variables needed in this case are:
|
|
|
|
|
|
|
|
|
|
1).
Based on the method provided in this paper, only
|
|
|
|
new variables should be added.
Therefore, the approach provided in this paper
reduces the number of variables by 1
1
|
|
|
|
|
|
1
100%. To illustrate this
benefit, assume that the projects fall into 3
categories (CAT=3), and the last project considered
in this planning horizon is planned to start at time
T=6, and at most 10 projects are available for any of
the categories. In this not so large example, the
number of new variables needed for modeling this
problem is 1
1
10361
100% =
99.44% less than the Glover method.
5 A NUMERICAL EXAMPLE
To illustrate how this method and algorithm works, a
pool of projects was generated. This pool contained
30 projects, each consuming 5 different types of
resources. Each of these 30 projects was randomly
assigned to one of three categories. The attributes of
the learning curve have been summarized in Table 1.
The availability of resource types 1 through 5 were
assumed to be 5, 7, 4, 6, and 5 units respectively.
The summary of the procedure to find the
optimum solution is provided in Table 2. In this
table, the ObjFunc column contains the value of the
objective function with the incentive, and the
MainObj column contains the objective function
value of the main problem. The optimal solution is
found after 4 iterations. The solution is proven to be
optimal because the upper bound and the lower
bound (feasible solution) of the main objective
function have converged and are equal. The operator
of this model could’ve stopped the model at step 3
since the gap between the upper bound and the lower
bound is at most 0.5%.
Step 5 has been added to illustrate the change in
the nature of the problem when the penalty factor is
too high. In this case, the number of projects
selected is big, but they are not the most profitable
set of projects. They are the projects which together
consume the most resources.
6 CONCLUSIONS
A model was introduced to deal with the project
selection problem when cost interdependencies
among projects exist. A new method to linearize the
quadratic constraints of this problem was introduced.
And based on this method an algorithm is offered to
solve the problem. It is shown that this method
reduces the number of variables in the linearization
procedure compared to previous works in this area
which is based on the Glover’s method.
This research has had contributions in both
modeling and methodology. However, there are
several different avenues for future work. In the
modeling part, other types of interdependencies can
be added to build a more comprehensive model.
Also, the assumption of certainty which is implied in
this model can be relaxed and a model which
considers the probable variations in costs can be
developed. As for the methodology, this method of
linearization can be applied to other problems.
REFERENCES
Anzanello, M. J. and Fogliatto, F. S. (2011). Learning
curve models and applications: Literature review and
research directions. International Journal of Industrial
Ergonomics, 573-483.
Bhattacharyya, R., Kumar, P. and Kar, S. (2011). Fuzzy
R&D portfolio selection of interdependent projects.
Computers & Mathematics with Applications, 3857-
3870.
Carazo, A. F., Gomez, T., Molina, J., Hernandez-Diaz, A.,
Guerrero, F. and Caballero, R. (2010). Solving a
Comperehensive model for Multi-Objective Project
Selection . Computers and Operational Research,
630-639.
Glover, F. and Woolsey, E. (1974). Converting the 0–1
polynomial programming problem to a 0–1 linear
problem. Operations Research, 180-182.
Iniestra, J. G. and Gutierrez, J. G. (2009). Multicriteria
decisions on interdeendent infrastructure
transportation projects using an evolutionary-based
framework. Applied Soft Computing, 512-526.
Killen, C. P. and Kjaer, C. (2012). Understanding project
interdependencies: The role of visual representation,
culture and process. International Journal of Project
Management, 554-566.
Lee, J. W. and Kim, S. H. (2000). Using analytical
network process and goal programming for
interdependent information system project selection.
Computers & Operations Research, 367-382.
Liesio, J., Mild, P. and Salo, A. (2008). Robust portfolio
modeling with incomplete cost information and
project interdependencies. European Journal of
Operaional Research, 679-695.
Liu, S.-S. and Wang, C.-J. (2011). Optimizing project
selection and scheduling problems with time-
dependent resource constraints. Automation in
Construction, 1110-1119.
ICORES2013-InternationalConferenceonOperationsResearchandEnterpriseSystems
86