against collection and sharing of construction data as
projects have become larger and more complex, with
greater work scope and increased need for
collaboration between stakeholders including clients,
designers, builders and subcontractors.
As such, this research aims to propose an
operating process for construction VR for collection
and sharing of construction data during the
construction phase. This process first reviews the
project information and designs, and on that basis
establishes a construction plan that can enhance
work efficiency through identification of
information such as work sequencing errors, planned
vs. actual progress and construction risks using 3D
visual simulation applied to existing business
workflows. In particular, this process allows for data
extraction by sequence for expedited identification
of and response to issues analyzed.
The work sequence review simulation can
demonstrate hundreds of activities and their
predecessor/successor relationships to visually
identify errors in work sequencing. The module first
generates a WBS (Work Breakdown Structure), 3D
model and schedule based on the project design, and
integrates them around the WBS.
In this research, we have developed an
automated module of our own for generation and
combined simulation of the WBS, 3D model and
schedule in order to increase usability and
efficiency. 3D and 4D objects can be simulated by
WBS level in this module. It would be helpful for
project managers to visualize project schedule by
work unit. Predecessor and successor relationships
by process can be determined using mouse controls
and the relationship entry module. Then the
activities were executed as simulations that not only
represented each process but also integrated the
overall schedule. By identifying the sequencing
errors in advance and re-adjusting the predecessor
and successor activities for each process
accordingly, the process can prevent abortive works.
The VR functions for current BIM systems are
focused on the simple simulation of finished
appearance by construction schedule. This study
suggests a VR function for visualizing construction
risk by construction schedule. Construction risk
means the risk in constructability of each activity.
VR function in the system represents different colors
of 3D object of each activity by risk level.
2.2 Application of Fuzzy Theory for
Quantifying Construction Risk
Construction risk information of each activity can be
visualized using Fuzzy analysis in the 4D CAD
system. Each activity has a risk degree that is
represented by different color. This study classifies
risk degree with 5 groups and each group has a color
from red color to blue color. Fig 1 shows 4D objects
that simulate the finished work by each risk degree.
Figure 1: Risk identification by Fuzzy analysis.
The fuzzy theory is used to obtain an objective
data from substantial and experienced data of risk
degree of each activity by field engineers. If a
finished activity simulates with red color in 4D
simulation system, project manager should monitor
the activity carefully because the activity has high
risk degree. In this 4D CAD system, all activities are
simulated with each color of 5 colors by each risk
degree that was analyzed using Fuzzy theory. Fuzzy
theory is used for verifying the subjective risk
degree with quantitative data.
The risk of each activity is analyzed by
multiplying risk probability to risk intensity. Project
manager should input those data for analyzing risk.
The developed 4D system in the study has a risk
analysis function using Fuzzy theory.
If project managers use this system, they can take
an intensive management plan for the activities with
risk degree of high level. And they can easily
identify those activities because the activities are
simulated in 4D CAD system with different color
such as red color or green color.
2.3 Visualization of Risk Information
for Construction Project
Fig. 2 shows a VR function for visualizing
construction risk analysis developed in this study.
The construction risk analysis module reviews
various internal and external risks on construction in
order to mitigate them in advance. To achieve this,
the module measured risk levels through Fuzzy and
risk analysis techniques, and simulated those risks
ICEIS2013-15thInternationalConferenceonEnterpriseInformationSystems
330