The Suitability of the Use of Mediation in the Settlement of
Construction Disputes in Malaysia
Nur Ezan Rahmat
1
and Nazirah Abdul Rahim
2
1
Faculty of Law, Universiti Teknologi MARA (UiTM), 40450 Shah Alam, Selangor, Malaysia
2
Eastlink Consulting, B-3A-12 Gateway Kiaramas, No. 1 Jalan Desa Kiara, Mont Kiara, 50480 Kuala Lumpur, Malaysia
(Nurezanrahmat,nazirahim)@gmail.com
Keywords: Alternative Dispute Resolution, Construction Dispute, Mediation.
Abstract: Construction projects are increasingly complex, resulting in complex contract documents. Complex
construction projects can likewise often result in complex disputes, which mainly arise from the intricacy and
magnitude of the work, multiple prime contracting parties, poorly prepared and/or executed contract
documents, inadequate planning, financial issues, and communication problems. Traditionally, resolving
construction disputes were predominantly relied on adversarial approach. The result is often leads to delay
and cost, not to mention escalation in the maintenance of a harmonious relationship between parties. In the
Malaysian construction industry, the present practice of Alternative Dispute Resolution (ADR) is focusing
mainly on arbitration and most recently adjudication. However, with mediation clauses regularly incorporated
into the standard forms of construction contracts and the introduction of Malaysia Mediation Act 2012,
mediation is also set to be one of the main mechanism in resolving construction disputes in Malaysia. This
article highlights the application of mediation as an alternative route in construction dispute resolution in
major construction standard form of contracts in Malaysia. It is also aims to give the readers an overview of
the suitability in application, advantages and disadvantages of mediation in construction dispute.
1 INTRODUCTION
The construction industry is one of the mainstays of a
country’s economic progress. However, construction
dispute is found to be a very common issue in
construction industry and it has brought negative
impacts to each of the participants in a construction
project.
The nature of construction industry is such that
will always be disputes between various contracting
parties. Disputes are something that construction
project personnel will have to face several times
during the life of a project and it may continue long
after a project has ostensibly finished. Carmichael
(2002) and Singh (2009) found that the contracting
parties in construction project are basically working
for a common target of completing the project which
shows that they are not in competition with each
other, but, different of opinions and conflicts do arise
at times. Immaturity and unhealthy discussions do
expedite the parties into conflicts and disputes.
It was argued that a conflict is actually a catalyst
which can create dialogue, promote creative thinking,
and inspire people to sustainable solutions if a
conflict is able to be well-handled (Richbell, 2008). A
conflict or dispute can be settled by a free frank
discussion if it is handled expeditiously in a mature,
non-emotional manner with a judicious approach
(Singh, 2009). Therefore, Cox & Thompson (1998)
contended that disputes should be avoided. If it is not
possible to be avoided, disputes must be minimized
or resolved as efficiently as possible because disputes
are always wasteful for organization’s resources.
Dispute prevention, flexibility, early dispute
intervention, use of alternative dispute resolution
methods, and a predetermined plan as to how disputes
will be handled are identified as the best practices for
resolving construction disputes (Cox & Thompson,
1998 and Winkler, 2009).
Dispute may be defined as a class or kind of
conflict, which manifests itself in distinct and
justifiable issues (Bower, 2003). However, Fulton
(1989) alleged that conflict and dispute are not
synonymous although the two words are used
interchangeably. Conflict means an inter-reaction
between people who are pursuing incompatible or
competing claims, and in fact conflict is the precursor
to a dispute (Fulton, 1989). A contractual dispute
118
Rahmat, N. and Rahim, N.
The Suitability of the Use of Mediation in the Settlement of Construction Disputes in Malaysia.
DOI: 10.5220/0010054001180124
In Proceedings of the International Law Conference (iN-LAC 2018) - Law, Technology and the Imperative of Change in the 21st Century, pages 118-124
ISBN: 978-989-758-482-4
Copyright
c
2020 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
arises when one party claims something, and the other
party rejects the claim, or disagrees over liability
either expressly or by conduct (Carmichael, 2002). It
is also stated that, when a claim or assertion made by
one party is rejected by the other party and that
rejection is not accepted, the dispute arises
(Kumaraswamy, 1997). Conflict management is
important to prevent a conflict turns into a dispute.
However, disputes are still occurring as a result of
conflict escalation. Therefore, dispute resolution
plays a crucial role at most of the time, especially in
construction industry which is widely known as a
risky business.
Wright (2004) stated that a disagreement in any
of a construction project must be settled quickly
before it develops into a dispute. Emmitt (2010) also
found that conflict is necessitate to be managed so
that it does not suppress information or become
personal and affect relationships. According to
Murdoch and Hughes (2008), contractors are very
keen to preserve a good relationship with clients.
Therefore, some of the parties will often seek
effective and quick resolution on points of
disagreement even if that implies giving up a claim
that would have good chances to succeed in court for
the sake of future business.
(Murdoch & Hughes,
2000).
Disputes are wasteful of a firm’s resources and
therefore should be avoided, wherever possible (Cox
& Thompson, 1998). This is because, the nature of
dispute is costly, lengthy, and complex and eventually
the cost of resolving the dispute always exceeds the
amount of the initial claim (Feld & Carper, 1997). An
owner will suffer the additional costs such as
increased financing costs, increased architectural and
engineering costs, lost revenue, and incurrence of a
delay claim from the contractor for his increased costs
of performance if a dispute is not resolved efficiently.
On the other hand, as the impact of construction
dispute, a contractor will also suffer additional costs
such as increased labour costs, costs of extended
equipment usage, additional construction financing
expenses, additional cost of extended home and field
office overhead, and lost revenue (Rossi, 1991).
Resolution of disputes always consumes much of
the construction professional’s time than is usually
justifies. From the point of filing of a legal claim by a
contractor, the time required to follow the legal
settlement process consumes valuable time that can
usually be spent more profitably in other areas of the
organization’s work (Stephenson, 1996). Edgerton
(2008) also agreed that the contract disputes are
lengthy and costly to all of the contracting parties.
These adversarial disputes severely degrade
productive working relationships and consume time
and money.
It is very often to see the disputes between
contractors and owners escalate into litigation, or the
contractors may absorb a major loss in order to avoid
lengthy disputes proceedings and damaged business
relationships (Pinnell, 1998).
Edgerton (2008) encouraged for the disputes to be
resolved at the lowest possible level so that the
dispute escalation may be eliminated. For example, a
dispute might first be taken to the superintendent or
the inspector at the field level. Then, it would be
escalated to the project level and the project manager.
Next, if it still could not be resolved at that level, the
dispute could move to the executive level.
Subsequently, the final step would be arbitration or
litigation with an outside party facilitating resolution.
2 DISPUTE RESOLUTION IN
THE CONSTRUCTION
INDUSTRY
The construction industry is regarded as one of the
most conflict and dispute ridden industries, which has
resulted in it being one of the most claim orientated
sectors. Traditionally, parties would enter into
litigation, often a costly and longwinded means of
resolving a dispute. Over the years, various methods
of ADR have been introduced into the construction
industry as mechanisms to avoid lengthy and
expensive litigation.
2.1 Adjudication
In certain types of contract, adjudication is a
mandatory pre-step before final process may be
commenced (Simmonds, 2003). The adjudication
process usually commences when it is more to be
achieved by discussion and negotiation, and that the
issue is important enough to warrant the time and
expense of adjudication. In addition, the dispute may
involve matters claimed by either or both parties
(John, 2008). One of the benefits of adjudication is
that it can often lead to a settlement without the matter
going any further due to the party that has lost in
adjudication will think very carefully before
proceeding with very expensive litigation or
arbitration. They might well lose again, with the
additional penalty of paying the other side’s costs
(Ashworth & Hogg, 2007).
The Suitability of the Use of Mediation in the Settlement of Construction Disputes in Malaysia
119
2.2 Arbitration
Fisher (2017) stated that binding arbitration is by far
the most often used alternative to litigation in
construction disputes, and arbitrated construct on
hearings usually involve two parties who are having
a contract dispute and an arbitrator they jointly
choose to resolve the dispute. It is also found that an
arbitrator is usually someone familiar with the
construction industry and most large claims involve
three arbitrators instead of one. Arbitration in
construction is usually performed by experts in the
construction industry such as architects, engineers, or
construction management professionals (Fisher,
2017). Wright (2004) identified that arbitration is a
better route than litigation for solving serious disputes
because an arbitrator with appropriate knowledge and
experience must always have a greater chance of
understanding the complex engineering or process
questions that are likely to arise than a court.
2.3 Dispute Review Board (DRB)
According to Edgerton (2008), dispute review board
is a panel of three experts from construction industry
who follow the progress of a construction project by
visiting the site and attending project meetings. The
conditions precedent for establishing DRB are
usually described in the contract documents. The
owner, contractor and members of dispute review
board have to sign a three-party agreement before
using the DRB to resolve any disputes while
construction is ongoing. Selection of the DRB
members is critical and several selection processes
are available. Normally the board members
themselves will choose the chairperson. By reaching
this consensus process, the perception of any board
members being biased can be avoided (Edgerton,
2008).
2.4 Expert Determination
Expert determination is carried out primarily in a
technical nature of disputes. The expert is required to
use his or her own skills and knowledge to make
necessary enquiries or conduct their own
investigations. The process of expert determination
usually provides a fast and final solution to the
matters in dispute and has been used successfully for
many years in property disputes concerning
valuations (Ramsey, Minogue, Baster & O’Reilly,
2007). The use of expert determination has been
encouraging, particularly for single issue, essentially
technical or valuation and disputes. This is because an
expert can bring his experience and professional
knowledge directly to resolve a dispute. Moreover,
technical issue is proven extremely difficult for a
legal arbitrator or arbitral tribunal, even when assisted
by expert witnesses (Ramsey, Minogue, Baster &
O’Reilly, 2007).
2.5 Negotiation
Negotiation is the art of reaching an agreement or
understanding through bargaining. There are no
formal rules for negotiation, but it is culturally
accepted style (Carmichael, 2002).
Since there are no formal rules, the procedures of
negotiation begin by setting up a forum so that the
parties can attempt to find a way out of the problem,
looking for mutual benefits that can be gained from
resolving the problem in a different way, or look for
compromises in order to overcome the problem
(Egbu, Ellis & Gorse, 2004). Wright (2004) identified
that negotiation is always going to produce the best
chance of a satisfactory solution to any dispute since
it is quick and the bruising encounters that come with
arbitration, litigation or adjudication can been
avoided. If there is an event that complete satisfaction
could not be reached, the objective of negotiation is
to reach a solution that will be acceptable to both
parties. The advantage of negotiation is the cost of
both sides is very much less if compared to other
dispute resolutions and the money that does not have
to go in legal fees can then go towards funding the
settlement (Wright, 2004).
The prevalence of construction dispute indicates
that the current approach to dispute resolution is not
effective enough. First, construction contracts tend to
address dispute resolution by specifying the
resolution methods to be used. Second, dispute
resolution methods are too frequently viewed as a
selection of stand-alone choices. What construction
contract and the persons drafting these frequently
overlook is that dispute prevention and dispute
resolution methods can be effectively combined into
more comprehensive dispute prevention and
resolution processes, where the benefits of synergy
can be exploited to successfully prevent or resolve the
dispute.
3 MEDIATION IN THE
CONSTRUCTION INDUSTRY
Mediation is a method of dispute resolution involving
a neutral third party who tries to assist the disputing
parties in reaching a mutually agreeable solution
iN-LAC 2018 - International Law Conference 2018
120
(Klinger & Susong, 2006).
Mubarak (2010) revealed
that the mediator can be an individual or a team.
A preliminary meeting will be arranged by the
neutral third party to discover the substance of the
dispute and to decide how best to proceed with a
mediation (Ashworth & Hogg, 2007). In the essence,
a mediator must demonstrate neutrality and patience,
and must collect all the facts before making any
recommendation (Mubarak, 2010). Fenn, O’Shea &
Davies (1998) found that the mediation has proven to
be most effective when used immediately after the
parties have determined that conflict management
techniques have failed and it has been highly
successful in resolving construction disputes at a
fraction of the time and expense required for
litigation.
In the Malaysian construction industry, the
practice of mediation is not new and has persistently
being as part and parcel of the industry. Even though
it has been introduced by several standard forms of
contract, the use of mediation in Malaysia has not
been considered popular. Contrary to other developed
countries such as Australia, Hong Kong, Singapore,
United Kingdom and Kuwait, mediation process has
been recognized as one of the popular techniques of
dispute resolution.
The Chairman of the Mediation Committee of the
Bar Council Malaysia emphasised that business
industry should actively adopt mediation in settling
business related disputes. Mediation process can ease
in reducing the agglomeration of commercial cases
waiting to be judged in the court for the purpose of
expedition in the process of resolution. At its best,
mediation is getting perceived to be one of dispute
resolution techniques for settling construction
disputes.
However, in Malaysian construction industry,
mediation is not a popular method compared to other
types of ADR such as arbitration and adjudication.
Although there are efforts to introduce mediation in
construction industry through several standard forms
of contract, its usage in Malaysia is considerably low
(Arain & Low, 2007).
Mediation is also known as a private, informal
process in which parties are assisted by one or more
neutral third parties in their efforts towards
settlement. The new and distinguishing feature here
is the addition of a neutral third party who aids the
parties in dispute towards settlement. A further
important factor is that the mediator does not decide
the outcome; settlement lies ultimately with the
parties (Rahmat, 2017).
A distinction is often made between styles of
mediation that are facilitative and those that are
evaluative. During a facilitative mediation, the
mediator is trying to reopen communication between
the parties and explore the options for settlement. The
mediator does not openly express his opinions on the
issues. If, on the other hand, the mediator is called
upon to state his or her opinion on any particular issue
then he is clearly making an evaluation of that issue.
3.1 Mediation Clause in Malaysian
Standard Form of Construction
Contract
Mediation can be classified into two types: mandatory
mediation and optional mediation. The former is
when the parties are by court sanction or by
agreement between the parties make it mandatory for
the parties to attempt mediation to settle the dispute
between them and the later, is an option between the
parties. For example, in the context of standard
construction contracts, Malaysian Institute of
Architects (MIA) Standard Form for Building Works
2006 provides for an optional mediation under Clause
35 whereas the Construction Industry Development
Board (CIDB) Standard Conditions of Contract for
Building Works (2000) provides for a mandatory
mediation where the parties must first attempt
mediation and can only commence arbitration in the
event that the mediation fails. On the other hand,
under Clause 35 of Asian International Arbitration
Centre (AIAC) Form of Contract 2017, it appears to
have similar principle to MIA 2006.
In general, the parties to a dispute will most likely
not resort to mediation if the agreement only provides
an option for the parties to do so or for one of the
parties to initiate the process. The trend is however
towards the enforceability of mediation clauses. In
England, the courts had held that if a party to the
contract which contains a mediation (ADR) clause
commences legal action, costs would not be awarded
to his favour if he did not attempt mediation or ADR.
(
see Dunnett v. Railtrack Plc (In administration)
[2002] 2 All ER 850. See also Cable & Wireless Plc
v. IBM UK Ltd [2002] 2 All ER 1041.
Further, in a multi-tiered dispute resolution
clause, it can be said that an attempt at mediation is a
condition precedent to the commencement of the
remaining binding dispute resolution mechanism in
the clause itself, frequently arbitration.
There are pitfalls and problems that can arise in
enforcing poorly or badly drafted mediation clauses.
Boulle & The (2000) have helpfully listed that the
following factors should be paid due attention by
draftspersons of mediation clauses:
i. mediation clauses should be clear and
certain in their own right, or it should be
possible to derive certainty from extrinsic
The Suitability of the Use of Mediation in the Settlement of Construction Disputes in Malaysia
121
documents expressly referred to in the
clauses;
ii. they should be complete and
comprehensive;
iii. they should specify the procedures to be
followed by the parties in setting up and
undertaking the mediation, with some
reference to the identity of the mediator and
timetables to be followed;
iv. alternatively, they should incorporate by
reference the Mediation Agreement or
Mediation Rules of an agency providing
mediation services;
v. they should uphold the non-ouster principle
by stipulating that the parties should first
submit their dispute to mediation before they
institute court proceedings; and
vi. they should avoid provisions requiring
participation in good faith.
With a good and clear mediation clause incorporated
into a construction contract, it will help the disputing
parties to decide when the problem arises.
3.2 Mediation Act 2012
In Malaysia, Mediation Act 2012 has received the
royal assent on 18 June 2012 and was gazetted on 22
June 2012. The act was enforced by the ministry in
August 2012 and has been applied in order to promote
and encourage mediation as a method of ADR.
In the absent of any specific Mediation Rule
mentioned in a construction contract, the Mediation
Act 2012 seeks to facilitate this mediation process.
Generally, the parties are free to agree on the
appointment of any person as their mediator. If parties
cannot come to a consensus, they can request the
Malaysian Mediation Centre of the Bar Council
(MMC) to appoint a qualified mediator from its panel.
According to the Mediation Act 2012, parties may
resort to mediation either before or during the court
proceeding (section 4). In fact, it is in the Practice
Direction No. 4 of 2016 (Practice Direction on
Mediation), issued by the Chief Registrar of the
Federal Court of Malaysia, which mentioned that
judges may encourage parties to settle their disputes
even after a trial has commenced.
Disputing parties may decide the terms of
mediation. Preferably, parties may come out with a
mediation agreement in writing and signed by both
parties setting out the terms of mediation. For
instance, in respect of which mediation forum to go,
parties’ choice of mediator, as well as express term
that mediation communication is to be treated with
utmost confidentiality and privilege from court
proceedings.
Mediator shall have no decision-making power
whatsoever. He shall only play the role in facilitating
communications and negotiations between parties
and in identifying their needs, and developing options
amongst them for amicable solution.
All disclosures, communications and even
admissions made under a mediation session are
strictly without prejudice or privilege. It is not subject
to discovery or be admissible in evidence in any
proceedings unless parties consented to it. It shall be
noted that regardless of choice of forum, parties must
fix a return date of not more than one month from the
date the case referred to mediation to report to the
court on the progress and outcome of mediation.
(Practice Direction No. 4 of 2016)
3.3 The Roles of AIAC and MMC
In Malaysia, the construction court has been
established in Selangor and Kuala Lumpur on 1 April
2013 in which it operates to assist the administration
and instantly resolved any matters or cases regarding
construction or connected with construction. Prior to
that, Malaysian Bar has established the MMC in 1999
to introduce mediation in order to provide a proper
solution for successful dispute resolutions and to
provide avenue for successful dispute resolutions.
The centre provides mediation services and trained
mediators who have been accredited and appointed to
the Panel of Mediators of the MMC.
In 1978, The Kuala Lumpur Regional Centre for
Arbitration (KLRCA) was established and offers
facilities and assistance for the conduct of arbitral
proceedings, including the enforcement of awards
made in the proceedings held under the auspices of
the Centre. The Rules for arbitration under the
auspices of the Centre are the UNCITRAL
Arbitration Rules of 1976 with certain modifications
and adaptations. The Centre provides mediation
services and rules which allows the parties to freely
choose their mediator or from its list of accredited
mediators, or failing which the Director of the Centre
shall assist in the appointment of mediator. Recently,
KLRCA has changed its name to AIAC.
3.4 Advantages and Disadvantages of
Mediation in Construction Dispute
Mediation is faster and less expensive than litigation
and arbitration. Mediation sessions usually take no
more than a day or two, compared to a court trial or
arbitration hearing that can take weeks. Mediations
iN-LAC 2018 - International Law Conference 2018
122
can be scheduled as soon as the parties are ready,
while arbitration hearings and court trials often take
years to be scheduled. This time advantage is
particularly important when the mediation takes place
while a project is still under construction because
resolution of disputes clears the way for more
cooperation between the project participants (Ooi,
2017). Recognizing the effectiveness of mediation in
resolving construction disputes, many construction
industry standard contracts require that the parties
make a good faith attempt to settle their dispute
through mediation prior to instituting litigation or
arbitration. Examples of construction disputes that are
most frequently mediated are:
i. Contractor’s defective work
ii. Architect’s defective plans and
specifications
iii. Delays in project completion and other
schedule issues
iv. Payment issues
v. Changes to the scope of work
vi. Differing site conditions
vii. Property damage to the project
viii. Disputes arising from termination of a
contractor or subcontractor.
This list is however not exhaustive. After there is a
settlement, if other items come into dispute, a new
mediation can be scheduled without affecting the
prior settled items. If a major dispute develops in the
early stages of a construction project, a quick, low
cost mediation can be scheduled which will allow the
project to continue in a timely manner. If binding
mediation is specified, there will be a final and
binding decision and the project will continue in a
timely manner. It is not unusual to have multiple
mediations in larger construction projects.
Mediation is so informal that if a construction
contract does not recognize an ADR option;
mediation may be scheduled by mutual agreement of
both parties to the contract. Both parties have the
opportunity to check the background and experience
of the mediator unless the mediator is specified in the
dispute resolution section of their contract. Most
contractors specify an ADR provider when they find
a mediator or arbitrator who is knowledgeable and
experienced in construction matters and who is fair
and equitable to both parties. In civil litigation, you
have no options in the choice of your judge.
Mediation is a private process and not subject to
public knowledge and possible media attention as can
be the case with civil litigation. Parties can request
various actions, including restructuring of existing
contracts, structured payment terms and even
apologies. Mediation is often successful as it takes
into account the personal and commercial interests of
both parties. Mediation settlements usually have a
high degree of longevity, given that they are
constructed by the parties. (Boulle & Teh, 2000)
For disadvantages, mediation does not always
end with a settlement agreement. Despite the parties’
best efforts, the dispute may not always be resolved
after attending a few mediation sessions. If the
mediation does not produce a resolution, each party
may know information regarding the other party’s
allegations and possible evidence that may be used in
court at a later date.
The informality of mediation could prove to be a
detriment when the parties involved have a disparate
level of sophistication, power, and/or resources which
could possibly result in an un-favourable settlement
for the party that lacks the sophistication, power,
and/or resources to properly understand and resolve
the dispute. Example, between main contractor and a
subcontractor or between a client and a consultant.
4 CONCLUSION
The use of mediation to resolve construction disputes
can thus be said to be the continuing international
trend. At least in Malaysia, it may be premature at this
stage to agree with the following statement of George
H Golvan QC but given time and with the increasing
popularity of mediation as a means of dispute
resolution, and with all infrastructures for the use of
mediation properly in place, a concurring note may be
unreservedly given. The statement is this: “Mediation
is such a suitable process for resolving commercial
disputes that it may well be arguable in the future that
a lawyer who fails to take advantage of an available
mediation procedure, and has instead committed his
or her client to protracted and expensive litigation,
could well be guilty of a breach of professional duty.”
Mediation is particularly well suited to
construction dispute because this dispute tends to
occur as a result of a breakdown in communication
between the parties and, as such, mediation provides
the setting for parties to communicate and negotiate
effectively with the presence of a neutral third party.
It is submitted that, with regard to small, low value
construction disputes, mediation is strongly
recommended and advised where conventional
negotiation methods have failed.
The finality of the mediation could also be
questioned. Parties to a settlement agreement may
attempt to dispute the settlement agreement and still
end up filing suit in court regarding the legitimacy of
The Suitability of the Use of Mediation in the Settlement of Construction Disputes in Malaysia
123
the settlement agreement. By filing suit, the party has
created a new dispute and denied the resolution of the
underlying dispute that led the parties to a mediator.
One way to ensure that the parties will not have to
spend future time still dealing with the same dispute
is to ask the parties to agree that the resolution
reached during mediation will be binding on all
parties involved.
It is submitted that the use of mediation as dispute
settlement mechanism in construction cases should be
promoted and its popularity should be enhanced.
ACKNOWLEDGEMENT
This research is financially supported by the Faculty
of Law, Universiti Teknologi MARA (UiTM), Shah
Alam, Selangor.
REFERENCES
Arain, F. M. & Low, S. P. 2007. Modelling for
Management of Variations in Building Projects.
Engineering, Construction and Architectural
Management 14(5). Emeraldinsight.
https://www.emeraldinsight.com/doi/abs/10.1108/096
99980710780737
Ashworth, A. & Hogg, K. 2007. Willis’s Practice and
Procedure for the Quantity Surveyor, Blackwell.
London, 2
nd
edition.
Boulle, L. & Teh, H.H. 2000. Mediation: Principles,
Process, Practice. Butterworth Asia. Singapore.
Bower, D. 2003. Construction Management Series:
Management of Procurement. Thomas Telford.
London.
Carmicheal, D. G. 2002. Disputes and International
Projects. A.A. Balkema Construction. Oxon: Spon
Press. Sydney.
Cox, A. & Thompson, I. 1998. Contracting for Business
Success. Thomas Telford. UK.
Edgerton, W. W. (Ed.). 2008. Recommended Contract
Practices for Underground Construction. Society for
Mining, Metallurgy, and Exploration. USA.
Egbu, C., Ellis, R. & Gorse, C. 2004. The Practice of
Construction Management. Blackwell. UK, 4
th
edition.
Emmitt, S. 2010. Managing Interdisciplinary Projects: A
Primer for Architecture, Engineering and
Construction. Routledge. UK.
Feld, J. & Carper, K. L. 1997. Construction Failure. John
Wiley & Sons. Canada, 2
nd
edition.
Fenn, P., O'Shea, M. & Davies, E. 1998. Dispute Resolution
and Conflict Management in Construction: An
International Review. E & FN Spon. New York.
Fisher, W.H. 2017. The Use of Arbitration in the
Construction Industry in England and Wales: An
Evaluation of its Continuing Role Following the
Arbitration Act 1996. Unpublished PhD thesis.
University of Wolverhampton, UK.
Fulton, M. J. 1989. Commercial Alternative Dispute
Resolution. The Law Book. Sydney.
George H Golvan QC, The Use of Mediation in Commercial
and Construction Disputes, (1996) 7 ADRJ 188 at p.
196.
John, M. 2008. Law and Management of Building
Subcontracts. Blackwell Publishing. Chichester.
Klinger, M. & Susong, M. 2006. The Construction Project.
American Bar Association. USA.
Kumaraswamy, M. 1997. Conflicts, Claims and Disputes.
Engineering Construction and Architectural
Management, 4(2), 95-111.
Mubarak, S. 2010. Construction Project Scheduling and
Control. John Wiley & Sons. New Jersey, 2
nd
edition.
Murdoch, J., & Hughes, W. 2000. Construction Contracts:
Law and Management. Routledge. UK.
Ooi, S.S. 2017. Mediation and the Courts on Settlement of
Disputes: An Analysis On Legislating Court Directed
Mediation in Malaysia. Unpublished PhD thesis.
University of Malaya, Malaysia.
Pinnell, S. S. 1998. How to Get Paid for Construction
Changes: Preparation, Resolution Tools, and
Techniques. McGraw-Hill. USA.
Rahmat, N. 2017. A Socio-Legal Study on the Conciliatory
Bodies Appointed Under Section 106 of the Law Reform
(Marriage and Divorce) Act 1976: The Constraints and
Suggestions for Reform. Unpublished PhD thesis.
International Islamic University Malaysia.
Ramsey, V., Minogue, A., Baster, J. & O‟Reilly, M. 2007.
Construction Law Handbook. Thomas Telford
Publishing. London.
Richbell, D. 2008. Mediation of Construction Disputes.
Blackwell. UK.
Rossi, F. F. 1991. Expert Witnesses. American Bar
Association. USA.
Simmonds, D. 2003. Statutory Adjudication: A Practical
Guide. Blackwell Publishing Ltd. UK.
Singh H. 2009. Construction Project Management.
Abhishek. Delhi.
Stephenson, R. J. 1996. Project Partnering for the Design
and Construction Industry. John Wiley & Sons Inc.
New York.
Winkler G. & Chiumento G. 2009. Construction
Administration for Architects. McGraw-Hill
Professional. USA.
Wright, D. 2004. Forms of Contract User Guide: The
Purple Book. Institution of Chemical Engineers. UK,
4
th
edition.
iN-LAC 2018 - International Law Conference 2018
124