will be discussed in section 5.1. Section 5.2 will
address validation aspects.
4.1 Data Collection, Analysis And
Model Development
4.1.1 Project Risk Identification
The need for project risk identification, in relation to
customer involvement, was based on the need to
avoid or reduce project uncertainty. Uncertainty (and
risk) were caused by the lack of an approach (in
SAFe) to characterise a project in relation to customer
involvement. Clear concepts and terminology were
lacking as well as measures for characterising
projects. In accordance with (Applegate et al, 1996) it
was suggested to consider project risk as being
influenced by three project dimensions, respectively
technology, project size, and project structure. Based
on the usage of a 7-points scale (from a very low via
an average, to a very high risk), a poject typology has
been developed. The responding experts accepted to
handle this typology for their projects. Two
respondents stated that their projects were sometimes
of medium risk, and that as a consequence customer
involvement could be marginal, but that motivating
these customers should be a focus point. However,
four out of five respondents identified their projects
as often being of a very high risk, mainly because of
the high technology and the size of the projects. In
these cases customer involvement had to focus in
particular on the competence of customers to be
involved. Another discussion point was the
responsibility to involve customers. Should this be
done by project managers or product managers? In
the second round of the Delphi study it was
unanymously agreed that the reduction of risks
regarding customer involvement could be best
reached by making product managers responsible,
because of their close contacts with and knowledge of
customers. These kind of results showed that project
risk identification could be a promising step to reduce
uncertainty in the collaboration with customers.
However it was stated by all participants that extra
measures for project characterisation were needed to
make project risk identification operational.
Regarding the position of risk identification in the
SAFe framework (see table 1), it was suggested by
the respondents to position this on the Program and
Value stream level (in relation to e.g. project
management issues such as increment planning and
defining a roadmap).
4.1.2 Customer Involvement level
Regarding customer involvement level two sub-
concepts have been identified by three out of five of
the respondents in the first round of the Delphi study,
respectively customer position and customer
contribution.
Regarding the customer position, from a program
manager point of view, the customers are funders of
a project. When a customer is within the organization,
then the customer is identified as an internal
customer. Two of the responding experts defined
their customers as internal funders. However,
external customers, and e.g. a customer group, can
also be recognized as funders. These are customers
engaged in projects that build specific solutions, and
as mentioned by one of the respondents, in these
projects, customers are engaged deeply in the project,
and they have the authority to define project
requirements and specifications. In this case they
should be treated, and involved as ‘internal’
customers/funders, since they have a similar authority
as the customers who are from inside the
organization.The respondents agreed that it was most
common that the customer’s position was that of a
main project funder. Besides these ‘internal’
positions, general development projects were
mentioned by three out of five respondents, in that
customers have an external position.
Regarding customer contribution in product
development it appeared from the interviews that a
customer was authorised in two ways, respectively
for interpreting and deciding on project data, and on
contributing as a source of information. In literature
this is considered as contribution as a subject or as an
object (Holtzblatt and Beyer, 1993). Two of the five
responding experts allow involved customers to
interpret and decide on project data and to determine
the direction of a project (so contribution as a
subject). On the other hand three respondents stated
that their customers don’t have this authority.
Customers can only give input and feedback to a
product manager, so they act as an object . This
contribution can be very limited.
Figure 2 summarises the concept of customer
involvement level on the basis of position in the
organization and customer contribution. In general
solutions projects, i.e. with customers as objects, the
customer authority and contribution should be very
limited. I these projects, the product managers limit
customer involvement since requirements are
completely ‘frozen’ at the beginning of product
development.