3 UTILISATION OF THE
APPROACH
The application of our approach can be structured
into four phases. During the first phase, as-is models
of service provider’s business processes are
generated. For this purpose, a business framework
should be used. Moreover, existing contracts of the
company have to be investigated as they determinate
the as-is situation. Based on the framework and on
the exiting contracts, as-is business processes can be
identified and documented. In Phase 2, an analysis
of the business process models takes place with
special attention to customer activities. In this phase,
business process designers are supported by means
of the central questions catalogue which has been
developed. By answering these questions, process
designers are effectively assisted in identifying
strengths and weaknesses in their customer
processes. Based on both, the answers to the central
questions and the created as-is models, to-be models
can be created, that allow for higher levels of
customer-integration in each area of activity in phase
3. The to-be models are on the one hand the
foundation of the final implementation phase,
because they represent the requirements definition of
business processes to be implemented in the
information systems. On the other hand, they can be
used for the contract negotiation and design between
the service provider and customer.
Our method for customer integration has been
applied at a medium-sized IT service provider which
offers broad IT infrastructure support for its
customers on such areas as acquisition, installation
and maintenance of hard and software, configuration
of networks, and IT consulting in general. For the
most part, the customers (currently 550) are tax
consultancies, solicitors, management consultancies,
wholesaler, and retailer. The customer integration
management method has been applied with regard to
the procedure model.
Phase 1: As-is modelling: Initially, a business
process framework for the as-is service processes
has been developed. The IT service provider under
consideration exhibits seven core processes and
eight support processes that are embodied in value
chains. Each value chain consists of several
subordinated value chains that in turn comprise
detailed process models. In the following, we focus
on the processes ‘Project preparation’ and ‘Project
performance’ of the IT service provider which are
subordinated processes of the core process ‘project
business’.
Phase 2: Customer activities analysis: For the
analysis of the as-is models, the central questions
catalogue was applied. Thus, the level of customer
integration in each process business model is
analysed.
• Answering, for example, the central question
‘Which activities in the performance creation
process are adopted by the customer?’ (see row
‘customer activities’ in Table 1) reveals for the
as-is model of the ‘Project performance’, that
customers are nor explicitly informed about
preparations they have to make (e. g. provisions
of rooms, availability of necessary staff
members, access to information systems) in
order to ensure a frictionless service
performance. Moreover, customers are not
regularly informed about the current project
status and upcoming project milestones.
• Answering the central question ‘Which aspects
of support activities should be visible to
customers?’ exposes for the ‘Project preparation
process’, that no customer integration in the
support area has taken place during the
preparation phase of outsourcing projects. Thus,
customers had no opportunity to follow or
participate in the process.
Phase 3: To-be modelling and contract
formulation: The analysis of the as-is models
resulted in a variety of requirements with respect to
a higher level of customer integration in each area of
activity.
• Requirements formulated for the ‘Project
performance process’ were, for example, that
necessary customer preparations are explicitly
communicated by the IT service provider. In
return, the customer ensures their observance.
Within the to-be model the two additional
functions ‘Transfer customer preparations’ and
‘Make preparation’ were introduced in the front-
office and customer area. The according
paragraphs have been assigned to the process
functions. Paragraph 3.2 of the IT outsourcing
contract comprises, for example, that the service
provider has to inform the customer about the
above-mentioned preparations two weeks in
advance. Moreover, the customer has to be
reminded one day before the on-site appointment
takes place. Additional process design
recommendations can be found in several new
functions and events (e. g. ‘Send delivery delay
notice’, ‘Check observance of project plan’, and
‘Post-processing of appointment’).
• Requirements exposed for the ‘Project
preparation process’ were, for example, that
important information for the customer should be
ICEIS 2005 - INFORMATION SYSTEMS ANALYSIS AND SPECIFICATION
264