
metal  feed  to  the  BOF  is  synchronous  and  without 
wait. Also, timely arrival of hot metal from the iron-
making-unit needs to be ensured. 
In  the  steel-melting-shop  unit,  the  liquid  steel 
from the BOF is taken to the Caster where the liquid 
steel  is  molded  via  secondary  refining  units 
comprising of Ladle Refining Furnace (LRF) and/or 
Vacuum Degassing (VD) units. The BOF should be 
synchronized  with  the  Casters  such  that  the  heat 
sequences for different grades are  maintained while 
maximizing  the  utilization  of  the  equipment  to 
ensure  the  highest  throughput  from  hot-metal 
charging  to  casting.  It  is  always  preferred  to  have 
uninterrupted sequence during continuous casting to 
achieve higher production and yield. 
Our study was based on an integrated steel plant 
having  two  BOFs,  with  one  working  and  one 
standby  mode,  one  LRF,  one  Vacuum  Degassing 
unit and one three-strand Caster (operated with two 
strands).  The  existing  operations  needed  to  be 
studied  and  analyzed  in  detail  and  additional 
facilities/ improvements  in the system needed  to  be 
proposed  to  utilize  the  Caster,  LRF  and  BOF  fully 
and thereby increasing the overall throughput of the 
system. It was also needed to suggest the number of 
hot metal ladles and steel ladles in active circulation 
required for the suggested production. 
2  THE PROCESS AND 
OPERATIONS 
Hot metal in the Blast Furnace (BF) is cast as per BF 
cast schedule into open top ladles placed in transfer 
cars  on  railway  tracks.  The  ladle  transfer  car  is 
carried to  SMS  or PIG  Casting Machine (PCM) by 
captive  locomotive  depending  on  the  readiness  of 
the converter to accept the hot metal.  
At  SMS  the  full  ladle  is  picked  up  from  the 
transfer car by an overhead crane and carried to the 
sampling point.  In  case  an  empty ladle  is  ready  for 
return to BF, the full ladle is picked and kept on the 
pit,  the  empty  ladle  placed  on  the  transfer  car  and 
then the full ladle is picked up again by the overhead 
crane.  Once  the  sampling  is  complete,  the  ladle  is 
carried  to  the  BOF.  In  the  mean  time  scrap  is 
charged  to  the  BOF  by  scrap  charging  crane.  On 
completion, the hot metal is charged to the BOF and 
blowing  starts.  Near  the  end  of  the  blowing  cycle, 
temperature  is  measured  and  samples  are  taken  for 
analysis. After pouring of the hot metal to the BOF, 
the ladle  is carried  to the pit  by overhead crane  for 
sending back to the BF. 
Steel  ladle  on  steel  transfer  car  gets  under  the 
BOF vessel and steel is tapped into the ladle through 
the tap hole. Once tapping is complete, slag pot car 
gets  under  the  BOF  vessel  and  slag  is  poured  into 
the slag pot through the BOF vessel mouth.  
After  processing  of  8  heats  in  the  BOF, 
maintenance  operations,  also  known  as  dozing  and 
mouth jam cleaning are carried out. After 15 heats of 
BOF  operation  the  maintenance  operation  of  tap 
hole  changing  is  performed.  And  after  75  heats, 
other  maintenance  works  on  the  vessel  are  carried 
out. The numbers are varied depending on the status 
and completion of the casting sequence. 
After  tapping  of  steel  into  the  steel  ladle,  it  is 
transported  to  the  ladle  refining  aisle  by  the  ladle 
transfer car, picked up by overhead crane and placed 
on the LRF transfer car. The purging lines are fixed 
and  the  transfer  car  goes  into  the  LRF.  The  steel is 
further  refined  in  the  LRF  by  adding  alloying 
materials  to  give  it  special  properties  as  required. 
Once  the  LRF  processing  is  complete,  the  ladle 
transfer car brings out the ladle and the purging lines 
are removed. The ladle is also moved to the VD unit 
by overhead crane, and further treatment done.  
The ladle is transported to the caster turret from 
the LRF or VD by overhead cranes. The ladle sits in 
a rotating turret at the casting machine. One ladle is 
in  the  'on-cast'  position  (feeding  the  casting 
machine) while the other is made ready in the 'off-
cast' position, and is switched to the casting position 
when  the  previous  ladle  is  empty.  Once  casting  of 
one  ladle  is  over,  and  the  turret  rotates,  the  empty 
ladle  is  transported  from  the  turret  to  the  slag 
dumping  area  and  slag  is  dumped.  After  slag 
dumping, the ladles are sent to the ladle preparation 
area and placed back on the transfer car for the next 
tapping from the BOF. 
3  OVERALL THROUGHPUT 
IMPROVEMENT 
The  process of  steelmaking  and casting,  from BOF 
to  Caster,  may  be  categorized  into  three  distinct 
stages,  viz.  primary  steelmaking,  secondary 
steelmaking  and  casting.  Primary  steelmaking  is 
concerned with the production of liquid steel, which 
is  subsequently  refined  in  terms  of  both  its 
composition  and  its  cleanliness  through  a  host  of 
secondary steelmaking processes. Molten steel with 
desired composition,  cleanliness  and  temperature is 
finally  transformed  into  solid  products  through 
continuous casting. Figure 2 shows the categories of 
the steelmaking process. 
SIMULTECH2015-5thInternationalConferenceonSimulationandModelingMethodologies,Technologiesand
Applications
112