excess costs must be avoided because it can endanger
all parties such as the owner and contractor, for
example from the owner will suffer losses because the
object of the project cannot operate, so it does not
generate profits. On the other hand, the contractor
must be responsible for delays and the contractor's
good name becomes bad.
Table 1: Indications of Delay in the Development of a New
Pipe Replacement Project on Deteriorated Pipelines.
June
2018
June
2018
Sept
2018
Oct
2018
Planned
Value
0,06% 6,35% 40,11% 53,20%
Earned
Value
0,00% 5,63% 39,71% 48,15%
Table 1 explains that there are indications of
delays in the construction of new replacement pipe
projects for damaged pipelines. Indications occurred
in June 2018, September 2018, and October 2018.
The largest deviation between the planned value and
the value obtained occurred in October 2018 at
5.05%. Many factors can make a project experienced
delay, for example weather factors that make it
impossible to do work or factors of lack of utilities
and construction equipment, delays in purchasing
material orders, lack of experienced and skilled
human resources in the field, delay costs down to
purchase activities on the project, in addition, there
are delays in critical activities because critical
activities have a large impact on the duration of the
project.
Therefore it is necessary to analyze the delay by
looking for any activities that are critical to the project
and factors that can cause overtime. To avoid
overtime in this new pipeline project because it could
endanger the owner and contractor as explained in the
previous paragraph. In this study, we will discuss
determining the critical trajectory, determining the
root cause or factors that can cause delays, a large risk
of delay, and what improvements can be made.
2 BASIC THEORY
2.1 Project Management
Project management is planning, organizing, leading,
and controlling company resources to achieve short-
term goals that have been determined. Project
management has a basic function consisting of
managing the scope of work, time, cost, and quality.
The key to successful implementation of a project if
you can manage these aspects correctly (Samad,
2019).
2.2 Risk
Risk is a combination of the probability of an event
and the impact of the event, the impact can be more
than one for one event. However, risks are generally
seen as negative things such as danger, loss, and other
impacts. These impacts and losses is actually a form
of uncertainty that should be understood and managed
effectively by the project implementer (Szymanski,
2017).
2.3 Critical Path
Critical path is a project management technique that
uses only one-time factor per activity. Critical path or
critical path is the fastest path in project work, every
project included in this path is not given a break /
break for the process. Critical path is a path that
consists of activities which if delay will result in delay
completion of the project Heizer, 2014).
2.4 Six Sigma Analysis
The statistical concept that measures a process that is
redelayd to the sigma number, where the closer to 6
the results will be as expected. Six Sigma is a
management philosophy that focuses on removing
defects by emphasizing understanding, measuring
and improving processes (Brue, 2002). Six Sigma has
5 stages, as follows (Larasatie, 2019):
(i) Define
Define aims to identify the process to be improved
and determine what resources are needed in project
implementation.
(ii) Measure
Measure is an advanced stage of define where at this
stage validation of a problem is done by calculating
and obtaining numbers that can provide clues about
the problem.
(iii) Analyze
At this stage, the cause of the deviation in a project
will be investigated with a hypothesis which will then
be tested.
(iv) Improve
At this stage, the main factors are ascertained and
give new influences so that they get the desired
results. The purpose of this stage is to implement a
new system so that the project can run more
optimally.
(v) Control
Maintain changes that have been made through