Revisiting the Highland Towers: Has the Judicial Tide Subsided?
Abdul Mu’iz Abdul Razak
Faculty of Law, Universiti Teknologi MARA, 40450 Shah Alam Selangor, Malaysia
Keywords: Construction, Court, Industry, Risks, Works.
Abstract: This paper aims to look into the treatment of the Malaysian courts in cases of defective works in the
construction industry with guidance from the Higland Towers tragedy, specifically the High Court case of
Steven Phoa Cheng Loon v Highland Properties Sdn Bhd. Through the decisions of the Malaysian courts
coupled with industry practice, the analysis might shed some light as to the direction of the Malaysian
construction industry. A doctrinal analysis is employed to ascertain the attitude of Malaysian courts towards
cases involving defective works. The purpose of this study is to analyse the current trend in Malaysian courts
and industry practice in dealing with defective works in the construction industry. Further, the analysis will
be utilised to provide guidelines to constrution industry players to ensure that possibility of defective works
is minimized and how best to deal with defective works appearing in the construction project. This paper
concludes with the recommendation for the construction industry players to adopt proper industry practice
with guidance as provided by the Malaysian courts in order to reduce the risk of defective works in
construction projects.
1 INTRODUCTION
Generally, a defect would mean that the contractor
failed to achieve a certain standard of workmanship
or failure to comply with requirements as to materials
to be used as set out in the construction contract.
Nevertheless, each construction contract might differ
in detail as to what amount to a defect or defective
works. These defining clauses, in whatever form,
would be scrutinised by the courts to comprehend
whether the situations as alleged by the parties to the
contract as being defective works or otherwise a mere
rectificable minor flaw. In both circumstances, it is
common in the industry that the contractors are left
with generally two choices: whether to offer
themselves for rectification works or come to an
agreement as to a settlement sum. The trend in other
commonwealth countries, especially in Australia is
that the contractors prefer to opt for rectification
works because then they would have more control
over the scope of work and that the situation would
be more familiar to them and would potentially
involve lesser rectification time and ultimately, lesser
cost (Campbell, 2018).
It should be noted on the outset that the
contractors have the implied obligation to ensure that
the works they carried out is in accordance with the
contract in a reasonable and safe manner while
ensuring that the end product is of good and
acceptable quality. One of the manner in which this
implied obligation would be breached is that if the
materials supplied and eventually used is defective
(Cremean & Ozer, 2018). By extension, this would
also mean that the defective works are not just
looking into the failure to comply with the standard
of workmanship, but goes beyond that by looking at
the possibility of using materials that are not suitable
for the purpose of the construction project, taking into
consideration various factors including the climate
condition, geographical location and project costs.
The Malaysian Construction Industry, despite
being a multi-billion ringgit industry, is still tainted
with the image and an overall fear of the end-user that
the completed project will be streamed with defects
and if the matter worsen, there will be years of dispute
resolution process because the parties to the
construction projects will refuse to take responsibility
of the defective works. This is not surprising as each
construction project has its own unique
circumstances, be it design, site conditions, cost and
parties involved (Ahmad Rashid, Jamaludin, &
Hussin Amin, 2014). This results in the subjective
consequence of each particular construction project,
be it in a positive or negative manner. Eventually,
208
Razak, A.
Revisiting the Highland Towers: Has the Judicial Tide Subsided?.
DOI: 10.5220/0010053702080211
In Proceedings of the International Law Conference (iN-LAC 2018) - Law, Technology and the Imperative of Change in the 21st Century, pages 208-211
ISBN: 978-989-758-482-4
Copyright
c
2020 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
when the relationship of the parties turned sour due to
the defective works, the dispute resolution
mechanism chosen by the parties would have the
chance to look into the matter and should the parties
were unsatisfied with the decision, ultimately the
courts would have to assess these particular
consequences in order to come to provide judgements
for each case.
The above discussion centred mainly on the fact
that the parties to the dispute of the alleged defective
works were in fact parties to the construction
contract, but what if this was not the case all the time?
What if the end user of the premise has no contractual
relationship with contractors who were involved in
the construction of the building in the first place and
are somehow directly affected by the defective works
prevalent in the completed project? In this situation,
tort claims has been held to be allowed in certain
jurisdictions (Xavier, 2001). It is understandable that
a contractor owes a duty of care to lawful occupiers
of the completed building, albeit the latter were not
the initial contractual parties. Further, this duty stems
from the idea that the contractor must ensure that the
completed building has been carefully constructed.
The scope of this study is to look into the basis of
claims for defective works by first looking into Steven
Phoa Cheng Loon v Highland Properties (2000). The
study will then proceed to look at the trend of the
Courts in dealing with defective works appearing
during the Defects Liability Period (DLP) and after
Certificate of Practical Completion (CPC) has been
issued. There is a vacuum of literary works focusing
on the attitude of the Courts towards defective works
in Malaysia and the objective of this paper is to
address this particular vacuum and analyse the trend
to provide guidelines to construction industry players.
2 MATERIALS AND METHODS
This is a legal research paper and the materials are
collected through extensive case law and library
research. A doctrinal approach is undertaken to identity
the key theme in the judgments on Malaysian Courts
with regards to cases involving defective works in
construction projects. “Defective works” in itself is a
wide subject in the construction industry scene, steps
are taken to ensure that the emphasis of this paper
would be on how the Courts reacted to cases involving
defective works and how they analyse each particular
case by employing different principles of law. Further,
the judgements will be scrutinised to ensure the Courts
employ the appropriate principle of law, which might
help in shedding some light as to which directions
Malaysian Courts should steer its decision-making
process. Data will be collected from court decisions,
journal articles, standard form contracts as well as
government regulations and policies involving
construction and building bodies in Malaysia.
3 RESULTS AND DISCUSSIONS
There is an overall repulse of the Courts to actions of
the construction industry players, involving but not
limited to, contractors, architects, engineers, and
quantity surveyors, which resulted in the defective
works in construction projects. Despite this being so,
very little has been done to ensure that the cases are
not repeated in future situations. It is interesting to
note that there are provisions both in current
legislations and in the contracts between the parties to
the construction project addressing the issue on
defective works, provided there are written agreement
in the first place. Nevertheless, in reality, there is very
little emphasis by the parties to the construction
project to the content of the contract with regard to
defective works until after there are disputes between
them. Recourse to the content of the contract and the
construction of the various clauses is necessary in
most situations in order to ascertain whether there is
in fact defect in the construction works. This is
particularly so because to ascertaining whether there
is actual defect is a technical and difficult question.
(Bailey & Bell, 2011)
In Steven Phoa Cheng Loon v Highland
Properties (2000) or otherwise known as the
“Highland Tower” case, the High Court had the
opportunity to address the defective construction
works, which is considered one of the worse in
Malaysian history, while commenting on the
conducts of the professionals involved in the project.
It involved a development project consisting of three
blocks of apartments with a steep hill adjacent to the
towers and a stream flowing around the vicinity. On
one tragic day of 11 September 1993, Tower 1
collapsed and claimed the lives of 48 occupants.
Tower 2 and 3 were then immediately vacated, which
caused major monetary losses to the occupants.
Several legal issues were raised before the court,
among others is with regard to the negligence of the
first defendant to completely implement the approved
drainage plan that should have been the solution to
the flow of stream. This is because the Court found
that the root cause of the collapse was the presence of
water in the foundational structure, which failed to
accommodate the lateral load and leads directly to the
destabilization of the slope. Should the first defendant
Revisiting the Highland Towers: Has the Judicial Tide Subsided?
209
acted and conducted the project in accordance to the
approved drainage plan, the disaster would be able to
be avoided. The approved drainage plan was found to
be implemented up to only 10% out of the whole plan,
despite the defendants reported to the authorities that
the approved drainage plan was complied with and
implemented entirely.
It is obvious from the case and the judgment of the
Court that the defendants, inclusive of the contractor,
architect and engineer, failed to achieve the relevant
standard of workmanship of the construction project.
The sole motivation for the defendant to disregard the
approved plan and the subsequent false notice of
compliance was for prospective financial gains. In
this regard, it prompted the then Justice James Foong
to hold as follows:
I have reiterated my strong sentiments against this
type of attitude of professionals whose only
considerations is to guard and secure their own
interest rather than their duties and obligations to
those closely affected and the public on which much
faith and reliance are placed on them to carry out
their professional duties. I need not elaborate further
except to remind this defendant that he has to live out
the rest of his life knowing truly well that he
contributed to the tragedy of Highland Towers (Steven
Phoa Cheng Loon v Highland Properties, 2000).
In the Highland Towers, it is important to note that
the High Court was very displeased as to the direct
involvement of the defendants to the defects in the
project. For example, there was evidence that the
second defendant, as the engineer, did not exercised
care in relation to the design and construct of the
foundational structure as to accommodate lateral load
while taking steps to guarantee the stability of the
slope adjacent to the towers. Failure of the second
defendant to do as required as the engineer and to
exercise care not only was an obvious breach of duty,
but proof of the fact that the defendant failed to
achieve a proper standard of workmanship as required
by the contract.
Furthermore, in the Highland Towers case, the
actions raised mainly from the basis of tort of
negligence whereby the plaintiffs sued various
parties, which contributed, either directly or
indirectly, to the defective works. Contrastingly, in
the High Court case of KC Leong Holdings Sdn Bhd
v Datin Moh Lee Bing (2015), it features a contractual
relationship between the parties, and consequently
claims under torts, despite were briefly discussed,
were dismissed. Damage suffered by the defendant in
this case is in the nature of pure economic loss where
the building is allegedly built defectively but caused
no damage other than to the building itself. The
defendant alleged that the buildings were constructed
negligently and were not fit for the purposes of
occupation. However, it is to be noted that the High
Court has taken the view that the proper cause of
action in this case should be premised under breach
of contract instead of breach of tortious duty of care
as alleged by the defendant. This is also supported by
the fact that the defendant’s concluding submission
featured a claim under s.74 of the Contracts Act and
not one under tort of pure economic loss. The trend in
this case is that there is an indication in the judgement
of the court that it is recommended for claims on
defective works to be based on breach of contract
despite the convincing nature of tortious duty of care.
It is refreshing to have a simple case like this which
serves as a reminder that the first avenue of which the
Court will scrutinize in the event of construction
dispute involving defective work is the duty arisen in
the contract between the parties and not the duty
which may arise under tort.
KC Leong Holdings Sdn Bhd v Datin Moh Lee
Bing (2015) also touched on an important issue with
regard to defective works. What happened if the
defects are discovered after the defect liability period
has lapsed? Firstly, is there a defects liability period
clause? If not, then the Court will not ordinarily imply
such a clause in the contract between the parties.
Secondly, referring to a Court of Appeal case of Toh
Ang Poo (t/a Poo Wah Enterprise) v Jasin
Construction Development (M) Sdn Bhd (2014), the
Court ruled that the right to claim under defects
liability period clause do not supplant the right to
claim for damages. They are, in fact, an addition to
the right to claim for damages. Hence, Toh Ang Poo
(t/a Poo Wah Enterprise) v Jasin Construction
Development (M) Sdn Bhd (2014) did not generally
establish that once defects liability period has lapsed,
contractor’s liability for defective works would cease,
and should there be defective works attributable to the
contractor, the principal would still reserve the right
to claim for damages within the limitation period
prescribed by the Limitation Act 1953.
In Toh Ang Poo (t/a Poo Wah Enterprise) v Jasin
Construction Development (M) Sdn Bhd (2014), the
Plaintiff in this case claimed for rectification costs for
defective works which were discovered within the
defects liability period. Defendant, on the other hand,
claimed that there were no defects and even if there
were any, it had been made good during the defects
liability period. This is because the Plaintiff had
certified all the Defendant’s works and made full
payment. There were grave discrepancies in the
allegation of defective works. For example the
Plaintiff alleged in November 2007 that the manholes
iN-LAC 2018 - International Law Conference 2018
210
were constructed without the cast in-situ concrete
surrounds, which if were to be true, it would not be
considered as defective works but rather a serious
ommission, hence an incomplete work. This is
bearing in mind that the consultant engineer had
issued the Certificate of Practical Completion (CPC)
in November 2006, one year prior to the allegation
made in November 2007. Since there was no
allegation of negligence of consultant engineer in
issuing the CPC, such defective works remained as
allegation and not proven. This indicates that CPC by
the consultant engineer serves as more than just
indicating that the there is completion of the
construction works but also as a proof that should
there are defective works, such certification would
not be issued.
The Federal Court in Juara Serata Sdn Bhd v
Alpharich Sdn Bhd (2015) took the chance to remind
construction industry players that with regard to the
defective works, the parties to the construction
contract must firstly refer to the terms of the
agreement and should it provided for the procedures
to address for the defective works, it must be
followed. In this case, the Appellant alleged defective
works against the Respondent, and according to the
written agreement, the former must provide written
instructions to the latter to make good the defects.
However, the Appelant engaged a third party
contractor to “remedy” the alleged defects and claim
the cost of such remedy works from the Respondent.
The Federal Court affirm the position held by both the
High Court and the Court of Appeal that the first
avenue to determine the rights and obligations of the
parties is the contract and the construction contract in
this case had provided for the procedures in the event
of defective works. Principal, or employer in this
case, cannot simply straightaway hire a third party
contractor to rectify the defects and claim such costs
to the original contractor.
4 CONCLUSION
It can be deduced from the words of the then Justice
James Foong in Steven Phoa Cheng Loon v Highland
Properties (2000) about the repulse and the overall
inclination of the courts in addressing the unethical
conduct of construction professionals of such
magnitude, which directly caused the defects in the
construcion project and eventually lead to the death
of the occupants and in most cases, caused the end-
product user some serious safety issues.
The judicial tide after the tragedy of the Highland
Towers is that there is a growing concern as to the
standards of workmanship and overall safety to the
end-product user. Attitude of the courts in shaping the
law with regards to defective works in construction
projects has been positive in the sense that the courts
are ready to read into the contract the obligation of the
contractual parties to ensure the project achieve a
minimum standard of workmanship, which would
ultimately ensure risk of defective works would be
minimised.
ACKNOWLEDGEMENTS
The writer would like to express his gratitude to I-
NLAC2018 for organising this conference. The writer
would like to express his deepest appreciation to the
Faculty of Law, UiTM Shah Alam for the assistance
in preparing this paper. The writer would like to thank
this family and close friends, colleagues at the Faculty
of Law, librarians at Perpustakaan Undang Undang,
Perpustakaan Tun Abdul Razak, UiTM and all who
are directly and indirectly assisted in preparing this
paper.
REFERENCES
Ahmad Rashid, Z. Z., Jamaludin, N. E., & Hussin Amin, A.
A. (2014). Managing construction latent defect
contractually. Malayan Law Journal Articles, 5, lxxxi.
Campbell, G. (2018). Big choice in rotten apples: to pay or
to rectify latent residential. Australian Construction
Law Bulletin, p. 70.
Cremean, D. j, & Ozer, N. (2018). ( 4 ) Content And
Construction Of Building Contracts. Halsbury’s Laws
of Australia (p. 550).
Bailey, I. (2011) Construction Law in Australia. Australia:
Lawbook Co.
Juara Serata Sdn Bhd v Alpharich Sdn Bhd, Malayan Law
Journal 773 (Federal Court Putrajaya September 8,
2015 )
KC Leong Holdings Sdn Bhd v Datin Moh Lee Bing,
Malayan Law Journal 10 (High Court Shah Alam June
30, 2014)
Stephen Phoa Chen Loon & Ors v Highland Properties Sdn
Bhd & Ors,
Malayan Law Journal 200 (High Court Kuala Lumpur
August 11, 2000)
Toh Ang Poo (t/a Poo Wah Enterprise) v Jasin Construction
Development (M)
Sdn Bhd, Malayan Law Journal 192 (Court of Appeal
Putrajaya November 7, 2013)
Xavier, G. (2001). Donoghue v Stevenson - A New FaÇade
for the Construction Industry? Malayan Law Journal
Articles, 2, 65.
Revisiting the Highland Towers: Has the Judicial Tide Subsided?
211