Research on Improving the Safety Margin of Rainwater System
Design for Large Civil Airports
Qing Zhao
China Airport Construction Group Corporation
cacc_zhaoqing@sina.cn
Keywords: Large Civil Airports, Rainwater Systems, Flood Control and Drainage, Rainfall Recurrence Period, Safety
Margin.
Abstract: Rainfall statistics obtained by using a self-recording rain gauge describe the natural law of atmospheric rainfall
occurring, while the uncertainty of atmospheric rainfall makes human beings unable to calculate or forecast
any climate event that is going to happen or the degree of its impact any more accurately. Although the
calculation formula of urban rainstorm intensity deduced from the statistical perspective is included into
relevant design specifications, and the proposed rainfall recurrence period standard is followed to instruct the
rainwater system engineering design, the rainfall recurrence period standard has been determined after
multidimensional consideration to such factors as technology, economy, management and coordination of the
designated age, and also reflects the technical strength of that age, which is also the minimum “threshold” of
design. This paper, combined with construction features and development issues of large civil airports, in
view of rainwater system engineering schemes involved in flood control and drainage of airports, and by form
of case study, puts forward the necessity to improve the safety margin of rainwater system design, and
conducts multidimensional research on how to improve the safety margin of design schemes, enabling the
equipment and facilities of rainwater systems to cope with sudden disastrous weather events, and to a certain
extent, adapt to the upgrade of technical standards in the future.
1 INTRODUCTION
As the global warming effect intensifies, looking at
climate data from the statistical perspective, we find
that many historical records have been constantly
refreshed, occurrence intervals of low-probability
climate events are getting closer, and the uncertainty
in climate is becoming more serious. On July 21,
2012 and July 20, 2016, heavy rainfall never seen
over the past 50 years occurred twice in Beijing, and
some suburban areas even suffered heavy rainfall
1
even never seen over the past century. These twice of
heavy rainfall not only caused massive waterlogging
on main urban roads, and flooded several flyovers,
but also endangered subway stations, while the
operation of Beijing Capital Airport also faced
challenges, and relied upon its emergency plan to tide
over the difficulty. During the same period, the flood
level of major river basin in China approached or
exceeded the highest water level in history, some
regions suffered a flood disaster, which caused
1
Refer to long diachronic, flood prevention design recurrence period standard series.
significant property damage to those regions, and as
the flood level rose up, the rainwater self-discharging
system and pumping station drainage system of
several civil airports adjacent to main drainage
channels were also under much pressure. Disaster
weather during the flood season threatens the safe
operation of airports; although the emergency plan of
airports can effectively reduce operational risks, we
should consider how to improve the ability to cope
with more complex climate risks? This requires in-
depth research on a better construction scheme to
avoid similar risks at the stage of airport planning &
design, and meanwhile, establishing an efficient
operation control system and an effective
management coordination mechanism. The focus of
this paper is to study how to improve the safety
margin of rainproof systems of large civil airports
from the perspective of planning, design and
management coordination. It will involve technical
standards, design schemes and multi-department
management coordination.
Zhao, Q.
Research on Improving the Safety Margin of Rainwater System Design for Large Civil Airpor ts.
In 3rd International Conference on Electromechanical Control Technology and Transportation (ICECTT 2018), pages 67-71
ISBN: 978-989-758-312-4
Copyright © 2018 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
67
2 DESIGN STANDARD
EVOLUTION
The drainage design of movement areas in China’s
civil airports 30 years ago applied the rainstorm
intensity formula, with its designed recurrence period
of 1 year
2
(i.e. P=1 year), lower than the design
standard proposed by International Civil Aviation
Organization. At the end of 1980s, the domestic civil
airport engineering design kept in line with the
proposed standard of International Civil Aviation
Organization, and raised such design standard to 5
years (i.e. P=5 years), and meanwhile, gradually
unified the rainwater system design standard of the
terminal area and working area with the movement
area, and the rainwater system design standard of
underpasses already reached 30 years (i.e. P=30
years). Rainwater system design schemes within
airports have become increasingly reasonable. In
recent 20 years, based on several decades of design
experiences, we have successively prepared the
industry standards and technical specifications in line
with the construction features of China’s civil
airports.
3 LAYOUT CHARACTERISTICS
AND PROBLEMS OF LARGE
CIVIL AIRPORTS
Large civil airports refer to airports with multi-
runway systems, with a basic structure of two long-
distance runways enclosing the terminal area, and for
2
Refer to short diachronic of rainfall, subject to urban rainwater system design storm recurrence standard series.
future
development, new runways will be constructed
successively, which, as far as runway locations are
concerned, will be defined as short-distance runways,
medium-distance runways or long-distance runways
relative to existing runways.
Near runway locations at airside, there are
navigation facilities and airfield lighting facilities.
Airport planning includes the cargo area, aircraft
maintenance area, and working area. In the working
area, there are various energy stations/rooms, such as
switch station and substation of the power supply
system, boiler room and refrigeration station of the
heating & cooling system, pump station of the water
supply and drainage system, regulator station of the
gas system, etc. (fig. 1)
During the airport construction peak in 1990s, all
of new provincial airports in China were planned with
multi-runway systems, and phase one projects mostly
first construct a runway and the relevant terminal area
and supporting facilities. Due to insufficient
experience in planning and construction at that time,
rainwater systems lacked systematic planning, with
inadequate consideration given to subsequent
expansion in the medium and long term.
As the airport construction scale expands,
especially when constructing the second runway, we
would find some problems, such as the connection
between existing facilities and subsequent expansion
facilities is not smooth, particularly in respect of
topographic connection, which caused an over-high
price for subsequent earthwork projects due to lack of
more thoughtful considration in the previous phase;
since in-site and off-site rainwater system schemes
were not smooth in connection, lots of rewiring and
crossing problems arose, leading to an increase of
project costs.
Figure1 diagram of the floor plan of the airport
ICECTT 2018 - 3rd International Conference on Electromechanical Control Technology and Transportation
68
Besides, the earlier planning and design lacked
systematic research on airport waterlogging issues.
For example, when the runoff amount generated by
rainfall within the scope of airports exceeds the
planned capacity of off-site flood systems, how
should airports resolve waterlogging issues on the
premise of ensuring their own safety? Also, targeted
research has been conducted on the “Sponge Airport”
proposed recently.
4 NECESSITY TO IMPROVE THE
SAFETY MARGIN OF
RAINWATER SYSTEM DESIGN
FOR AIRPORTS
4.1 Large civil airport project cases
The author was lucky to have the opportunity to take
part in the design of Shanghai Pudong Airport
construction project in 1990s, and experienced the
process from project initiation to planning, design and
construction site service. The Pudong Airport project
is near the mouth of the Yangtze river, with long-term
planning of land for at least two runways to be
provided by subsequent land reclamation by filling
the sea in the long run. Due to lack of soil source at
the location near sea and in site per se, airports must
solve the problem of flood prevention in-site and off-
site. Through multiple rounds of scheme
argumentation, and with overall consideration to all
adverse factors at that time, the scheme design
reserved a certain safety margin, and from completion
to present, for 18 years, the rainwater system
operation of Shanghai Pudong Airport remains safe
and sound. The project has used a combination of
multiple schemes to have addressed the rainwater
system and damp/flood prevention issues within
airports.
The new Guangzhou Baiyun Airport is China’s
first project that has constructed two long-distance
runways simultaneously. The flood prevention
standards outside the airport are far lower than the
airport construction standards. Through systematic
analysis, and considering by the project team the
planned conditions of off-site water systems, in areas
restricted by in-site topography, the project uses
forced drainage to raise the water level of the in-site
drainage system, while for off-site open drainage
channels, uses an inverted siphon drain culvert to
cross low-standard watercourse for connection to
flood control and drainage channels with planned
conditions satisfying the requirements of civil
airports. At the time of rainwater system design, when
raising the design standards up to a higher grade for
recalculation, we found the original design scheme
could still realize smooth drainage. By comparing
design calculation results, we find the cost for
improving the safety margin of rainwater systems is
limited, while the reduced degree of heavy rainfall
risks faced by airports is significant (Table 1).
4.2 Necessity to improve the safety
margin of design
Inspirations from the above two cases: the design
standards are rigid and fixed, and multi-dimensional
research schemes can be used to improve the safety
margin of design. With the improvement of overall
strength of engineering construction projects in
China, considering that civil airport projects are a
long-range program, the upgrade of technical
standards is inevitable in the future. Therefore, it’s
necessary and feasible to improve the safety margin
of rainwater system design of large civil airports. The
rainwater system design of airports follows the
specified standards, which can be moderately raised
up to a higher grade at recalculation, and can be
optimized in combination with specific design
conditions.
Table 1: Comparison of Calculation Results on Different Designed Rainfall Recurrence Periods
Designed Rainfall Recurrence
Periods
P=5
years
P=10
years
P=20
years
P=50 years Remarks
Runoff Growth Calculation -
16% 32% 41%
Relative to P=5 years
Project Cost Growth -
6% 15%
About
20%
Notes: Take the calculation results of rainwater system design of a regional airport for example.
Research on Improving the Safety Margin of Rainwater System Design for Large Civil Airports
69
5 NEW TECHNOLOGY
APPLICATION AND
GRASPING KEY POINTS OF
SAFETY MARGIN
At present, the newly developed flood control and
drainage simulation software is introduced into new
airport projects in Beijing and Qingdao. The flood
control and drainage simulation software validates
the safety of design schemes, and simulates the
degree of waterlogging within airports under super-
standard rainfall conditions. This points out a
direction for further optimization of in-site rainwater
system planning and design schemes, and also
provides effective support for the operation
department to make contingency plans for the future.
All the new airport projects launched recently are
multi-runway projects. Also, reclaimed land is used
to build artificial islands for construction of multi-
runway civil airport projects, similar to Kansai
International Airport in Japan. With regard to flood
prevention of airports constructed on reclaimed land,
consideration shall be given to the year-by-year rise
of sea levels caused by climate changes.
In the age of information explosion and rapid
technology progress, the rate of technology upgrade
goes far beyond our imagination. Relevant mandatory
specifications and technical standards promulgated
by the state at different time frames are the minimum
“threshold” under social, economic and technical
conditions at that time, so the safety margin of design
proposed herein is based on all-round thinking and
research, and adaptable to the upgrade of technical
standards in the future.
According to research and experience
accumulation on design schemes of more than 20
large civil airport projects, factors that should be
considered for improving the safety margin of
rainwater system design for airports are summarized
as follows:
5.1 Planning
1) Apply the same standard to off-site existing flood
systems or planned drainage watercourse;
2) Transfer in-site rainwater system risks to off-
site water systems to the greatest extent, which is
good for actual operation and operation cost control
of airports;
3) On the premise of observing the design
standards and specifications, make sure to reserve a
safety margin of design;
4) Use the “Sponge Airport” concept to reduce the
pressure of flood systems, but in-site rainwater
system design standards shall not be lowered.
5.2 Details of design schemes
1) Favorable for connection between current
construction and future expansion, ensuring airports
can realize reasonable and effective connection at
different construction sequences;
2) The airport topography design and rainwater
systems shall give consideration to connection with
future construction schemes, and the selection of
rainwater system as self-drainage or forced drainage
shall control the volume of earth works within a
degree acceptable to projects;
3) Various energy and water resource facility
stations, depots, venues and underground entrances
shall reserve a safety margin higher than the design
specifications, all of which shall be designed to
prevent rainwater from flowing backward.
4) To the extent allowed by designed conditions
and controllable investments, the design of rainwater
system pipelines, open channels and box culvert cross
sections shall reserve a certain margin.
5.3 Operation management
1) According to the principle of administration by
region and segment, in-site rainwater systems are
controlled by the airport operation department, while
off-site segments are controlled by the local
watercourse administration;
2) Outlets with self-drainage functions are subject
to dual-brake control as per internal and external
division of labor, wherein, the outer gate is in a
normally open state and controlled by the watercourse
administration, while the inner gate is controlled by
the airport operation department to prevent from
backflow;
3) Build smooth in-site and off-site information
communication channels to exchange data and
information in a timely manner for use of emergency
plans;
4) Clear rainwater system pipelines, channels and
culverts every year, and regularly maintain and
update equipment, facilities and key parts of
rainwater pumping stations.
6 CONCLUSION
With the rapid development of civil aviation
transportation, we should make a forward-looking
ICECTT 2018 - 3rd International Conference on Electromechanical Control Technology and Transportation
70
master plan for large civil airports to lead each
specific planning, and only those airport construction
schemes of multi-system coordinated development
would be scientific and reasonable. Facing climate
challenges, we shall not stop at bearing, but cope with
the upgrade of technical standards, and employ new
technologies and new philosophies to reduce risks
brought about by climate environments to airport
operation.
REFERENCES:
PRC National Standard Code for Design of Outdoor
Wastewater Engineering GB 50014-2006;
CAAC Code for Drainage Design of Civil Airports
MH/T5036-2017;
ICAO Convention on International Civil Aviation Annex
14 Volume 1 Airport Design & Operation (Sixth
Edition July 2013).
Beijing Municipal Planning Commission, Beijing
Municipal Bureau of Quality and Technical
Supervision. Code for design of stormwater
management and harvest engineering DB11/685-2013.
Laizhen Zhou. The construction and development of China
civil airports(1949-2013). China civil aviation press.
2014.
Guanghui Zhang. China civil airports. China civil aviation
press. 2008.
Beijing Municipal Commission of Housing and Unban-
Rural Development. Beijing municipal engineering
budget quota (pipeline engineering).2017.
Research on Improving the Safety Margin of Rainwater System Design for Large Civil Airports
71