Simulation of Vehicle Movements for Planning Construction Logistics
Centres
Fei Ying
1
, Mike O’Sullivan
2
and Ivo Adan
3
1
Department of Built Environment Engineering, Aucland University of Technology, Auckland, New Zealand
2
Department of Engineering Science, University of Auckland, Auckland, New Zealand
3
Department of Industrial Engineering, Eindhoven University of Technology, Eindhoven, The Netherlands
Keywords: Construction Logistics, Simulation.
Abstract: Materials supply is one of important elements in construction operation and a major factor affecting the quality
of construction projects. With materials accounting for 60% of the on-site cost of a typical construction
project, effective management of this vital resource is essential. Logistics processes, being crucial for
successful completion of the project, are often entrusted to external professionals specialized in logistic
services, such as logistics centres. However, this tendency is yet to be developed in construction. The purpose
of this paper is to examine the potential of managing logistics costs by planning construction logistics centres.
The planned centres are then evaluated using vehicle movement simulations. The enclosed results from the
simulations indicate that using a logistics centre will have reduced waste for the construction project
considered. A literature review and case study analysis are employed, with simulation results using Flexsim.
The paper emphasizes that creating a logistics centre for a project at its early stages of planning and then
designing an integrated logistics service for that project may help find ways of making the overall construction
project more effective by improving management of materials.
1 INTRODUCTION
Lean construction is an attempt to apply lean
principals that originate form Toyota Production
System (TPS) to construction, aiming at managing
and improving construction processes with minimum
cost and maximum value by considering customer
needs (Gao and Low, 2014). Following years of
developing, there have emerged significant studies
that have correlated lean principals with construction.
Lean construction alters the traditional view of the
project as transformation and have changed the way
constructors manage the operations (Jorgensen and
Emmitt, 2008). Lean tools and techniques come into
helping identify and eliminate the waste that adds no
value. In practice, Construction Supply Chain
Management (CSCM) is one of the systems to
implement lean construction philosophy.
CSCM is defined as “the network of facilities and
activities that provide customers with economic value
to the functions of design development, contract
management, service and material procurement,
material manufacture and delivery, and facilities
management” (Love et al., 2004). The term
“logistics”, as used in the title of the paper, is related
to the term “supply chain”. Logistics is defined as
“the process of strategically managing the
acquisition, movement and storage of materials, parts
and finished inventory (and the related information
flows) through the organisation and its marketing
channels, in such a way that current and future
profitability is maximised through the cost-effective
fulfilment of orders” (Gattorna and Day, 1993). For
the construction industry, logistics comprise
planning, organisation, coordination, and control of
the materials flow from the procurement of raw
materials to the incorporation into the finished
building (Agapiou et al., 1998).
Building materials and construction components,
along with human resources, are the first and most
important requirements for construction. Materials
supply is thus a factor affecting the quality of
construction projects and the profitability for
construction firms. With materials accounting for up
to 60% of the on-site cost of a typical construction
project (Song et al., 2005) and between 15 and 30 per
cent of urban waste (Formoso et al., 2002), effective
258
Ying, F., O’Sullivan, M. and Adan, I.
Simulation of Vehicle Movements for Planning Constr uction Logistics Centres.
DOI: 10.5220/0007346802580263
In Proceedings of the 8th International Conference on Operations Research and Enterprise Systems (ICORES 2019), pages 258-263
ISBN: 978-989-758-352-0
Copyright
c
2019 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
management of this vital resource is essential.
Furthermore, research suggests that improved
logistics will attain monetary and schedule savings,
reduce material waste, increase productivity and
safety (Jang et al., 2003; Poon et al., 2004; Shakantu
et al., 2003; Spillane and Oyedele, 2013). Thus,
effective construction logistics should provide
appropriate trade-offs involving costs and service in
the supply chain by integrating materials supply,
storage, processing and handling; site infrastructure
and equipment location; physical site flow
management and information management (Shakantu
et al., 2008).
Many industries attempt to integrate logistics
processes into logistics chains of suppliers and
customers, from obtaining raw material, through
manufacturing, distribution and final sale and service
to the end-users. Logistic processes, which are crucial
for successful completion of the project, are often
entrusted to external professionals specialised in
logistics services, such as logistics centres (Sobotka
and Czarnigowska, 2005). However, in the field of
construction, this tendency is to be developed.
Moreover, recent research has shown that, in the
management of material deliveries, an ad hoc,
intuitive approach is often adopted (Spillane and
Oyedele, 2017; Ying et al., 2014). Consequently,
there appears to be a significant need for an enhanced
understanding of transportation in a construction
context in order to deliver the full benefits from the
adoption of efficient construction logistics. The
purpose of this research is to address how the
efficiency of construction logistics can be improved
by using logistics centres. In order to evaluate the
effect of using a logistics centre, we provide a
simulation case study that measures logistics waste
with and without a logistics centre.
Next section surveys the related literature. It
follows by defining the problem environment and the
research methodology. The mathematical models and
scenario considered are then described. The paper
ends with conclusions and further research directions.
2 LOGISTICS ISSUES IN
CONSTRUCTION
2.1 Lack of Supply Chain Innovations
While many industries have experienced
performance improvements through supply chain
management initiatives, the construction industry is
yet to realise these improvements to the same extent.
Several researchers have explained the particular
features of the industry that hinder these potential
benefits, such as the fragmented structure of the
industry (Fadiya et al., 2015), the negative
consequence of arm-length relationships (Briscoe and
Dainty, 2005), and the lack of trust and commitment
among the firms involved in the process (Gadde and
Dubois, 2010).
Determining project logistics process requires a
wide range of construction project management
knowledge, such as knowledge of the building
materials market, financing, and managing
contractors’ approaches to supply. It also demands a
deep understanding of the impact of logistics on
project efficiency in terms of cost, quality and time.
Furthermore, it is of great impact to be aware of
logistics costs and their relationship to variables such
as batch size, place and time of the delivery, and
required storage conditions.
2.2 On-site and off-Site Logistics
Efficiency and effectiveness of a construction project
heavily depend on the integration between on-site and
off-site logistics. However, a lack of planning of
materials deliveries and unloading among
subcontractors and their site workforce causes
significant issues in this interface (Ying et al., 2014).
Previous research shows that substantial benefits can
be attained through the rearrangement of on-site
logistics (Lindén and Josephson, 2013). Off-site
logistics refers to supply logistics involving suppliers
of building materials.
The aim of logistics customer service is to ensure
that construction materials are appropriate and
available for construction operations. Thus, service
related factors affecting vehicle movements are
planning, training, loading and the logistics
management strategy. It is widely recognised that the
troublesome logistics in the construction industry is
influenced by the characteristics of the industry,
including the fragmentation of the construction
industry supply chain, lack of coordination and
communication among actors, inefficient planning
both on-site and off-site. From the project managerial
perspective, the real-time scheduling of materials
planned and keyed to the master plan for material
delivery is highly desirable. However, frequently this
is unachievable because of many factors, such as
inadequate detailed information at the
commencement of a contract, and considerable
variations during the construction stage.
Simulation of Vehicle Movements for Planning Construction Logistics Centres
259
3 RESEARCH METHODOLOGY
The guiding purpose of this study was to develop a
simulation framework for analysis of potential
improvements of logistics performance using
logistics centres. The focus of the work is to identify
achievable benefits through optimising off-site
logistics. The studies in this work were carried out as
a case study with simulation modelling. The case
study described in this paper has been developed from
a commercial project hosted by a university. The
$100 million project consists of a 13 level tower block
with a roof top plant room surrounded with lecture
theatres and student facilities. The new construction
integrates several existing buildings on campus. The
construction has three stages: ground works,
structure, and fit-out.
Special attention has been paid to the numbers and
patterns of vehicle movements, since it was expected
that appropriate interventions to improve
construction logistics could be identified through
analysing these elements. The vehicle movements
were recorded by the gates-person on the site. Details
such as delivery company name, date, time, truck
type, materials, and activities were noted on printed
tables.
3.1 Flexsim
The simulation case study has been developed in the
Flexsim environment. “Flexsim is an object-oriented
software environment used to develop, model,
simulate, visualize, and monitor dynamic-flow
process activities and systems” (Nordgren, 2003).
Flexsim models consist of a tree of individual nodes
that contain model objects, library objects,
commands, and all model information. Within this
tree are flowitems which are simple objects that are
created to move through the model. Flowitems can
represent actual objects, or they can be representative
of a more abstract concept.
Figure 1: Simulation pathway without a logistics centre.
(a) Simulation pathway without a logistics centre.
Vehicles arrive to depots according to historical data
(which is also used to determine the vehicle size and
load), travel to the construction site, are unloaded
according to triangular distributions and leave the
system
Figure 2: Simulation pathway with a logistics centre.
(b) Simulation pathway with a logistics centre.
Vehicles arrive in the same way as without the
logistics centre, but now some of the smaller vehicles
travel to the logistics centre where their loads are
aggregated before being delivered in a larger vehicle
to the construction site. Other vehicles go directly to
the construction site as before. Some depots dispatch
both small and large vehicles, but only the small ones
go to the logistics centre
The movement of vehicles within the construction
logistics process is depicted in Figure 1, for the
scenario with no logistics centre, and Figure 2 for
the scenario with a logistics centre, respectively. In
the construction logistics model two different
flowitems library classes are used. The Box class is
used to represent the cargo of a vehicle and the Pallet
class is used to represent the vehicle. These classes
are used as they already contain the functionality for
loading and unloading required for simulating
construction logistics. Deliveries are simulated using
historical data by creating a delivery vehicle (a Pallet)
at a depot and creating the appropriate cargo (a
number of Boxes) and combining them together. Note
that the arrival time at the depots of the loaded
vehicles is calculated from their arrival time on-site
less the travel time from the depot to the site. This
combined flowitem can have its properties altered,
e.g., image type, colour, to enable the simulation’s
visualisation to be representative of the construction
site activities, which is useful for validating the
simulation via visual inspection. The delivery
flowitem then travels from its origin (e.g., the
supplier) to the construction site or (if it is being used)
the logistics centre. At the logistics centre smaller
vehicles can be unloaded, i.e., the underlying Pallet
and Box objects separated, and combined into a larger
vehicle, i.e., a new (higher capacity) Pallet is
ICORES 2019 - 8th International Conference on Operations Research and Enterprise Systems
260
combined with the Boxes from multiple (smaller)
Pallets, which then travels to the construction site.
This way transportation between suppliers, the
logistics centre (if it is being used) and the
construction site is visible. It is important to set the
correct speed between locations to get the desired
travel duration.
Once loaded vehicles arrive to the construction
site they are unloaded either by hand or using
equipment available on-site. In this model there are
two cranes that can be used for unloading along with
a hoist. If the unloading equipment is already busy,
then the vehicle needs to wait in the loading bay for
the appropriate equipment or, if the delivery area is
full, wait outside the site itself. Once unloaded both
vehicles and their load leave the system.
In the model, queues and queuing mechanisms are
used to model vehicles waiting to be unloaded. It is
possible to change the strategy of queueing from the
default of First-in First-Out (FIFO) to investigate
priority policies that may streamline deliveries. Once
the equipment required to unload a vehicle is
available, the vehicle is unloaded with the unloading
duration dependent on the type of load, the size of the
load, and the equipment being used. The load (the
Box objects) are separated from the vehicle (the
Pallet) and the vehicle leaves the site. At this point the
delivery is complete and box the load and the vehicle
are removed from the model.
By experimenting with the use of a logistics centre
and policies for unloading deliveries, the simulation
model can be utilised to evaluate the effect of a
logistics centre and also determine if similar
improvements could have been achieved by adopting
a less ad hoc approach to managing deliveries.
4 KEY FINDINGS
The main aim of this paper is to contribute to the
knowledge of setting up logistics centres to improve
construction logistics performance. The key findings
section of the paper is focused on where to locate the
logistics centre and the potential improvements that
can be achieved in practice by using this centre. The
improvements are measured by simulating vehicle
movements to the site and/or the logistics centre and
observing the effect on vehicle waiting time on-site.
4.1 Locating Logistics Centre
In order to determine the best location for the logistics
centre, data from vehicle deliveries were used to
visualise the depots where each vehicle began its
delivery from. Google API was used for this
visualisation and travel durations between the depots,
the logistics centre, and the construction site were
also acquired via Google API. The depot address of
each subcontractor and material supplier were first
translated into longitude and latitude, visualised on a
background map, then used in the simulation model
for deliveries. The result of the visualisation, as
shown in Figure 3, can then be used to evaluate
potential locations for the logistics centre at which
delivery loads of vehicles could be merged. The size
of the circles in Figure 1 represents the amount of
deliveries that originated from this particular
company, hence its depot. The exception is the large
grey circle which the construction site itself. It is
obvious that a large percentage of deliveries
originated from certain suburbs. The simulation
model depicted in Figure 3 located the logistics centre
in one of these suburb, Penrose, and evaluated the
subsequent performance improvement. The logistics
centre location is shown as a small black rectangle
neat the centre of Figure 3.
Figure 3: Flexsim visualisation of companies.
4.2 Simulations of Vehicle Merging
One scenario simulated in this case study merges all
small vehicle loads, within the Penrose region (shown
in red in Figure 3), at the Penrose logistics centre and
the delivers the aggregated load of materials to the
construction site located in the Auckland CBD. In the
simulation model the assumption is that all small
vehicles go to the hoist with a mean process time of
30 minutes, while all large vehicles are directed to
one of the cranes (with equal probability) with a mean
process time of 45 minutes. The process times are
modelled using a Triangular distribution with
minimum value equal to 2/3 of the mean and
maximum value equal to 4/3 of the mean. Hence,
there are two symmetric distributions, with the
appropriate mean values, for unloading via either a
crane or the hoist
Simulation of Vehicle Movements for Planning Construction Logistics Centres
261
The number of total deliveries occurring during
construction is 6889 of which 2256 (33%) are made by
small vehicles. The total deliveries from the Penrose
region during construction is 2465 (36%) of which 857
(12% of total deliveries) are small vehicles. By
merging small vehicle deliveries from the Penrose
region each day the number of deliveries can be
reduced from 857 to 281, a reduction of 67%. Note,
however, that the new deliveries from the Penrose
logistics centre will require larger vehicles with more
load so that merged vehicles use a crane with a mean
process time of 60 minutes.
A comparison of the system with and without the
logistics centre is now possible via the Flexsim
simulation (running 20 replications for 468 days each).
Table 1 shows the number of small vehicle, large
vehicle, and merged vehicle deliveries. Table 2 shows
the expected waiting time (in minutes) for the cranes
and the hoist with and without the Penrose logistics
centre. Note that the waiting time for the hoist
demonstrates a clear difference and is almost halved
when the Penrose logistics centre is used. However, the
waiting time for the crane also demonstrates a clear
difference with the waiting time being slightly worse
when the Penrose logistics centre is used.
Although waiting time is one key measure of waste,
a better comparison between the systems is that of total
unloading time on-site. Aggregating the loads of small
vehicles from the Penrose region onto larger vehicles
means that the cranes are used more (281 more times)
and for longer each time (mean process time of 60
minutes), but there are far less small vehicle deliveries
on-site. While the average waiting time (for a crane or
the hoist) is the time vehicles waste while idle, the total
time spent unloading on-site measures the “busy-ness”
caused by deliveries. If aggregating loads at a logistics
centre causes more total on-site busy-ness, even if it
reduces the average waiting time per vehicle, then its
efficacy is questionable. Table 2 shows that the total
time spent unloading on-site is reduced by
approximately 18 days over the duration of the
construction project. Note that this saving is offset by
unloading (and possibly waiting) tie at the logistics
centre, but time spent at the logistics centre does not
reduce productivity at the construction site so it is not
measured.
Table 1: Number of each type of delivery vehicle.
Delivery
Vehicle
Type
No Logistics
Centre
Penrose
Logistics Centre
Small
2256
2256 857 =
1399
Large
6889 2256 =
4633
4633
Merged
0
281
Table 2: 95% confidence interval for expected waiting time
(minutes).
Measure
No Logistics
Centre
Penrose
Logistics
Centre
Waiting time for
Hoist (mins)
[29.4, 30.1]
[16.1, 16.6]
Waiting time for
Crane (mins)
[41.6, 49.3]
[46.4, 49.0]
Total on-site
unloading time
(days)
[191.5, 191.7]
[173.6, 173.9]
5 CONCLUSIONS
The simulation confirms that using logistics centres
can improve construction logistics performance.
Through logistics centres, off-site logistics are
consolidated and optimized. This in turn will
stimulate the planning of on-site logistics
performance. This approach could solve previously
observed problems identified in relation to
insufficient planning, limited storage capacity, waste
in extra material handling, and low delivery
reliability.
When the principles of logistics centres are
applied, the interface between off-site and on-site
logistics could be connected seamlessly. The main
findings in relation to reduced waiting time to be
unloaded, the number of vehicle movements on-site,
and total on-site unloading time are encouraging. This
would significantly increase the efficiency of cranes
and hoists utilization, which are the most expensive
equipment on construction sites.
Future research will investigate the feasibility of
establishing logistics centres, especially determining
any impediments to implementing this concept in the
construction industry. The improvement of
construction logistics efficiency will not be realised
without commitment that is initiated from within the
construction industry and application of logistical
expertise. Further research will focus in identifying
the financial costs and benefits logistics centres could
ICORES 2019 - 8th International Conference on Operations Research and Enterprise Systems
262
bring to various actors, such as main contractors,
subcontractors and material suppliers.
REFERENCES
Agapiou A, Clausen LE, Flanagan R, et al. (1998) The role
of logistics in the materials flow control process.
Construction Management and Economics 16: 131-
137.
Briscoe G and Dainty A. (2005) Construction supply chain
integration: an elusive goal? Supply Chain
Management: An International Journal 10: 319-326.
Fadiya O, Georgakis P, Chinyio E, et al. (2015) Decision-
making framework for selecting ICT-based
construction logistics systems. Journal of Engineering,
Design and Technology 13: 260-281.
Formoso CT, Soibelman L, Cesare CD, et al. (2002)
Material waste in building industry: main causes and
prevention. Journal of Construction Engineering and
Management 128: 316-325.
Gadde L-E and Dubois A. (2010) Partnering in the
construction industry -- Problems and opportunities.
Journal of Purchasing and Supply Management 16:
254-263.
Gao S and Low SP. (2014) Impact of Toyota way
implementation on performance of large Chinese
construction firms. Journal of Professional Issues in
Engineering Education and Practice 140: 1179-1183.
Gattorna J and Day A. (1993) Strategic issues in logistics.
International Journal of Physical Distribution and
Logistics Management 16: 3-42.
Jang H, Russell JS and Yi JS. (2003) A project manager's
level of satisfaction in construction logistics. Canadian
Journal of Civil Engineering 30: 1133-1142.
Jorgensen B and Emmitt S. (2008) Lost in transition: the
trasfer of lean manufacturing to construction.
Engineering, Construction and Architectural
Management 15: 383-398.
Lindén S and Josephson P-E. (2013) In-housing or out-
sourcing on-site materials handling in housing? Journal
of Engineering, Design and Technology 11: 90-106.
Love PED, Irani Z and Edwards D. (2004) A seamless
supply chain management model for construction.
Supply Chain Management: An International Journal 9:
43-56.
Nordgren WB. (2003) Flexible simulation (Flexsim)
software: Flexsim simulation environment. 35th
conference on Winter simulation: driving innovation.
New Orleans, LA, USA, 197-200.
Poon CS, Yu ATW, Wong SW, et al. (2004) Management
of construction waste in public housing projects in
Hong Kong. Construction Management and Economics
22: 675-689.
Shakantu W, Muya M, Tookey J, et al. (2008) Flow
modelling of construction site materials and waste
logistics: A case study from Cape Town, South Africa.
Engineering, Construction and Architectural
Management 15: 423-439.
Shakantu WM, Tookey JE and Bowen PA. (2003) The
hidden cost of transportation of construction materials:
An overview. Journal of Engineering, Design and
Technology 1: 103-118.
Sobotka A and Czarnigowska A. (2005) Analysis of supply
system models for planning construction project
logistics. Journal of Civil Engineering and Management
XI: 73-82.
Song J, Haas CT, Caldas Ch, et al. (2005) Locating
materials on construction site using proximity
techniques. ASCE Construction Research Congress
Proceedings of the Construction Research Congress.
San Diego, CA.
Spillane JP and Oyedele LO. (2013) Strategies for effective
management and safety in confined site construction.
Australasian Journal of Construction Economics and
Building 13: 50-64.
Spillane JP and Oyedele LO. (2017) Effective material
lobistics in urban construction sites: a structural
equation model. Construction Innovation 17: 406-428.
Ying F, Tookey J and Roberti J. (2014) Addressing
effective construction logistics through the lens of
vehicle movements. Engineering, Construction and
Architectural Management 21.
Simulation of Vehicle Movements for Planning Construction Logistics Centres
263