until the predecessor activity is completed.
Therefore, it could not allow overlapping unless
activities were further divided (Fondahl, 1961).
Precedence Diagram Method (PDM), which was
developed based on the concept of CPM analysis,
introduced three alternative relationships, i.e., start-
to-start (SS), finish-to-finish (FF), and start-to-
finish; and lag factor between various activities. The
PDM is also called activity on node (AON) network,
and some authors call both methods (CPM and
PDM) as CPM. PDM with three additional
relationships between activities has provided a more
flexible realistic project representation in schedule
networks and more accurately reflects the sequence
of construction operations as they occur in real life
(Ahuja, 1994). There are various computer software
packages available such as Primavera P6 and MS
Project, which provide the PDM schedule.
PDM seems to be more friendly compare to the
CPM. For example, suppose that providing concrete
floor for a warehouse needs three construction
activities. Let activity A is “install formwork,
activity B is “reinforcement arrangement”, and
activity C is “pour concrete”. The duration of each
activity is estimated as 4, 4 and 2 days, respectively.
Based on CPM assumption the technological
relationship between these three activities will be
finish-to-start, and they have to be executed as
series. Therefore, the project duration would be 10
days. Whereas, in PDM as shown in Fig.1, activity
A “reinforce arrangement” and activity B “install
formwork” can be executed concurrently so that
start-to-start with two days lag would be the prober
relationship between them. Thus, the PDM
relationship reduces the project duration to 8 days.
However, the new relationships of PDM can
change some of the basic concept of critical
activities and critical path. According basic
definition of critical activity in CPM, the
shortening/lengthening of a critical activity on
critical path always results in decreased/increased
project duration. But, this definition does not always
apply on PDM. Crashing some critical activity in
Figure 1: PDM schedule with SS relation.
PDM in order to reduce the project duration can
have anomalous effects (Wiest, 1981; Wiest and
Levy, 1977).
To better illustrate the anomalous effect of new
relationships of PDM on critical activities, consider
the simple project schedule that shows on Activity-
on-Node network in Fig.2. Each rectangle in
network represents a project activity. The
technological relationships between activities are
indicated by arrows. The project consists of 7
activities. Activities S and F are assumed to be
artificial activities indicating the project
commencement and the project completion,
respectively. The results of CPM calculation are
shown in Fig.3 as bar-chart fashion along a
horizontal time scale. The sequence of activities and
precedence arrows denoted by bold line, represent
the critical path. As shown in
Fig.3, we can identify activities 1, 4, 5, 6, and 7
as critical (zero total float). First, let us to define the
characteristics of a critical activity in traditional
CPM as: (i) any delay in the start time of a critical
activity will result in a delay in the project duration,
(ii) any change in the length of a critical activity will
result the same change in the entire project duration.
The first characteristic is true on all critical activities
in schedule network in Fig.3. The second
characteristic is still true on critical activities 1, 6,
and 7. However, this characteristic cannot be true on
critical activities 4 and 5. For example, shortening
activity 4 would have reversely effect on project
duration, meaning it will increase the project
duration. Conversely, lengthening it will decrease
Figure 2: PDM schedule network.
Day0123456789
A, 4 (0)
B, 4 (0)
C, 2 (0)
0 4
2 6
2 6
SS = 2
6 8
6 8
Name, Duration (TF)
LS LF
ES EF
Legend
CriticalActivityEffectonProjectDurationinPrecedenceDiagramMethodSchedulingNetwork
315