Simulation and Model Sensitivity Analisys of a Wind Turbine Tower
Manufacturing Plant
Paulo Tomé
2
, Eduardo Teixeira
1
, Freddy Assunção
1
, Luís Marques
1
,
João C. P. Reis
2
and João M. C. Sousa
2
1
TEGOPI - Industria Metalomecânica, S.A., Vilar do Paraíso, Portugal
2
LAETA, IDMEC, Instituto Superior Técnico, Universidade de Lisboa, Lisboa, Portugal
Keywords: Wind Turbine, Manufacturing, Industrial Process.
Abstract: A modelling method for a complex wind turbine tower manufacturing plant is proposed, through the
specification of the major assumptions in the model. Using this methodology a DES model was developed,
and a sensitivity analysis to some of the main process variables accounted for in the model is presented.
From this study several versions of the model were developed, and their results are compared against real
data from a manufacturing company.
1 INTRODUCTION
With early applications for water pumping and
milling, the use of wind energy dates back to the 2nd
century B.C. (Brito, 2014) with the first wind mills.
In recent years, having developed greatly trough the
70’s as consequence of the oil crisis (Hemami,
2012), wind energy plays an important role in
today’s society. In Portugal, according to REN
(Redes Energéticas Nacionais, 2013), at the end of
2012 almost 23% of the connected power was
obtained using wind. Nowadays, most wind towers
in use can be described by the four major
components: tower, rotor (hub and three blades),
nacelle and foundation (Hemami, 2012). In this
paper the manufacturing process of a tubular
metallic tower is considered and modelled using
DES.
2 MODELLING
2.1 Simulation Methods
According to McHaney (McHaney, 2009), computer
simulation can be broadly defined as:
“Use of a computer to imitate operations of a real
world process or facility according to appropriately
developed assumptions taking the form of logical,
statistical, or mathematical relationships which are
developed into a model.”
Figure 1.1: Typical modern wind tower with tubular
metallic tower (Hemami, 2012).
A model is defined as the representation of a
system with the purpose of studying it. Only aspects
that influence the problem in study must be
considered and then represented in the model. By
definition the model is a simplification of the real
system (Banks, et al., Fourth Edition).
It is possible to classify computational simulation
according to three categories: Monte Carlo
Simulation (MCS), Continuous Simulation (CS) and
Discrete Events Simulation (DES). MCS uses
generation of random numbers to simulate, without
considering time explicitly as a variable. This
method of simulation is defined by Law and Kelton
(Law & Kelton, 2000) as being “a scheme using
random numbers that are used to solve deterministic
or stochastic problems where time plays no role”.
CS models use a set of equations in representation of
725
Tomé P., Teixeira E., Assunção F., Marques L., C.P. Reis J. and M.C. Sousa J..
Simulation and Model Sensitivity Analisys of a Wind Turbine Tower Manufacturing Plant.
DOI: 10.5220/0005040807250732
In Proceedings of the 4th International Conference on Simulation and Modeling Methodologies, Technologies and Applications (SIMULTECH-2014),
pages 725-732
ISBN: 978-989-758-038-3
Copyright
c
2014 SCITEPRESS (Science and Technology Publications, Lda.)
a system evolution trough time. DES is
characterized by blocks of time when nothing
happens until an event changes the state of the
system.
For this study, DES methodology is considered.
The definition of important concepts as system,
system state, entity, attributes, events and others can
be found for instance in references (Banks, et al.,
Fourth Edition) and (Altiok and Melamed, 2007).
2.2 Case Study
The desired model is required to simulate to a
certain degree of accuracy the resource allocation
and production output of part of a Portuguese wind
turbine tower manufacturer, in order to help the
company evaluating the effect of altering key
variables in production time.
According to the company, a tower is produced
from smaller elements (in Portuguese named:
virolas) welded to each other in order to become a
section of a tower (in Portuguese named: tramos).
The sections are then assembled on sight for
obtaining the complete tower. A simplification of
the process flow is given in figure 2.2.
Figure 2.1.a: Virolas. Figure 2.1.b: Tramos.
Figure 2.2: Production flow.
The considered entities (Virolas) are assumed to
have an unlimited stock. Therefore the operations of
“Preparation” and “Assemble Virola” do not
interfere with the production and for this reason they
are not modelled.
A tower built from 34 Virola elements welded to
form 5 Tramos sections, according to figure 2.3 is
considered.
The production of a subsection consists of the
operations of transportation of the elements to the
production line, welding, inspection, assembling of
accessories and other operations. For each
production line, depending on the section in
production, around 65 to 90 different operations can
be executed in order to manufacture that section.
Figure 2.3: Sections of the considered tower (TEGOPI).
As an example, the simplified flow diagram for
the lower section S5 is presented in figure 2.4. The
simplification is due to some operations being
grouped, as is the case of “welding” that represents a
sequence of six different welding operations.
Since each process requires different machine
and worker resources, in order to be able to evaluate
the impact of changing the availability of any of
them in the model, the modelled system features:
10 production lines
• 20 vehicles
• 26 different resources
• 12 worker profiles
• Around 500 operations
2.3 Model Assumptions
With the purpose of modelling the studied system in
an objective way, a set of assumptions was defined,
such as:
i. The production orders are to be specified for
the sections (Tramos)
ii. The created entities are transported to the
production line by vehicles and workers
simultaneously
iii. The vehicles mentioned in ii travel in specific
networks and have a limit for the maximum
transporting weight
Prepar-
ation
Virola
Assembl
e Virola
Assemble
Tramo
Weldin
g
Tramo
Inspection
Tramo
Finish
SIMULTECH2014-4thInternationalConferenceonSimulationandModelingMethodologies,Technologiesand
Applications
726
Figure 2.4: Simplified flowchart of the manufacturing process of section S5.
iv. All vehicles are “driven” by two workers,
where the profile of the worker is depending on the
entity type to transport.
v. At the production line the entities are
processed according to the array of operations
specified by the company
vi. Whenever a shift is interrupted or finished,
the workers assigned to the running operations are
released
vii. At the beginning of a shift where pending
operations exist, those are resumed according to the
priority associated to the respective entities.
In addition, two specific production lines are
assigned to the production of each specific section
due to weight constraints of the vehicles.
Production orders are given for the sections by
specifying a start date and a destination production
line. As soon as one element reaches the assembly
stand of one production line, the next element of the
production sequence is created and sent to this same
production line. Initial element priorities can be
specified for each entity and destination production
lines.
If an order for the production of a section is
given and the destination production line is busy, the
model will create the entity, but this entity will not
be allowed to leave the stock area until the
destination line finishes the work in progress. Then
becoming available to processes the new ordered
section.
The model takes transportation times according
to the distances from stock to production line
locations into consideration. After completing the
transportation tasks, the vehicles stay idle at the
unload station. For accepting a transportation request
a condition is evaluated. This condition specifies
that the chosen vehicle is one of the available ones
and has a load capacity that is enough to carry the
element, but with the lowest possible carrying
capacity.
All operations are performed by at least one
worker sometimes using resources to perform the
task.
Having had access to the average times of the
different operations only but knowing that this times
are not constant, a time distribution is used to model
this behaviour. According to reference (Altiok &
Melamed, 2007), a triangular distribution can be
used when the actual time distribution is unknown
but it is reasonable to assume that minimum (a) and
maximum (b) possible values exist and that the most
likely value (c) is inside this interval. Triangular
distributions are defined by the following function:
2

, 

2

,

0, 
(1)
In the model the average value provided by the
company is considered to be the most likely value
(c). The minimum and maximum values (a and b)
are obtained applying a percentage deviation around
c. The model considers 5% deviation around c, but it
is possible to change this rule easily by using the
spread sheets attached to the model.
Multiple profiles of workers are defined (12 in
total) according to the company’s specifications.
These profiles are not flexible to perform a task from
another profile. The same applies for resources. This
implies that an interrupted operation can only be
resumed when the needed worker profile(s) and
resource(s) are available to attend this task. Workers
and resources “capacities”, costs and reliability logic
SimulationandModelSensitivityAnalisysofaWindTurbineTowerManufacturingPlant
727
(the last only for resources) are able to be feed easily
and changed into the model through the attached
spread sheets. For the later purpose of model
validation reliability logic is not considered since it
is not mentioned in the supplied data.
3 RESULTS ANASLYSIS
According to Kelton (Kelton, Smith, Sturrock,
2013), only for the simplest models one is able to
prove categorically the aspects of correct modelling.
Therefore, the model should be tested in a way that
is possible to verify that it behaves in the desired
manner. First the model sensitivity to changing key
variables is tested and analysed. Latter, data
provided from the company is used to evaluate
model performance. Multiple versions of the model
are used to verify this point.
3.1 Sensitivity Analysis
Since transportation of elements from the stock
location to the production line takes a considerable
amount of time, figure 3.1 shows the production
time using calculated distance (Model*1) or an
smaller average distance (Model*2) for the
production of section S5 in production line 8.
As expected, the net time needed for the
production of this section decreases when average
distances are considered. A decrease in occupation
times of both workers (PF1 and PF8) and vehicles
can be observed in figure 3.2 with a greater level of
detail.
Figure 3.1: Production times: section S5 figuin line 8.
In fact, when the complete model is considered
and production orders that lead to the manufacture
of 4 towers are given, Model*2 needs about 3 days
less of labour for finishing the production.
Figure 3.2: Resources occupation: section S5 in line 8.
The order in which operations are executed is
related to the priority given to the entities (Virola) in
processing. Once that the number of resources is
limited, situations can occur where not enough
resources are available to attend to all requested
operations. Therefore, the priority assigned to
entities plays an import role in the system and by
changing this parameter model results should be
affected. According to the company TEGOPI -
Industria Metalomecânica, S.A., Portugal, the
priority is defined to be highest for entities of section
S5 followed by the entities of sections S1, S4, S3
and therefore, S2 entities were given the lowest
priorities of the set. This configuration is used in
both Model*1 and Model*2.
A new set of priorities was defined for Model*3
by keeping the relative priority of the different
sections but increasing priority of the sections that
will form the two first towers. This way assuring
that priority is given to an older production order
and by doing so a better approximation to the real
system should be achieved. A summary of due dates
obtained with the models considered up to this point
can be observed in table 3.1.
Table 3.1: Due dates summary.
Due date
Model*1 Model*2 Model*3
4
th
tower 8-May-13 3-May-13 30-Apr-13
In the construction of the model, special attention
was placed into the allocation of workers to
operations. Since specific profiles of workers are
used to perform operations on the job-shop using
resources of some kind, varying the available
number of workers and their profiles should have a
major effect on the delivery dates. This effect can be
832
301
519
752
245
508
150
350
550
750
950
Total time Stopage
time
Net time
Time (hours)
Model*1 Model *2
242
111
21,0
236
105
9,6
0
50
100
150
200
250
300
PF1 PF8 Vehicles
Time (hours)
Model*1 Model *2
SIMULTECH2014-4thInternationalConferenceonSimulationandModelingMethodologies,Technologiesand
Applications
728
observed through analysis of the results obtained
with Model*4. Model*4 is built from Model*3 but
setting an unlimited number of both workers and
resources.
Table 3.2: Limited VS Unlimited resources.
Due date
Model*3 Model*4
1st tower 28-Feb-13 15-Feb-13
2nd tower 4-Apr-13 25-Feb-13
3rd tower 10-Apr-13 21-Mar-13
4th tower 30-Apr-13 26-Mar-13
As expected, the model reacted to the increase
of resources by reducing significantly the delivery
times. Note that for obtaining the results above the
number of workers used is much higher than the
ones scheduled by the company. Figure 3.3 and
figure 3.4 show the comparison of used resources.
Figure 3.3: Workforce: TEGOPI VS Model*4.
3.2 Model Validation
Validation of the model is achieved by comparing
delivery times of the different scenarios with data
provided from the company.
3.2.1 Single Production Line
With knowledge of the average processing times of
each operation to be performed in each section, it is
possible to obtain an estimated average time for the
total delivery time of each section. For this scenario
unlimited resources were considered so that delays
resulting from lack of resources do not occur.
Figure 3.4: Resources TEGOPI VS Model*4.
Figure 3.5 to figure 3.7 show the occupation of the
resources to manufacture section 5S for the cases:
Validation scenario and Model*2. Model*2 is
chosen because it considers average distances from
stock to production, thus better matching the
available data for validation.
Figure 3.5: Machine occupation: section S5.
Deviations between 0.2% and 2.1% when compared
with the validation data were obtained for machine
occupation. Workers utilization varies up to 4.8%.
Regarding transportation times there is a 15.2%
difference between the validation data and Model*2.
In case Model*1 was considered, around 21 hours of
total transportation time would be needed.
0
10
20
30
40
50
60
1st Shift 2nd Shift 3rd Shift
Number of Workers
Tegopi Model*4
0
2
4
6
8
10
12
14
Arc
ArcoSubmerso
Carro chanfrar
EasyLaser
Lix2
Lix4
Macarico
Rebarbadeira
RF1
Semi
UltraSom
SO213
SO257
SO283
SO294
SO296
Tegopi Modelo*4
0
10
20
30
40
50
60
70
80
90
100
ARC.
Arco-Submerso
Carro chanfrar
Easy-laser
Maçarico
Rebarbadeira
Semi
SO213
SO294
Ultra-sons
VS - Linha8
Time (hous)
Validation Scenario Model *2
SimulationandModelSensitivityAnalisysofaWindTurbineTowerManufacturingPlant
729
Figure 3.6: Workers occupation: Section S5.
Figure 3.7: Vehicles occupation: section S5.
Figure 3.8 compares the net production time used.
Figure 3.8: Production time: section S5.
3.2.2 Validation Scenario
Having already verified model sensibility to key
parameters, the considered models can now be
compared to the expected due dates from the
validation data.
Although the model results may seem to be poor
some considerations must be taken into account:
According to the supplied data there are shifts
where worker profiles are not available (e.g.: PF6 is
not available on the third shift).
Table 3.3: Due dates: Multiple scenarios.
Validation Data Due Date
Production
Order
Due Date Model*1 Model*2 Model*3
1st tower 11-Jan-13 13-Feb-13 11-Mar-13 26-Feb-13 28-Feb-13
2nd
tower
18-Jan-13 22-Feb-13 22-Mar-13 21-Mar-13 4-Apr-13
3rd tower 23-Jan-13 15-Mar-13 29-Apr-13 1-May-13 10-Apr-13
4th tower 28-Jan-13 19-Mar-13 8-May-13 3-May-13 30-Apr-13
Meanwhile, on the data for validation this
situation appears not to occur since there is no
indication of delayed operations as result of
missing workers.
In simulation it often occurs, that after the end
of a shift the next shift does not have enough
resources to resume all interrupted operations.
Priority operations are resumed first. This can
lead to delay due to lack of resources in low
priority operations.
Model does not consider workers to be flexible.
Take for instance an operation that uses the worker
profile above (PF6) and that is interrupted in the end
of the 2
nd
shift. This operation can only be resumed
after one shift of interruption, affecting the
production time due to this delay.
3.2.3 Unlimited Resources
A version of the model with unlimited resources and
average paths (Model*4) is used. This allows the
model to get closer to the data for validation,
according to table 3.4.
For the first and second towers results are
matching the expected since the production lines
start free and times are not affected by delay. For the
next towers delay occurs since the production lines
are occupied when the production order reaches the
system.
Table 3.4: Due dates: Model*4.
Validation Data
Due date
Model*4
Production
Order
Due Date
1
st
tower 11-Jan-13 13-Feb-13 15-Feb-13
2
nd
tower 18-Jan-13 22-Feb-13 25-Feb-13
3
rd
tower 23-Jan-13 15-Mar-13 21-Mar-13
4
th
tower 28-Jan-13 19-Mar-13 26-Mar-13
0
50
100
150
200
250
300
PF1
PF2
PF3
PF4
PF5
PF6
PF7
PF8
PF9
PF10
PF11
PF12
Time (hours)
Validation Scenario Model *2
7
8
9
10
Total Time
Time (hours)
Validation
Scenario
Model *2
150
250
350
450
550
650
750
850
Total time Stopage
time
Net time
Time (hours)
Validation Scenario Modelo*2
SIMULTECH2014-4thInternationalConferenceonSimulationandModelingMethodologies,Technologiesand
Applications
730
Table 3.5: Due dates tower 3 and 4: Model*4.
Validation Data
Due date
Model*4
Production
Order
Due Date
3
rd
tower 23-Jan-13 26-Feb-13 27-Feb-13
4
th
tower 28-Jan-13 4-Mar-13 5-Mar-13
To eliminate this effect, a scenario for the
production of towers three and four only was
simulated. Results in table 3.5 show that the due
dates in this situation are inside the acceptable limits
for the model.
In order to achieve these results, Model*4 used
145 workers. The company actually scheduled 84
workers. A situation in which the number of workers
used is higher than the number scheduled is verified.
Figure 3.9: PF5 1st shift usage: Model*4.
The number of workers PF5 of the 1
st
shift
(PF5_t1) is chosen because it represents the bigger
deviation.
Four workers are scheduled by the company and
ten were used by Model*4. Figure 3.9 shows
detailed statistics regarding the workers of PF5_t1
used by Model*4. Hence profiles PF5_t1[7] to
PF5_t1[10] are used for less than a eight hours shift,
results appear to show that the model lacks some
logic for task selection preventing that, for example,
a task with more than eight hours duration starts
close to the end of a shift.
In a situation when more workers are available, a
larger number of machine resources is used
according to figure 3.10.
Figure 3.10: Allocated machines: Model*4.
3.2.4 Tuning of Model Assumptions
In this version of the model another approach is
used, using the knowledge that for completing the
scheduled production of the four towers the
company spent three months. The model will be
used to achieve this delivery time using a number of
workers similar to the one scheduled by the
company.
Model*4 is used as the starting point and then,
the number of workers is limited based on the
previous usage time. Workers with less than 10
hours of use are discarded for the next run. Using the
previous example of PF5_t1, in Model*5 the number
of workers of this profile is limited to 6. This way
Model*5 uses 96 workers but still more machines
than the number scheduled by the company. Now
limiting the number of machines according to
specification (Model*6) and then reducing five more
workers (Model*6.1) the model has provided the
following results.
Table 3.6: Due dates: Model*6 and Model*6.1.
Due date
Model*5 Model*6 Model*6.1
1
st
tower 15-Feb-13 19-Feb-13 21-Feb-13
2
nd
tower 25-Feb-13 4-Mar-13 5-Mar-13
3
rd
tower 21-Mar-13 22-Mar-13 28-Mar-13
4
th
tower 26-Mar-13 5-Apr-13 9-Apr-13
0
20
40
60
80
100
120
140
160
BusyTime (h)and nunber of occorences
BusyTime Occurrences
8h 16h
24h
0
2
4
6
8
10
12
14
Machine resources used
Tegopi Modelo*4
SimulationandModelSensitivityAnalisysofaWindTurbineTowerManufacturingPlant
731
With delivery time of approximately three months,
Model*6.1 uses a total of 91 workers meaning 8.3%
above the number of workers specified by the
company. Although more workers are used in
simulation, this value is according to the company’s
expectation for the model’s performance without
considering resource flexibility.
4 CONCLUSIONS
The proposed model allowed the analysis of the
behaviour of the studied system. Although the model
represents all the production process with a
reasonable degree of detail, special emphasis was
given to workers allocation to tasks. Nevertheless it
is easy to change other parameters and test more
scenarios.
Individual production lines were studied and
analysed in greater detail by verifying worker and
resources utilization and completion time to ensure
they could be used for correct modelling of the
overall plant.
It is possible to establish that transport traveling
distance and priority logic have a significant
influence in the response of the model. But more
important, the model is very sensitive to changes in
worker capacity and worker distribution by the
several specialization profiles. This is due to the
demand of at least one worker to execute each task
from the productive process.
The model results agree with the data supplied
by the company for the individual production lines.
For the overall plant the results showed some
discrepancies, but the sensitivity analysis allowed an
identification of the most significant problems of the
original model version. By redesigning some of the
model assumptions and logic that were originally not
part of the supplied data, it was possible to improve
the model results to within 8.3% of error relative to
the real data values. This result was considered as
acceptable by the industrial partner under the
assumptions that were considered.
ACKNOWLEDGEMENTS
This work was supported by FCT, through IDMEC,
under LAETA Pest-OE/EME/LA0022 and partially
supported by the project R046, IDMEC.
REFERENCES
Altiok, T. & Melamed, B., 2007. Simulation Modeling and
Analysis with Arena. United States of America:
Elsevier Inc.
Banks, J., II, J. S. C., Nelson, B. L. & Nicol, D. M., Fourth
Edition. Discrete-Event System Simulation. New
Jersey: PRENTICHEA L-L lN TERNATIONAL
SERIEINS lN DUSTRIAL AND SYSTEMENSG
INEERING.
Brito, S. d. S., 2014. CRESESB. [Online] Available at:
http://www.cresesb.cepel.br/content.php?cid=tutorial_
eolica.
Chance, F., Robinson, J. & Fowler, J., 1996. Supporting
manufacturing with simulation: model design,
development, and deployment. San Diego, CA., IEEE.
Hemami, A., 2012. Wind Turbine Technology. 5 Maxwell
Drive, Clifton Park, NY 12065-2919, USA: Cengage
Learning.
Kelton, W. D., Smith, J. S. & Sturrock, D. T., 2013. Simio
and Simulation: Modeling, Analysis, Applications -
Third Edition. s.l.:Simio LLC.
Law, A. M. & Kelton, W. D., 2000. Simulation Modeling
and Analisys, Third Edition. s.l.:McGraw-Hill Book
Company.
McHaney, R., 2009. Understanding Computer Simulation.
s.l.:Roger McHaney & Ventus Publishing ApS.
Redes Energéticas Nacionais, R., 2013. Energia Eólica em
Portugal 2012.
TEGOPI, n.d. [Online] Available at: http://www.tegopi.pt/
?mod=pdinamicas_pag&id=2&_item=1.
SIMULTECH2014-4thInternationalConferenceonSimulationandModelingMethodologies,Technologiesand
Applications