Resource Flow based Order Selection Method in Project Cost
Estimation Process
Nobuaki Ishii
1
, Yuichi Takano
2
and Masaaki Muraki
3
1
Faculty of Engineering, Kanagawa University, 3-27-1 Rokkakubashi, Kanagawa-ku, Yokohama, 221-8686, Japan
2
School of Network Information, Senshu University, 2-1-1, Higashimita, Tama-ku, Kawasaki, Kanagawa, Japan
3
Graduate School of Decision Science and Technology, Tokyo Institute of Technology, Tokyo, Japan
Keywords: Business Process Modeling, Competitive Bidding, Project Management, Resource Allocation.
Abstract: Since the project price is fixed in EPC (Engineering, Procurement, and Construction) projects, the
contractor should devote significant resources to the cost estimation process to realize the accurate cost
estimation and then accept profitable projects from clients in competitive bidding situations. However, it is
impossible for any contractor to devote sufficient resources to all the orders because of the resource
constraints. In this study, a multistage project cost estimation process model, consisting of pre-evaluation,
order selection, man-hour allocation, and a series of cost estimation steps, is developed. Then, this study
devises a resource flow based order selection method and man-hour allocation method to provide successful
results to clients and to maximize the contractor’s profits under the limited resources. Specifically, those
methods dynamically select orders to estimate cost at each order arrival and allocate the resources to the
selected orders, respectively. The effectiveness of our method is demonstrated through simulation
experiments using the developed model.
1 INTRODUCTION
EPC (Engineering, Procurement, and Construction)
projects (Pritchard and Scriven, 2011) correspond to
the execution process of industrial projects, such as
process plants, structures, and information systems.
Those projects start after the final investment
decision by the clients, and are complete when the
contractor delivers facilities based on the client’s
requirements for a limited period of time under a
lump sum turnkey basis. Since any EPC project
includes unique and non-repetitive activities, many
uncertainties exist in the project execution process.
Furthermore, since the project price is fixed before
the start of the project, the contractor often faces
eventual loss of profit in EPC projects. Thus, it is
necessary for any contractor to precisely estimate the
project cost in order to determine the bidding price.
Namely, the cost estimation process in an EPC
project is critical for any contractor who seeks to
increase profits and reduce the possibility of
realizing a loss, i.e., a deficit risk, due to cost
estimation error.
Cost estimation is also crucial for ensuring the
proper volume of accepted orders. Inaccurate cost
estimation could not only lead to deficit orders but
could also exhaust the contractor’s resources, which
are necessary to carry out long-term deficit projects,
as Ishii et al. (2014) stated. Moreover, a contractor’s
deficit order would have severely harmful effects on
the client’s business. For example, it would generate
an additional cost and/or delay to the project
delivery date, thus the client would miss a business
opportunity.
Since the quality and quantity of the data
available for cost estimation determine the accuracy
of the estimated cost, a significant amount of high-
quality data is required to improve accuracy. In
process plant engineering, for example,
the data and
methods required to attain the target accuracy of
project cost estimation have been studied
(AACE,
2011). In any cost estimation method, such as
parametric, analogy, and engineering (Kerzner,
2013), higher accuracy requires more data and,
accordingly, more engineering man-hours (MH) to
acquire and analyse the data for cost estimation.
Thus, experienced and skilled human resources
who can acquire data for cost estimation and create
project plans are required for accurate cost
estimation.
Those resources, however, are limited for
Ishii, N., Takano, Y. and Muraki, M.
Resource Flow based Order Selection Method in Project Cost Estimation Process.
DOI: 10.5220/0006481901550162
In Proceedings of the 7th International Conference on Simulation and Modeling Methodologies, Technologies and Applications (SIMULTECH 2017), pages 155-162
ISBN: 978-989-758-265-3
Copyright © 2017 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
155
any contractor. Furthermore, once the orders are
successfully accepted, the corresponding project
execution will also need considerable human
resources. For these reasons, the contractor should
realize appropriate selection of orders and allocation
of MH for cost estimation of each selected order to
maximize the total expected profit under the
constraint of the total MH.
Based on the above observations, this paper
examines the cost estimation process of EPC
projects in dynamic order arrival situations. Namely,
activities of the project cost estimation process are
identified, and a model of the multistage project cost
estimation process that divides the cost estimation
process into four phases, i.e., pre-evaluation, order
selection, MH allocation, and a series of cost
estimate steps, is developed.
We next devised an order selection method based
on resource flows for dynamically selecting orders
to estimate cost at each order arrival through the pre-
evaluation and the order selection in the developed
model. In addition, we use MH allocation rules for
allocating the limited resources to the selected orders
in the MH allocation. The resource flow based order
selection method selects orders on the basis of the
flow rate of the contractor’s MH for estimating cost
and that of the expected profits from the orders. MH
allocation rules prioritize orders in the queue waiting
for allocating MH for estimating cost, and then it
allocates MH to the orders based on the priority. We
finally analyse the effectiveness of our developed
methods through numerical examples by using the
discrete-event simulation model of the multistage
project cost estimation process.
2 RELATED WORK
A variety of studies have been conducted on project
cost estimation from the viewpoints of cost
estimation accuracy, MH allocation for cost
estimation, order selection, and so on. For example,
AACE (2011), Humphreys (2004), and Towler and
Sinnott (2008) demonstrated the relationship of cost
estimation accuracy and the methods and data used
for cost estimation in the field of process plant
engineering projects. Furthermore, they suggested
that cost estimation accuracy is positively correlated
with the volume of MH for cost estimation.
However, only a few of studies have examined
management issues on the project cost estimation
process that uses the methods and data for cost
estimation.
Regarding MH allocation in the cost estimation
process, Ishii et al. (2016a) developed an algorithm
that determines the bidding prices under the limited
MH for cost estimation. Their algorithm allocates
MH to maximize expected profits based on the cost
estimation accuracy determined by allocated MH. In
addition, Takano et al. (2014) developed a stochastic
dynamic programming model for establishing an
optimal sequential bidding strategy in a competitive
bidding situation. Their model determines the
optimal markup in consideration of the effect of
inaccurate cost estimates. Takano et al. (2016) also
developed a bid markup decision and resource
allocation model that determines the optimum bid
markup and resource allocation simultaneously.
Furthermore, Takano et al. (2017) developed a
multi-period resource allocation method for
estimating project costs in a sequential competitive
bidding situation. Their method allocates resources
for cost estimation by solving a mixed integer
programming problem that is formulated by making
a piecewise liner approximation of the expected
profit functions. Those studies, however, assume the
order arrivals in advance, and thus they cannot deal
with dynamic order arrival situations.
Regarding the order selection in the cost
estimation process, Shafahi and Haghani (2014)
proposed an optimization model that combines
project selection decisions and markup selection
decisions in consideration of eminence and previous
works as the non-monetary evaluation criterion used
by owners for evaluating bids. In addition, Ishii et al.
(2016b) developed the threshold function method
(TFM) for deciding bid or no-bid on newly arrived
orders based on the threshold function of MH
utilization with respect to the expected profit of
orders. In TFM, the threshold function is determined
through simulation experiments under a set of
averaged conditions for estimating cost. They show
that TFM increases the expected profits from orders
compared to the case of no order selection by
simulation experiments. In TFM, however, the
contractor needs to build a simulation model of the
cost estimation process and certain computational
loads to obtain the threshold function. In addition, a
long-term
and stable cost estimation conditions, such
as order arrivals, expected profits from orders, and so
on, are assumed in advance to determine the threshold
function through simulation runs.
Thus, TFM could
not deliver good performance in practical situations
where the cost estimation conditions are unstable and
change dynamically.
Based on the above literature review, we found
that most of the studies have paid little attention to
SIMULTECH 2017 - 7th International Conference on Simulation and Modeling Methodologies, Technologies and Applications
156
the project cost estimation process in practical
situations. More specifically, in practice, the
contractor needs to select orders to bid and allocate
MH for cost estimation dynamically to each selected
order which has different characteristics. In light of
these facts, this paper develops a method for
selecting orders and determining MH allocation in
consideration of the contractor’s available MH and
the orders’ profitability under the dynamic order
arrival conditions as is the case in practical
situations.
3 A MULTISTAGE MODEL OF
PROJECT COST ESTIMATION
PROCESS
3.1 Project Cost Estimation Activities
The project cost estimation process can be
recognized as a series of activities that starts with the
arrival of bid invitations from the client and closes
by the date of bidding (Ishii et al., 2016b). A variety
of orders arrive, and the contractor selects orders to
estimate the project costs through the cost estimation
process. Then, the contractor determines the
accuracy of cost estimation by allocating MH to the
cost estimation activities of selected orders in
consideration of the MH availability, expected
profits, competitive bidding situations, and so on.
When the available MH is not sufficient to estimate
cost accurately, the contactor must allocate fewer
MH, thereby reducing expected profit due to
inaccurate cost estimation, or no-bid on the order.
3.2 Overview of the Model
Based on the above observations, we propose a
multistage model of the project cost estimation
process which consists of pre-evaluation, order
selection, MH allocation for cost estimation, and a
series of cost estimation steps, as shown in Figure 1,
by referencing the model developed by Ishii et al.
(2016b). In the model, we assume that the cost is
estimated through the cost estimation steps: E1, E2,
and E3 estimate. Each step needs MH and a period
of time for cost estimation, and the accuracy of the
estimated cost increases through the cost estimation
activities in each step.
The cost estimate manuals, such as AACE
classification matrix (AACE, 2011), the classes of
estimates by Kerzner (2013), and so on, can be used
for reference of the cost estimation accuracy and for
the required MH in each step. For example, AACE
classifies cost estimation into five classes and
indicates the methods, data, and the accuracy of cost
estimation in each class. Two of the classes in
AACE are in the order of magnitude type estimation
for a project feasibility study. Thus, the developed
model divides the cost estimate activities into three
steps in reference to the AACE system. Namely, we
assume that the project cost is estimated through a
series of three cost estimation steps, and the
accuracy of the estimated cost is improved in
accordance with the steps.
In the model, the pre-evaluation and the order
selection determine whether to select and bid the
newly arrived order or not. Specifically, the pre-
evaluation evaluates the resource flow of the process
if the newly arrived orders are selected as explained
in section 4.1. The order selection determines
whether to select orders for estimating costs or not
from the viewpoint of changes of the resource flow,
the volume of orders to be accepted, the expected
profits, MH availability for cost estimation, and so
on.
Figure 1: A model of multistage project cost estimation
process.
The selected order is first filed in the queue for
the E1 estimate and waits to be assigned the MH for
cost estimation by the mechanism of MH allocation
for cost estimation. If any MH is not assigned to the
order until the bidding date, the contractor does not
bid for it due to the lack of MH. If the MH is
assigned to the order, its project cost is estimated
with the accuracy of the E1 estimate. This order is
then filed in the queue of the E2 estimate and waits
for MH assignment for the E2 estimate. If the MH is
not further assigned to the order until the bidding
date, the contractor determines the bidding price
based on the accuracy of the E1 estimate. By
contrast, if the MH is assigned to the order waiting
Queue
for
E1
Estimation
E1
Queue
for
E
Estimation
E2
Queue
for
E3
Estimation
E3
MH allocation
for cost
estimation
MH for cost estimation
Bid
price
decision
&
Bid
Order selection
Decline
bid
invitation
Results of cost estimation
Newly
arrived
orders
Goal: Attain total volume of accepted
orders, Maximize expected profits
Orders for bid
No-bid orders due
to lack of MH
Total volume of MH
MH allocation rule
Pre-
evaluation
Evaluation
results
Expected profits & MH for cost estimation
within the cost estimation process
Resource Flow based Order Selection Method in Project Cost Estimation Process
157
in the queue of the E2 estimate, its project cost is
estimated with the accuracy of the E2 estimate, and
filed in the queue of the E3 estimate. The same
decision is made for the orders in the queue of the
E3 estimate.
The project cost estimation problem, addressed
in this paper, is a kind of dynamic scheduling
problem that determines the processes dynamically
for each order arriving at a system. In our problem,
however, orders and the volume of resources for cost
estimation are determined dynamically under the
conditions of resource availability and due date of
the order in order to maximize the total expected
profits from orders. On the contrary, in the standard
scheduling problems (Jacobs et al. 2011), orders and
the volume of resources are predetermined, and the
orders are scheduled so as to minimize the makespan
and/or reduce tardy jobs. From this perspective, we
believe that the project cost estimation problem in
this study can be recognized as a novel dynamic
scheduling problem.
4 METHODS OF ORDER
SELECTION AND MAN-HOUR
ALLOCATION
This section shows the two methods, i.e. order
selection and MH allocation for cost estimation, that
are used in the project cost estimation process shown
in Figure 1.
These two methods are developed based on the
following assumptions:
Assumptions:
1) Orders for cost estimation arrive randomly;
2) Expected profit, required MH and periods for
cost estimation of each estimate step are
predetermined;
3) Probability of a successful bid of each order,
i.e. accepted order, is predetermined.
4.1 Resource Flow based Order
Selection Method
For the order selection through the pre-evaluation
and the order selection shown in Figure 1, we
develop a resource flow based order selection
method (RFSM) that decides estimating cost or
declining bid invitation on arrived orders according
to the changes of MHR and EPR by the arrived
orders. MHR and EPR are the flow rate of MH for
cost estimation and the total expected profits from
orders, respectively, within the cost estimation
process. Those are determined as Eqs. (1) and (2).
For explaining the basis of RFSM, in this section,
we assume that the project costs of at least step E2
are estimated in all the selected orders.
/
ii
iUE
M
HR MH D
=
(1)
/
ii
iUE
E
PR EP D
=
(2)
where i is order under estimating cost in the
process. MH
i
, EP
i
, and D
i
are the volume of cost
estimation MH, the expected profit, and period for
cost estimation of order i, respectively. In addition,
UE is a set of orders within the cost estimation
process.
Now, assume that P
E3
MHR
E3
, EPR
E3
indicates
the coordinate point where costs of all the orders are
estimated to E3, P
E2
MHR
E2
, EPR
E2
indicates the
coordinate point where costs of all the orders are
estimated to E2, and MHR
CP
is the maximum flow
rate of MH available in the cost estimation process.
Then, the rate of maximum expected profits
EPR
max
is calculated based on the magnitude
relationship between MHR
E3
and MHR
CP
as Eqs. (3)
or (4).
1) If MHR
E3
MHR
CP
:
EPRmax EPRE3 (3)
2) If MHR
CP
MHR
E3
:
23
3223
23
23
max
EE
EEEE
CP
EE
EE
MHRMHR
EPRMHREPRMHR
MHR
MHRMHR
EPREPR
EPR
+
=
(4)
Eq. (4) assumes that there is linearity between
P
E3
and P
E2
, then EPR
max
exists where MHRcp
intersects the line connecting the points of P
E3
and
P
E2
as shown in Figure 2.
Next, if the new order nwd has arrived for cost
estimation, P’
E3
(MHR’
E3
, EPR’
E3
) and P’
E2
(MHR’
E2
,
EPR’
E2
), which indicate the coordinate points
including nwd, are calculated in Eqs. (5) to (8).
nwd
EEE
MHRMHRRMHR
33
'
3
+=
(5)
nwd
EEE
EPREPRREPR
33
'
3
+=
(6)
nwd
EEE
MHRMHRRMHR
22
'
2
+=
(7)
nwd
EEE
EPREPRREPR
22
'
2
+=
(8)
SIMULTECH 2017 - 7th International Conference on Simulation and Modeling Methodologies, Technologies and Applications
158
where MHR
nwd
and EPR
nwd
indicate MHR and
EPR of a newly selected order for cost estimation,
respectively, in steps E2 and E3. In addition, R is a
coefficient to discount the flow rate by the next
order arrival if the newly arrived order is not
selected. It is calculated by Eq. (9) by the average
cost estimation period of orders within the cost
estimation process ED and the number of orders
within the process NE, where R=0 if NE=0.
NEEDNEEDEDR /11/)/( ==
(9)
Figure 2: Relations between MHR and EPR.
Then RFSM evaluates EPR’
max
indicating the
flow rate of maximum expected profits if nwd is
selected by Eqs. (10) or (11). Eq. (11) calculates the
value where MHRcp intersects the line connecting
the points of P’
E3
and P’
E2
based on the assumption
that there is linearity between P’
E3
and P’
E2
as is the
case of Eq. (4).
1) If MHR
E3
< MHR
CP
:
EPR’max ERP’E3 (10)
2) If MHR’
E2
< MHR
CP
< MHR’
E3
:
2
'
3
'
3
'
2
'
2
'
3
'
2
'
3
'
2
'
3
'
max
EE
EEEE
CP
EE
EE
MHRMHR
EPRMHREPRMHR
MHR
MHRMHR
EPREPR
EPR
+
=
(11)
Finally, the order nwd is selected for cost
estimation in the case of R×EPR
max
EPR’
max
or
MHR’
E3
MHR
CP
.
The former condition means that the flow rate of
expected profit EPR’
max
gained by selecting nwd for
cost estimation is higher than the flow rate of
expected profit R×EPR
max
gained by cutting nwd.
The later condition means that the flow rate of MH
for cost estimation including nwd, i.e., MHR’
E3
,
is
less than the maximum flow rate available in the
process.
4.2 Man-Hour Allocation Method
For the allocation of MH for cost estimation under
dynamic order arrival situations, we use a
dispatching method, as is the case of the dynamic
scheduling problem in production systems (Jacobs et
al., 2011) because the project cost estimation is
similar to the production.
Specifically, when MH is released from the cost
estimation of an order, this method selects an order
based on the MH allocation rules, which prioritize
orders in the queue of each estimate step. The
selected order is subsequently assigned the required
MH for its cost estimation step. If the required MH
is more than the MH available, the selected order
waits in the queue until the required MH is released.
Table 1 shows potential rules that could be
applicable for dynamic MH allocation in the project
cost estimation problem.
Table 1: Potential MH allocation rules.
Rule Description
FIFO
First-In First-Out: Order is selected on a first-in
first-out basis.
SDUF
Shortest DUe date First: Order remaining with
the shortest estimation period is selected.
SET
Shortest Estimation Time: Order having the
shortest estimation period is selected.
HEPF
Highest Expected Profit per MH First: Order
having the highest expected profit per MH for
cost estimation is selected.
5 NUMERICAL EXAMPLES
This section evaluates the performance of the
developed methods for managing the project cost
estimation process effectively by simulation
experiments. We use a general-purpose simulation
system AweSim! (Pritsker and O’Reilly, 1998) for
building a simulation model of the multistage project
cost estimation process.
5.1 Design of Simulation Experiments
In our simulation experiments, the performance of
the two order selection methods, i.e., the developed
method in this paper RFSM, and the existing method
TFM (Ishii et al., 2016b), are compared as two basic
cases shown in Table 2. Namely, 100 simulation
runs of a 120 period simulation length are performed
by each method, and the average expected profits
per 12 periods are compared.
P
E3
(MHR
E3
, EPR
E3
)
P
E2
(MHR
E2
, EPR
E2
)
MHR
CP
EPR
max
X
[MH/Period]
[$/Period]
Flow rate of MH fo
r
cost estimation
Flow rate of total
expected profits
Resource Flow based Order Selection Method in Project Cost Estimation Process
159
Table 2: Basic simulation case.
Order selection
method
MH allocation rule
Case A RFSM
HEPF
Case B TFM
The total volume of MH for cost estimation is set
as 16,000 [MH/Period] in reference to a mid-size
process plant EPC contractor. Furthermore, as the
MH allocation rule, the HEPF rule is used
throughout all the simulation experiments, because it
is reported that the higher expected profit is gained
by HEPF rule (Ishii et al., 2016b))
Three order arrival scenarios— scenario S1,
scenario S2, and scenario S3— based on the order
arrival intervals defined by the triangular
distribution, as shown in Table 3, are determined. In
each scenario, orders of the three sizes, i.e., Small,
Medium, Large, arrive dynamically. The total
periods for cost estimation, periods for cost
estimation in each step, and the volume of MH for
cost estimation are set as shown in Table 4. In
addition, two scenarios of expected profit of
accepted orders, i.e. scenarios I and II, are set as
shown in Table 5. Furthermore, as the probability of
order acceptance, the arrived orders are sorted into
grade H: 70%, M: 40%, and L: 10%. Regarding the
rate of the grade, grade M is set as 40%, and grade H
changes from 0% to 60%, and thus it changes from
60% to 0% in grade L accordingly in each
simulation experiment. The expected profit of each
order is computed by multiplying the value in Table
5 by the probability of order acceptance. For
example, if the arrived order’s grade is M (40%) and
the expected profit of the accepted order is 20
[MM$], the expected profit is 8 [MM$].
Regarding the threshold function used for
selecting orders in TFM, the order with the expected
profit per MH 35.0 [$/MH] and the volume of MH
under estimating cost 6,000 [MH] are set, i.e., the
threshold function P(350, 6000), by using the
algorithm developed by Ishii et al. (2016b), under
cost estimation conditions as follows;
1) order arrival interval: S2,
2) the expected profit of orders: I,
3) the rate of probability of order acceptance in
each grade: H:30-M:40-L:30 [%].
Namely, the newly arrived order is selected for
estimating cost by the threshold function in TFM
when its expected profit per MH is higher than 35.0
[$/MH] and MH under estimating cost is less than
6,000 [MH].
Table 3: Order arrival interval [Orders/Period].
Scenario o
f
order
arrival
Parameters of
triangular
distribution
Order size
Small Medium Large
S1
Min.
Mode
Max.
1.05
1.50
1.95
2.70
3.00
3.90
3.15
4.50
5.85
S2
Min.
Mode
Max
0.84
1.20
1.56
1.68
2.40
3.12
2.52
3.60
4.68
S3
Min.
Mode
Max
0.70
1.00
1.30
1.40
2.00
2.60
2.10
3.00
3.90
Table 4: Cost estimation conditions.
Order size
Small Medium Large
Total periods available
for cost estimation
Triangular distribution
(Min.: 4.0, Mode: 7.5, Max.:9.0)
Periods for
cost
estimation
E1
E2
E3
1.0
1.5
2.0
1.0
1.5
2.0
1.0
1.5
2.0
MH for cost
estimation
[M MH]
E1
E2
E3
1.0
2.0
3.0
2.0
3.0
4.0
3.0
4.0
5.0
Table 5: Expected profit of accepted orders [MM$]
(Mode of triangle distribution. Min. & Max. are -/+ 10%
of the mode value.)
Scenario of
expected profit
Order size
Small Medium Large
I
E1
E2
E3
1
10
20
2
20
40
3
30
60
II
E1
E2
E3
1
15
20
2
30
40
3
45
60
5.2 Results of Simulation Experiments
As shown in Figures 3 and 4, RFSM gains almost
the same or higher expected profit than that by the
existing TFM. Especially, RFSM performs well
when the rate of probability of order acceptance on
grade L is large. For example, in the case of 0-40-
60% in the rate of probability of order acceptance,
the expected profit by RFSM is increased 17.1%
compared to that by TFM as shown in Figure 3. On
the other hand, in the case of the expected profit by
TFM being better than RFSM, its difference is less
than 5.0% as shown in Figure 3 and 4. TFM uses the
fixed threshold function determined under the cost
estimation conditions shown in section 5.1
throughout the simulation experiments. We can say
SIMULTECH 2017 - 7th International Conference on Simulation and Modeling Methodologies, Technologies and Applications
160
that TFM could not maintain the performance when
the cost estimation conditions change dynamically.
In addition, RFSM has almost the same or higher
expected profit than that of TFM at all the rate of
probability of order acceptance in the scenario S1.I
where orders arrive less than the scenario S2.I. as
shown in Figure 5. For example, in the case of 0-40-
60% in the rate of probability of order acceptance,
the expected profit by RFSM is increased 23.8%
compared to that by TFM.
It is also obvious that the expected profit gained
by RFSM is expanded compared to that of TFM
when the conditions of the expected profit in each
step are changed to the scenario II as shown in
Figures 6 and 7. For example, in the case of 0-40-
60% in the rate of probability of order acceptance,
the expected profit by RFSM in scenario S2.I is
increased 17.1% compared to that by TFM as shown
in Figure 3, however it is 24.0% in scenario S2.II as
shown in Figure 6. In these cases, TFM cuts too
many orders because of the higher ratio of low profit
orders compared to the cost estimation conditions
that determines the threshold function of TFM.
Figure 3: Expected profits in scenario S2.I.
Figure 4: Expected profits in scenario S3.I.
Figure 5: Expected profits in scenario S1.I.
Figure 6: Expected profits in scenario S2.II.
Figure 7: Expected profits in scenario S3.II.
Furthermore, since RFSM determines the order
selection based on the changes of the resource flow
rate, which reflects the conditions of the cost
estimation process, we can say that the resource flow
based method is effective for the selecting order
50
100
150
200
250
300
350
400
Expected profit [MM$/Period]
RFSM
TFM
Rate of grade on order acceptance probability H-M-L) [%]
17.1%
4.3%
50
100
150
200
250
300
350
400
Expected profit [MM$/Period]
RFSM
TFM
Rate of grade on order acceptance probability H-M-L) [%]
5.0%
10.0%
50
100
150
200
250
300
350
400
Expected profit [MM$/Period]
RFSM
TFM
Rate of grade on order acceptance probability H-M-L) [%]
23.8%
50
100
150
200
250
300
350
400
Expected profit [MM$/Period]
RFSM
TFM
Rate of grade on order acceptance probability H-M-L) [%]
24.0%
50
100
150
200
250
300
350
400
Expected profit [MM$/Period]
RFSM
TFM
Rate of grade on order acceptance probability H-M-L) [%]
19.2%
Resource Flow based Order Selection Method in Project Cost Estimation Process
161
especially when the conditions of cost estimation,
such as order arrival intervals, the expected profit of
accepted orders, and so on, change dynamically.
In addition, RFSM needs no complicated
mechanism to determine the order selection rules as
TFM requires. Thus, RFSM can work by lower
computational loads than that of TFM. We can say
that the RFSM is simple and sufficient to be
implemented as an order selection mechanism in the
project cost estimation process in practical situations.
6 CONCLUSIONS
This paper explores the project cost estimation
process of EPC projects in dynamic order arrival
situations, and then it develops a model of
multistage project cost estimation process. Based on
the process, we develop a resource flow based order
selection method. It selects orders for cost
estimation at each order arrival according to the
changes of the flow rate of the contractor’s man-
hours for estimating cost and that of the expected
profits from the orders to maximize the total
expected profits from orders. We analyse the
effectiveness of the developed method in terms of
the expected profit through numerical examples.
The following conclusions can be drawn from
the analysis of the numerical examples:
For increasing the total expected profits from
orders in EPC projects, the resource flow based
order selection method is effective as an order
selection mechanism in the cost estimation
process.
The performance of the resource flow based
order selection method is obvious, especially,
in the cases where the cost estimation
conditions change dynamically.
Several issues require further research. For
example, a generalized algorithm of resource flow
based order selection method that extends the
coordinate points of cost estimate more than three to
correspond to the number of cost estimation steps
should be developed. Regarding the expected profits
from orders, the interrelationship of the order
selection method and the MH allocation rule should
be explored. Management technologies for an
advanced model of the cost estimation process that
changes the total volume of MH associated with the
backlog of orders should also be explored.
ACKNOWLEDGEMENTS
This work was supported by JSPS KAKENHI Grant
Number 16K01252.
REFERENCES
AACE International, 2011. Cost estimate classification
system – As applied in Engineering, Procurement, and
Construction for the process industries. AACE
International Recommended Practice No. 18R-97.
Humphreys, K. K., 2004. Project and cost engineers’
handbook, CRC Press. Boca Raton.
Ishii, N., Takano, Y., Muraki, M., 2014. An order
acceptance strategy under limited engineering man-
hours for cost estimation in Engineering-Procurement-
Construction projects. International Journal of Project
Management, 32 (3), 519-528.
Ishii, N., Takano, Y., Muraki, M., 2016a. A revised
algorithm for competitive bidding price decision under
limited engineering Man-Hours in EPC projects,
Oukan, Journal of Transdisciplinary Federation of
Science and Technology, 10(1), pp. 47-56.
Ishii, N., Takano, Y., Muraki, M., 2016b. A Dynamic
Scheduling Problem in Cost Estimation Process of
EPC Projects, Proceedings of the 6th International
Conference on Simulation and Modeling Methodolo-
gies, Technologies and Applications, 187-194, Lisbon.
Jacobs, F. R., Berry, W. L., Whybark, C. D., Vollmann, T.
E., 2011. Manufacturing planning and control for
supply chain management, McGraw-Hill. New York.
Kerzner, H., 2013. Project management: a systems
approach to planning, scheduling, and controlling,
John Wiley & Sons, New Jersey.
Pritchard, N., Scriven, J., 2011. EPC contracts and major
projects, Sweet & Maxwell, London, 2
nd
edition.
Pritsker, A. A. B., O’Reilly, J. J., 1998. AWESIM: The
integrated simulation system. Proceedings of the 1998
Winter Simulation Conference, 249-255. Washington,
D.C.
Shafahi, A., Haghani, A., 2014. Modeling contractors'
project selection and markup decisions influenced by
eminence. International Journal of Project
Management, 32 (8), 1481–1493.
Takano, Y., Ishii N., Muraki, M., 2014. A sequential
competitive bidding strategy considering inaccurate
cost estimates. OMEGA, 42 (1), 132-140.
Takano, Y., Ishii, N., Muraki, M., 2016, Bid markup
decision and resource allocation for cost estimation in
competitive bidding, Optimization Online.
Takano, Y., Ishii, N., Muraki, M., 2017. Multi-Period
resource allocation for estimating project costs in
competitive bidding, Central European Journal of
Operations Research, 25 (2), 303-323.
Towler, G., R. Sinnott, R., 2008. Chemical engineering
design principles, practice and economics of plant and
process design, Elsevier. Amsterdam.
SIMULTECH 2017 - 7th International Conference on Simulation and Modeling Methodologies, Technologies and Applications
162