following we report the results of the interpretations
carried out, after applying the decision model to the
EVM indicators collected.
WP ACTI
ITIES
PERSON/DAYS COST SOLAR DAYS
PLANNED
PERSON/DAYS COST SOLAR DAYS
ACTUAL
A1
A2
A3
A4
A5
A6
A6
A7
A7
A8
A8
A9
P4
WP1
WP2
WP3
48 8.151,60€ 18
9,6 1.630,32€ 3,6
81,6 13.857,72€ 30,6
14,4 2.445,48€ 5,4
48 8.151,60€ 18
91,2 15.488,04€ 34,2
144 24.454,80€ 54
33,6 5.706,12€ 12,6
9,6 1.630,32€ 3,6
480 81.516,00€ 180
40,07 8.005,36€ 18
8,01 1.601,07€ 3,6
60,1 12.008,04€ 27
12,02 2.401,61€ 5,4
20,03 4.002,68€ 9
76,13 15.210,18€ 34,2
16,03 3.202,14€ 7,2
120,20625 24.016,08€ 54
12,02 2.401,61€ 5,4
28,05 5.603,75€ 12,6
4,01 800,54€ 1,8
4,01 800,54€ 1,8
400,68 80.053,60€ 180
Figure 5: descriptive statistics of planned and actual
values.
ACTIVITY
% of
progress
A1 10%
A2 12%
A3 27%
A4 30%
A5 35%
A6 54%
A6 58%
A7 88%
A7 91%
A8 98%
A8 99%
A9
100%
BCWP BCWS SV ACWP CV SPI CPI EACC EACT
8.151,60 8.151,60 0,00 8.005,36 146,24 1,00 1,02 80.053,60 6,00
9.781,92 9.781,92 0,00 9.606,43 175,49 1,00 1,02 80.053,58 6,00
23.639,64 22.009,32 1.630,32 21.614,47 2.025,17 1,07 1,09 74.532,66 5,59
26.085,12 24.454,80 1.630,32 24.016,08 2.069,04 1,07 1,09 75.050,25 5,63
34.236,72 28.530,60 5.706,12 28.018,76 6.217,96 1,20 1,22 66.711,33 5,00
41.980,74 44.018,64 -2.037,90 43.228,94 -1.248,20 0,95 0,97 83.939,70 6,29
49.724,76 47.279,28 2.445,48 46.431,09 3.293,67 1,05 1,07 76.116,54 5,70
61.952,16 71.734,08 -9.781,92 70.447,17 -8.495,01 0,86 0,88 92.693,64 6,95
74.179,56 74.179,56 0,00 72.848,77 1.330,79 1,00 1,02 80.053,60 6,00
77.032,62 79.885,68 -2.853,06 78.452,52 -1.419,90 0,96 0,98 83.018,54 6,22
79.885,68 80.700,84 -815,16 79.253,06 632,62 0,99 1,01 80.870,47 6,06
81.516,00 81.516,00 0,00 80.053,60 1.462,40 1,00 1,02 80.053,60 6,00
EVM INDIC
R
LUES
Figure 6: EVM values for the entire project.
The TAC (initial estimation of project duration) is 6
months, while BAC (initial estimation of project
cost) is €81.516,00. The first activity (A1) required
18 solar days, according to the plan, and a total of 40
person/days (p/d) compared to 48 planned with a
lower cost. The EVM indicators for this activity
confirm this data. In A2, descriptive statistics show
that actual values are lower than planned ones. The
project was proceeding correctly and project
managers decided to designate the extra budget to
future activities. In A3, the activities were carried
out in less time with respect to planned (27 solar
days, and 60 p/d, compared to 30 solar days and 81
p/d planned). In accordance to the interpretation of
the decision model, project managers decided to
designate part of the budget not spent and the
resources assigned to this task. In A4 the trend of
EVM indicators confirms the results of the previous
phases as they satisfy the baseline values of the
decision model. As it appears from both the
descriptive statistics and the EVM values, A5 was
carried out with less effort and cost than planned.
In A6, when the milestone checkpoint was
carried out, the project was behind schedule and not
completed yet. At this point the EVM indicators
pointed out a situation over budget as more than
expected was being spent and project cost and effort
were higher than planned. As improvement action
managers decided to designate part of the resources
saved in the previous phases to the current one.
Consequently, staff that had terminated activities
early and had the required skills were assigned to
this activity. Also, part of the budget saved in the
previous phases was also shifted to this one. This
improvement action had positive effects, i.e. at the
next milestone checkpoint the EVM indicators had
returned within the baseline values. Having
recovered both budget and resources from previous
activities, the overall budget and effort for the
project were not impacted. Indeed, the EVM
indicators related to A6 are inline with the baseline
values. This was possible because manager decisions
in previous checkpoints were taken in order to
prevent difficulties in further activities. In A7
another delay occurred. After a period of 54 days,
the activity was not completed. The EVM indicators
confirm this situation for A7 (Figure 6 first row),
which are below the threshold values. Managers
reallocating resources from previous activities or
from activities that were ahead of schedule and
below budget and shifted them to A7. For what
concerns A8, after 12.6 days it was not completed
(Figure 5). A9 requested fewer resources in terms of
performances and cost to be carried out, and
consequently indicators SPI and CPI returned to
satisfy the baselines.
Having collected EVM values during milestones
with a granularity related to activities rather than
work packages or entire project, allowed the project
managers to appropriately monitor and control the
general trend of the performance indicators and
readily act to recuperate delays accumulated during
the project. Indeed, the resources saved in on-
schedule/budget activities were allocated on other
critical off-schedule/budget ones. As so, delays were
mitigated by improvement actions without impacting
on the overall final project cost and effort, which by
the end of the project turned out to be within the
expected thresholds. Deviations from the plan in
some activities were successfully recovered in other
ones by readily reallocating budget and effort to face
problematic situations pointed out during monitoring
checks. Having adopted a decision model to guide
the interpretation of indicators turned out to be
helpful as it simplified the entire monitoring and
control process as the project progressed in time.
4 DISCUSSION AND
CONCLUSIONS
Earned Value Management technique is easy to
understand and apply. Nonetheless, there are several
critical factors that any manager should keep in
mind: collecting cost values at a low level of
granularity requires an advanced level of
ICEIS2015-17thInternationalConferenceonEnterpriseInformationSystems
506