In theory, when CSR level is adjusted from low
to high, the reactive capacity increases and the
voltage decreases, vice verse. Three dimensional
scattering projection diagram 5 is derived from 340
sets of statistic data. This figure reflects the
occurrence number of some certain voltage
difference caused by the change of capacity.
4.1 Main Impact on Voltage
When the operating capacity of CSR decreases, most
of the voltage increases although the amplitude are
generally small. Nearly 90% of the voltage
differences are concentrated between 1kV and 6kV.
Voltage differences reach to 10kV or 20kV also
occurred, but most are 2kV. When the operating
capacity increases,most of the voltage decreases.
Nearly 90% of the voltage drops are concentrated
between 1kV and 6kV. Voltage drops reach to 10kV
also occurred, but most are 2kV as well. From above,
CSR with total capacity of 300Mvar, switching at
75Mvar of each level, do not significantly affects the
voltage of 750kV bus, as amplitude of variation
always within 1%, tending to nominal value.
Through the analysis of the data, putting the CSR
into operation and its frequent switching won’t
influence the operation of 750kV equipment.
4.2 Analysis of Special Circumstances
As stated, after the switching of CSR, some voltage
differences are not within 6kV. Two main classes,
one is the amplitude of variation bigger than 6kV.
For example, within the 340 sets of data, voltage
differences (increase) reach to 20kV appeared twice,
12kV appeared twice. Voltage differences (decrease)
reach to 9kV appeared once, 8kV appeared once.
Although they conform to the theory but are
different from normal situation. Another is when the
operating capacity increases, bus voltage also
increases and when the operating capacity decreases,
bus voltage also decreases, opposite to the theory, as
shown in Figure 5 within red circles.
In the first situation, increasing 20kV for
example, referring to the nearby switching actions
and corresponding weather information, wind speed
changed rapidly at that time so the grid connection
capacity of wind power is bigger. At 14:29,
31/03/2012, the operation capacity of CSR dropped
from 100% to75%, causing voltage increase from
756kV to 758kV, 2kV increment. Then at 14:38,
31/03/2012, the operation capacity dropped from
75% to 50%, causing voltage increase from 758kV
to 778kV, 20kV increment. This phenomenon
appears many times within small period furing 340
sets of data, and always accompanied with large
amplitude of voltage variation. This phenomenon
indicates that the primary causes of large amplitude
of voltage variation after CSR put into operation are
the big variation of grid connection capacity of wind
power and lacking of CSR switching capacity within
one operation time. Introducing short term wind
power predicting outcomes into control logic of CSR
is a promising method to solve this problem.
In the second situation, the variation of voltage
goes against the theory. Firstly, because all the data
were recorded manually, so man-made faults won’t
be eliminated. What’s more, another possibility is if
wind power changes quite fast, bus voltage
fluctuated frequently, so during a small period the
voltage increments or decrements caused by the
wind power grid connection is bigger than the
voltage decrements or increments caused by the
switching of the CSR, so the variation of voltage
goes against the theory.
5 CONCLUSIONS
CSR is the effective means in solving voltage and
reactive power problems of the power grid caused
by the large scale wind power integration. This
thesis combines with the actual operation states of
300Mvar stepped CSR in Dunhuang 750kV
substation of China, analyzed its operating
characteristics, summarized the impact of switching
actions on bus, the conclusion is as follows:
(1) 300Mvar CSR is sufficient in solving the voltage
and reactive power fluctuation problems of the
power grid of Dunhuang.
(2) The switching times of CSR is relatively high
during the period when wind power fluctuates
frequently. It is suggest that maintenance
between January and March and strengthened
inspection of equipment between May and July
be arranged.
(3) The thyristor switching of 50% and 75%
capacity act relative frequently and 25% capacity
is always put into operation, so they all should be
treated as emphasis during the maintenance.
(4) After putting the CSR into operation, the
variation of bus voltage is limited nearly within
the acceptable range. That means CSR don’t
have large impact on bus voltage.
(5) As wind power changes with large amplitude and
frequently, large amplitude of voltage variation
after the variation of CSR capacity may
occurred. Introducing short term wind power
SMARTGREENS2013-2ndInternationalConferenceonSmartGridsandGreenITSystems
108