3. Analysis on river channel evolution before and after the construction of diversion junction
3.1. Water level changes of river channel before and after the construction of diversion junction
Test observation is carried out on the changes of channel water level at different flow levels of 500,
1500 and 2500 m
3
/s under four conditions, i.e., before the gate construction of diversion junction and
the constructions of 8-hole, 11-hole and 12-hole sluice gates. The results show that in the case of
small flow level, the backwater of small flow level has a large amplitude, which is about 100 cm. But
in the case of large inflow, the channel water level of normal inflow has exceeded control-application
water level, so the discharge gate is open to use, when the backwater at corresponding flow level has
a smaller amplitude, basic under 20 cm. In addition, under three arrangement schemes of 8-hole, 11-
hole and 12-hole sluice gates, the backwater amplitudes are basically approaching, and those of 11-
hole and 12-hole sluice gates are slightly smaller than 8-hole sluice gate.
3.2. River regime changes of river channel before and after the construction of diversion junction
In this test, the changes of river regime under the three flow levels of 500, 1500 and 2500 m
3
/s are
observed. When the flow is 500 m
3
/s, the mainstream bending is obvious. However, the mainstream
bending degrees at the two flow levels of 1500 and 2500 m
3
/s are reduced to a certain extent, but
artificial groin has more significant control on the mainstream than the natural change of river
channel. Through comparing the running trajectory of mainstream line before and after the gate
construction at three flow levels, it can be seen that there are no obvious changes in river regime
before and after the gate construction at the flow levels of 500, 1500 and 2500 m
3
/s. Therefore, after
the construction of diversion junction, whether the combination of 8-hole or 11-hole gates is used or
the scheme of total 12-hole gate is applied, the three arrangement schemes have basically not
changed the current running trend of original channel.
3.3. Flow velocity changes before and after the construction of diversion junction
As viewed from the test results of mean vertical velocity at three flow levels of 500, 1500 and 2500
m3/s before and after the construction of diversion junction, the location of maximum vertical
velocity at different flow levels on different cross sections basically corresponds to the lowest point
of river section, and the basic rule of velocity distribution is almost consistent with water depth
changes. The greater the water depth is, the larger the mean vertical velocity will be. Therefore,
before and after the construction of diversion junction, when the big river inflow is small, the control
of sluice gate is applied, resulting in sharp decrease of flow velocity in backwater segment. For the
flow of 500 m3 / s, flow velocity decreases by about 50%. When the big river inflow is large, the
floodgate is open to use, when the water intake junction has less effect on river velocity, and the
change rule of flow velocity and water level change correspond to each other.
3.4. Changes in riverbed erosion and deposition of river channel before and after the construction of
diversion junction
In order to increase comparability, the inlet water and sediment, outlet water level, initial topography
and other conditions of this erosion and deposition test scheme are identical. The on-way changes in
channel erosion and deposition before and after the construction of diversion junction are shown in
Figure 2. As viewed from the overall change trend, the on-way riverbed erosion quantity from test
inlet to fish-mouth river segment shows a gradual increase trend, while that from fish-mouth segment
to outlet segment presents a gradual decrease trend, and the on-way erosion and deposition changes
of the entire test river segment is basically āV-shapedā. The construction of water intake junction has
not changed the overall trend of the changes in river channel erosion and deposition, but it still has
some impacts on the changes in river channel erosion and deposition. Thus, it can be seen that after
the construction of water intake junction, the riverbed surface erosion ability of test river segment has
IWEMSE 2018 - International Workshop on Environmental Management, Science and Engineering
210