2 RELATED METHODOLOGY
AND RESEARCH
Dynamic lot-sizing can be referred back to Wagner
and Whitin (1958), and diverse lot-sizing heuristics
have been adopted in many operations management
works.
For example, Teunter, Bayindir and Van Den
Heuvel (2006) studied the dynamic lot sizing
problem for systems with product returns and
remanufacturing, and proposed modifications of the
Silver Meal (SM), least unit cost and part period
balancing heuristics.
Decision makers may want to optimize two or
more objectives simultaneously under various
constraints, and a MOP can then be applied.
A
complete optimal solution seldom exists, and a
Pareto-optimal solution is used then (Wee et al.,
2009).
There are a few methods to derive a
compromise solution (Rosenthal, 1985). For example,
the weighting method assigns priorities to the
objectives and sets aspiration levels for the
objectives. The
-constraint method is a modified
weight method.
One of the objective functions is
optimized while the other objective functions are
incorporated in the constraint part of the model.
GA, a heuristic search process for optimization,
was first developed by Holland (1975). Based on
Darwin’s survival of the fittest principle, GA mimics
the process of natural selection (Maiti et al., 2006). It
has been widely applied to solve production and
operations management problems (Aytug et al.,
2003). The fundamental concept of GA is to code the
decision variables of the problem as a finite length
array, which is called chromosome, and to calculate
the fitness, the objective function, of each string
(Yang, Chan and Kumar, 2012).
3 PROBLEM DESCRIPTION AND
ASSUMPTIONS
The following assumptions and notations are defined
with the modification of those used in the models of
Kang (2008) and Kang and Lee (2010). The
assumptions are summarized as follows:
• The demand of each period is independent and
follows a normal distribution with a constant
coefficient of variation (
).
• At most one order can be placed from each
supplier in each period.
• The replenishment lead time is of known
duration, and the entire order quantity is delivered at
once in the beginning of a period.
• All-units discount schedule is considered. The
price of each unit is dependent on the order quantity.
• The inventory holding cost for each unit is
known and constant, independent of the price of
each unit.
• Planning horizon is finite and known. There are T
periods in the planning horizon, and the duration of
each period is the same.
• The expected ending inventory level in period t
(i.e., the expected beginning inventory level in
period t+1) is the safety stock level in period t.
• The initial inventory level (X
1
) is zero.
All the required notations in this paper are defined
below.
Notations
Indices:
i Supplier (i = 1,2,…, I ).
k Price break (k = 1,2,…, K ).
t Planning period (t = 1,2,…, T ).
v Integer number for calculating the quantity
purchased (v= 1,2,…, V ).
w Integer number for calculating the time
transported (w= 1,2,…, W ).
Parameters:
E(d
t
) Expected demand in period t.
ˆ
t
Standard deviation of demand in period t.
t
Pool standard deviation of demand in period t.
h Inventory holding cost, per unit per period.
r
i
Transportation cost per time from supplier i.
s Shortage cost, per unit per period.
z
Standard normal value of service level α.
()Lz
Standardized number of units short with
service level α.
M A large number.
o
i
Ordering cost per replenishment from supplier
i.
p
ik
Unit purchase cost from supplier i with price
break k.
q
ik
The upper bound quantity of supplier i with
price break k.
Decision variables:
()
it
PQ Purchase cost for one unit based on the
discount schedule of supplier
i with order quantity
it
Q in period t.
it
Q Purchase quantity from supplier i in period t.
AnIntegratedReplemishmentModelunderDynamicDemandConditions
615