P4 2.0 55.6 3.6 100.0
P5 7.8 100.0 7.8 100.0
P6 8.3 58.2 14.2 100.0
P7 8.3 12.7 19.5 30.0
P8 7.0 70.0 8.5 85.5
P9 2.4 100.0 2.4 100.0
P10 1.0 100.0 1.0 100.0
P11 20.0 10.0 20.0 10.0
P12 12.0 55.8 12.0 55.8
P13 32.5 81.3 32.5 81.3
P14 2.7 100.0 2.7 100.0
P15 2.3 40.9 5.7 100.0
P16 2.6 100.0 2.6 100.0
P17 1.0 14.7 6.8 100.0
P19 0.0 0.0 5.0 100.0
P20 10.0 45.5 22.0 100.0
P22 1.0 16.7 6.0 100.0
P23 1.0 20.0 5.0 100.0
P24 20.0 24.4 32.8 40.0
P25 20.0 21.1 95.0 100.0
Based on table 4.5, there is a difference between
the amount of supply and demand. At low load, there
is a difference of 0.1 MW while at peak load, there is
a difference of 0.26 MW. At low loads, there are 60%
power plants whose production capacity is not used at
all. Whereas during peak loads there are only 30%
power plants whose production capacity is not fully
utilized
4.2 Analysis
The SEED model succeeded in scheduling a more
detailed power plant and distribution. Power plant
scheduling is done using the economic dispatch
model. In addition to scheduling a power plant, the
SEED model also simultaneously optimizes
distribution lines and losses as well as the goal of
minimizing total fuel costs. The total fuel cost is
influenced by the characteristics of the plant, the
amount of electricity demand, and losses in the
transmission/distribution network. The longer the
distance that must be traveled by electricity from the
generator to the customer, the greater the losses that
will occur. In this case, the losses on the
transmission/distribution network are affected by
mileage.
Minimizing losses can be an effort to reduce total
fuel costs. However, minimizing losses does not
always produce the smallest total cost. This can occur
due to different generator characteristics. If the
electric power system has the same generator
characteristics, reducing losses will automatically
reduce the total fuel cost.
Based on experiments using five scenarios, it is
known that: Scenario 1: If losses can be minimized,
PLN's power plants are able to meet electricity
demand at low load and peak load. Electricity demand
during peak load is 343.4 MW, while the production
capacity of all PLN-owned power plants is 346.6
MW, meaning that if losses on the entire transmission
network can be reduced below 3.2 MW, the PLN-
owned power plant can serve demand at the time peak
load. However, if losses cannot be controlled, then the
electricity demand must be supplied from other plants
through a cooperation mechanism. Cooperation
between generators as electricity suppliers must be
calculated in detail. This is due to differences in the
characteristics and location of each power plant
owned by electricity suppliers. Differences in
generator characteristics cause differences in total
fuel costs and emissions.
Based on the simulation results for scenario 2,
cooperation between PLN's power plant and IPP can
supply electricity during low load and peak load. This
is because the combined production capacity of PLN
+ IPP is greater than the total demand and losses.
When the load is low, the production capacity of PLN
and IPP's power plants is used in a balanced manner.
During peak load, all IPP's power plant production
capacity is used, while PLN's power plant production
capacity is 55% used. Although the percentage of
PLN's power plant capacity usage is smaller, losses
and emissions generated are greater than IPP's.
In scenario 3, cooperation between PLN's power
plants and rental plants can meet electricity during
low and peak loads. As a percentage, the cooperation
between the two prioritizes the use of rental power
plants compared to PLN's power plants during peak
loads, the production capacity of rental plants is used
entirely
In scenarios 4 and 5, the same pattern is found.
Production priority is always given to the Excess
capacity generator. Even in scenario 4, both under
low load and peak load conditions, the Excess
Capacity generator is the main generator.
In general, it can be said that PLN's power plants
are the ones with the lowest fuel costs. This can be
seen in the utilization of plants, which are almost
always 100%. However, the production capacity of
PLN's power plants has never been used at 100%. In