 the mean
lateness time in case of different risks will rise
along with increasingly higher BN closeness.
And it becomes more and more serious when
the BN closeness accounting for more than
100% while it has no significant different when
the BN closeness accounting for less than 75%.
Mean time in process: the equivalent of Time in
Process (TIP), namely, the time from project
opening to completion. As illustrated in Figure
7 mean TIP will rise along with rising BN
closeness. Higher BN closeness will result in
more serious bad multi-tasking and more
delivery delays of projects. However, it has no
significant difference when the BN closeness
accounting for less than 75%.
0.0
5.0
10.0
15.0
20.0
25.0
30.0
50%
60%
70%
80%
90%
100%
110%
120%
130%
140%
150%
160%
170%
180%
190%
200%
Throughputs
BN Closeness
Low risk
Medium risk
High risk
Figure 2: Project throughputs in case of different risk
degrees and BN closeness.
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
50%
60%
70%
80%
90%
100%
110%
120%
130%
140%
150%
160%
170%
180%
190%
200%
BN Closeness
Delivery Ra te (%)
Low risk
Medium risk
High risk
Figure 3: Delivery rate of BN closeness in case of
different risk degrees.
THE INFLUENCE ANALYSIS OF OPENING PROJECTS ON PROJECT PERFORMANCE
403
0
20
40
60
80
100
120
50%
60%
70%
80%
90%
100%
110%
120%
130%
140%
150%
160%
170%
180%
190%
200%
Complete Rate
(%)
BN Closeness
Low risk
Medium ris
k
High risk
Figure 4: Complete rate of BN closeness in case of
different risks.
-50.0
0.0
50.0
100.0
150.0
200.0
250.0
300.0
50%
60%
70%
80%
90%
100%
110%
120%
130%
140%
150%
160%
170%
180%
190%
200%
Mean Tardiness
(da ys)
BN Closeness
Low risk
Medium risk
High risk
Figure 5: Mean tardiness of BN closeness in case of
different risk degrees.
0.0
50.0
100.0
150.0
200.0
250.0
300.0
50%
60%
70%
80%
90%
100%
110%
120%
130%
140%
150%
160%
170%
180%
190%
200%
Mean Lateness
(da ys)
BN Closeness
Low risk
Medium risk
High risk
Figure 6: Mean lateness of BN closeness in case of
different risk degrees.
0
50
100
150
200
250
300
350
50%
60%
70%
80%
90%
100%
110%
120%
130%
140%
150%
160%
170%
180%
190%
200%
Mean TIP
(days)
BN Closeness
Low risk
Medium risk
High risk
Figure 7: Mean TIP of BN closeness in case of different
risk degrees.
4 CONCLUSIONS
The main purpose of this study is to get the most
appropriate degrees of BN closeness in uncertain
environment and verify the viewpoints of Dr.
Goldratt according to the experimental results. In
case of various risks, the setting of BN closeness at
75%~100% can result in better performance in terms
of the throughput, complete rate, delivery rate, mean
tardiness and mean lateness in the multi-project
environment. On the contrary, when increasing BN
closeness, the mean tardiness, mean lateness and
duration will increase.
ACKNOWLEDGEMENTS
The authors would like to thank the National
Science Council of the Republic of China for
financially supporting this research under Contract
NSC 99-2221-E-159-007.
REFERENCES
Adler, P. S., Mandelbaum, A., Nguyen, V. & Schwerer, E.,
1995, From project to process management: An
empirically-based framework for analyzing product
development time, Management Science, 41(3), 458.
Anavi-Isakow, S. & Golany, B., 2003, Managing multi-
project environments through constant work-in-
process, International Journal of Project Management,
21(1), 9-18.
Castro, J., Gómez, D. & Tejada, J., 2008, A rule for slack
allocation proportional to the duration in a PERT
network, European Journal of Operational Research,
187(2), 556-570.
Cates, G. R. & Mollaghasemi, M., 2007, The project
assessment by simulation technique, Engineering
Management Journal, December(1), 3-10.
Dietrich, P. & Lehtonen, P., 2005, Successful management
of strategic intentions through project - Reflections
from empirical study, International Journal of Project
Management, 23(5), 386-391.
Goldratt, E. M., 1997. Critical Chain . North-River Press.
Goldartt, E. M., 2006, The Strategy & Tactic Tree for
Projects.
Herroelen, W. & Leus, R., 2005, Project scheduling under
uncertainty: Survey and research potentials, European
Journal of Operational Research, 165(2), 289-306.
Shou, Y. & Yao, K. T., 2000, Estimation of project buffers
in critical chain project management, in Proceedings
of the 2000 IEEE International Conference on
Management of Innovation and Technology -- ICMIT
2000, 1(1), 162-167.
SIMULTECH 2011 - 1st International Conference on Simulation and Modeling Methodologies, Technologies and
Applications
404