3.4 Project System
A project that is experiencing delays is certainly due
to factors that influence waste (Hapsari, 2014). A
project that is experiencing delays is certainly due to
factors that influence waste. Waste in the project is
actually something that must be considered in the
sustainability of the project. Project system have been
carried out by understanding the project and
discussions with the implementer to identify the
waste that is likely to arise in project implementation.
3.5 Waste Identification using Fishbone
Diagrams
Lean is an often-used adjective in business these days,
but there’s some confusion over its exact definition.
In essence, the goal of Lean is to maximize value
while minimizing waste (Eby, 2017). Identification of
waste or known as Non-Value-Added activity aims to
determine the waste that occurs in the project. The
identification process is done by using fishbone
diagrams and If-Then formulations so that the project
implementer can take appropriate corrective and
preventive actions for future projects where there is
the potential for waste to occur so that excessive
waste can be avoided. Based on fishbone diagrams
below, it can be seen the types of waste that most
often appear in Offshore Pipeline installation projects
from 8 waste that have been defined by Womack and
Jones (1996) are Waiting and Unnecessary Motion.
Waiting, which is a condition where project
activities have been delayed so that the delayed
activity can result in delays in project
implementation.
Unnecessary Motion, which is the movement that
is not necessary, where the movement of
unproductive workers that should not need to be done
in the implementation of the project.
From Figure 1, the Fishbone Diagram above can
be seen as the causes of waste generation in the
project. It contains 9 failure modes and 20 causes that
have been classified based on factors causing waste.
Those are Man, Material, Method, also Tools and
Machine. The causes of waste then processed into If-
Then formulation to further know possible actions
that implementer can take to minimize waste with
preventive or corrective steps.
3.6 Managing Variations
The variations contained in the project is considered
as uncertainty, therefore the project executor needs to
adjust the existing variations by estimating. In this
project, the variation made estimation is time. The
aim is that the project executor can estimate the time
needed during implementation.
Identification of waste in the project system
project analysis found that the most influential waste
in the project is waiting and unnecessary motion. By
knowing the waste, then the scheduling improvement
recommendations will be made with the Critical
Chain Project Management (CCPM) as follows.
3.7 Critical Chain Project
Management
All projects are carried out in a dynamic environment.
This is an inherent characteristic of project activities
which duration cannot be estimated precisely.
Estimate Activity Durations is the process of
estimating the number of work periods needed to
complete individual activities (PMBOK, 2013).
Among other factors, the accuracy of the estimation
depends on the level of uncertainty. Variation
problems must be addressed early in the development
schedule. Safety time must be included in the project
and must ensure its robustness. Time analysis have
been used in many areas such as in graving dock
project (Silvianita et al, 2018).
Table 3: Work Breakdown Structure with CCPM.
Pipeline Installation
Summary Task CCPM Duration (Days)
Basic Engineering 91
Project Management
Team (PMT)
105
Coated Pipe 10” 126
Pipe Bend 125
Crossing Material 137
Riser Clamp dan
Riser Fabrication
25
Survey 4
Preparation 40
Pipeline Laying 7
Mobilization 4
Riser Installation 13
Crossing Installation 7
Precommissioning 4
Certification 16
Final Acceptance 11