Measurement of Project Risk Management Maturity Level using
Project Management Maturity Model (PMMM): Case Research a
Telecommunication Company in Indonesia
Akhmal Muammar Dwiki Rafsanjani, Devi Pratami, Achmad Fuad Bay and Ageak Raporte Bermano
School of Industrial Engineering, Telkom University, Jl. Telekomunikasi Terusan Buah Batu No.1, Bandung, Indonesia
Keywords: Risk, Project Management Maturity Model, Project Risk Management, Construction, Project-Based
Organization
Abstract: Construction projects are highly dynamic, but have a lot of risks in every field of work. To reduce the
occurrence of a risk to the project, it is obligatory to do project risk management to avoid losses to the
project time, cost, and quality. Evaluation of risk management also needs to be done to improve the quality
of project risk management. Hence, this research aims to improve project management in one of the project-
based organizations in Indonesia by measuring the maturity level of project risk management. This research
uses the Project Management Maturity Model (PMMM) as its framework with seven risk management
processes as its criteria. This criterion will be used to compile a self-assessment survey that will be
disseminated to gather evidence. This research also carried out the weighting and ranking of these criteria
using the Analytical Process Hierarchy (AHP) method. The results of this research found that from the
results of weighting and ranking that the criteria of priority are plan risk management, and the maturity level
obtained in the six risk management processes at level 1which is the initial process, and one process at level
4 which is the managed process. Overall, the maturity level of PBO project risk management is currently at
level 1, which is the initial process.
1 INTRODUCTION
Construction projects have close links with
economic, social, and infrastructure development for
any country. Construction projects can provide
employment, encourage growth, and act as a link
between other sectors and the economy (Dixit et al.,
2018). The construction project itself is a dynamic
field and has a lot of risks, especially construction
projects which are very flexible and complex have a
very high risk because it is implemented outside and
involves many parties (Alifen, Setiawan, and
Sunarto, 1999). When working on a construction
project, it is very important to do risk management
to avoid loss of costs, qualities, and project
schedules. Risk management is an approach taken to
risk by understanding, identifying, and evaluating
the risk of a project (Labombang, 2011).
Yazdanifard and Ratsiepe (2011) stated that one of
the main problems of project management is the
poor risk management implemented by the company
because of risk management covers and influences
all activities in a project. In a research conducted by
Pratami, Fadlillah and Haryono (2018) on one of the
telecommunications construction projects, there
were found 27 risks with a very high level, 6 risks
with a high level, and 3 risks with a very low level
so a risk assessment is needed when the project will
begin to find out the risks contained in the project.
The results of the Project Management Institute's
(2018) research stated that poor project performance
was occurred due to low levels of project
management maturity. The level of project
management maturity allows organizations to
identify how to improve project performance
(Brookes et al., 2014). This was reinforced by the
research conducted by Kaming and Setyanto (2009),
which stated that there is a relationship between the
maturities of project management with the level of
success of project implementation. Therefore it is
important to know the extent of the achievement of
organizational performance through the level of
maturity of its project management
76
Rafsanjani, A., Pratami, D., Bay, A. and Bermano, A.
Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a Telecommunication Company in Indonesia.
DOI: 10.5220/0009405900760083
In Proceedings of the 1st International Conference on Industrial Technology (ICONIT 2019), pages 76-83
ISBN: 978-989-758-434-3
Copyright
c
2020 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
(Hartono, Wijaya and Arini, 2014).
To explain this research in more detail, a
research case was taken at one of the PBO (Project-
Based Organizations) in Indonesia engaged in
telecommunications services and networks. The
project management problem is one of the issues in
this organization, especially in project risk
management. Therefore the purpose of this research
is to identify the maturity level of the organizational
project risk management in order to improve the
performance of project risk management
implementation.
This research is expected to have a contribution
to developing project risk management maturity
assessment by using the PM Solutions project
management maturity model (PMMM), as the PM
Solutions model has not all yet integrated with
PMBOK 6
th
edition. This research gives additions to
implement risk response and monitor risk process to
the maturity assessment in order to be integrated
with the PMBOK 6
th
edition. The result of this
research can also be used in other projects and
organizations engaged in construction, especially
telecommunication construction, to escalate the
maturity level of their project risk management.
2 LITERATURE REVIEW
2.1 Analytic Hierarchy Process (AHP)
Analytic Hierarchy Process is a measurement
method used to obtain an assessment of the scale
made consisting of and continuous (Saaty, 1987).
AHP has special applications in making group
decisions and is used throughout the world in
various decisive circumstances in fields such as
government, business, industry, health care, and
education (Saaty, 2008).
The procedure for conducting AHP can be
summarized as follow (Saaty, 2008):
Define the research problem and form it into a
hierarchy. The hierarchy contains objectives,
criteria, and alternatives;
Make a pairwise comparison matrix filled
with a comparison of elements in pairs
according to the criteria;
The assessment synthesis to produce a whole
set of priorities for the hierarchy;
Check the consistency of the assessment;
The final decision will be obtained based on
the process that has been done.
2.2 Project Management Maturity
Model (PMMM)
Project Management Maturity Model (PMMM) is a
tool developed and used to measure the level of
project management maturity (Patel, Sharma, and
Shah, 2016). PMMM is a conceptual framework
where the project management process can be
optimized to improve organizational capability
efficiently. PMMM has been used as a reference to
measure the level of project management maturity in
various industries. PMMM offer best practice to
assist organizations determine the maturity of the
organizational project management processes, map
logical pathways to improve organizational
processes, determine priorities for short-term
process improvement actions, find out the need for a
project management office and assess compliance
with organizational structure, track progress towards
improvement plans project management, building a
culture of project management excellency
(Crawford, 2015).
Plan Risk
Management
Identify Risk
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
Plan Risk Response
Implement Risk
Response
Monitor Risk
Project Risk
Management Process
Figure 1: Project Risk Management Hierarchy Process
Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a
Telecommunication Company in Indonesia
77
Figure 2: PM Solutions Project Management Maturity Model
3 RESEARCH METHODOLOGY
3.1 AHP Implementation
The Analytic Hierarchy Process used in this research
aims to weight and rank the project risk management
process because AHP can be applied to prioritize
available criteria by weighting criteria and ranking
(Forman and Gass, 2001). Weighting is
implemented by expert judgments that have
experience in telecommunications construction
project work. AHP in this research has seven
criteria, which are project risk management
processes obtained from PMBOK 6th Edition. The
hierarchy arrangement in this research is shown in
Figure 1.
3.2 Model Determination
This research uses the PM Solutions Project
Management Maturity Model (PMMM) as the
maturity model. The PM Solutions model was
developed by a team of experienced project
managers and has been successful in helping many
ProjectManagementMaturityModel
LEVEL1
Initi al Process
LEVEL2
Structured
Processand
Standards
LEVEL3
Organizational
Standardsand
Institutional
Process
LEVEL4
Managed
Proce ss
LEVEL5
Optimizing
Process
Project
Integeration
Management
Project
Scope
Management
Project
Time
Management
Project
Cost
Management
Project
Quality
Management
Project
HumanResource
Management
Project
Communication
Management
Project
Risk
Management
Project
Procure ment
Management
Project
Stake holder
Management
ProjectRiskManagementis
broken downintospesisf ic
1.Planrisk management
2.IdentifyRisk
3.PerformQualitativeRisk
Anal ysis
4.PerformQuantitativeRisk
Anal ysis
5.PlanRiskResponse
6.ImplementRiskResponse
7.Moni torRisk
Spe ciccomponentsareused
tomeasurematurityand
de velopactionplans
Maturi tyLevel
ICONIT 2019 - International Conference on Industrial Technology
78
companies measure their level of maturity (Grant
and Pennypacker, 2015). The structure of the PM
Solutions Model is shown in Figure 2, and this
model has been defined by the process of project
risk management in accordance with the standards of
the PMBOK 6
th
edition.
The model of PM Solutions has five levels of
maturity that is in correspond with the structure of
the SEI Capability Maturity Model (Grant and
Pennypacker, 2015). In table 1, the maturity level is
further described and adjusted to project risk
management (Crawford, 2015):
Table 1: Explanations of each maturity level
Level Description
Level 1: Initial Process
The organization does not
have a method or approach
related to PRM, and the
process is only done on an
ad hoc basis, management
awareness related to
project risk management is
very low
Level 2: Structured
Process and Standards
There is a PRM process,
but it is only used for large
scale project, management
has supported the
implementation of project
risk management
Level 3: Organizational
Standards and
Institutionalized Process
All PRM processes have
standards for all projects
and can be reused; the
processes and standards
used by the organization
are formally documented.
Level 4: Managed
Process
The PRM process has been
integrated with
organizational processes
and systems, and
management has mandated
to comply with the PRM
process, there is an
analysis of project
performance
Level 5: Optimizing
Process
There is a process to
measure the effectiveness
and efficiency of the
project, and there are
lessons learned,
management is more
focused on continuous
improvement
3.3 Designing Self-Assessment Survey
The self-assessment survey was designed with
adjustments to the description of the maturity level
of the PM Solutions model and consisted of 48
question items. The self-assessment will be given to
three company managers, project managers, and the
project team to be filled in accordance with
company conditions accompanied by evidence to
support the assessment. The evidence will be
validated to ascertain whether the evidence is in
accordance with the criteria or not.
3.4 Validation of Research Result
Validation is done after the result of AHP
management and project risk management maturity
level measurement is obtained. The validation is
done with the help of expert judgment. Expert
judgment is determined through several criteria such
as already having project management certificate,
experience in project management, and around ten
years' experience in the construction project,
especially telecommunication constructions.
4 RESULT
4.1 Weighting and Ranking of AHP
The results of the weighting implemented by the
expert judgment are included in the comparison
matrix of the results of the recapitulation of
comparison criteria including plan risk management,
identify risk, perform a qualitative risk analysis,
perform a quantitative risk analysis, plan risk
response, implement risk response, and monitor risk.
Then normalize the project risk management
maturity criteria until the weighting and ranking of
the project risk management criteria are shown in
Table 2.
.
Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a
Telecommunication Company in Indonesia
79
Figure 3: Result of Project Risk Management Maturity Level
Based on Table 2 it can be deduced that the order
of importance of the project risk management
maturity criteria from highest to lowest in a row are
plan risk management, identify risk, perform a
qualitative risk analysis, plan risk response,
implement risk response, monitor risk, and perform
a quantitative risk analysis
Table 2: Result of AHP
Criteria Priority
Vector
Percentage Rank
Plan Risk
Management
0,28 28% 1
Identify Risk 0,19 19% 2
Perform Qualitative
Risk Analysis
0,15 15% 3
Plan Risk Response 0,14 14% 4
Implement Risk
Response
0,11 11% 5
Monitor Risk 0,08 8% 6
Perform
Quantitative Risk
Analysis
0,05 5% 7
4.2 Project Risk Management Maturity
Level
The results of the assessment of the project risk
management maturity level on PBO presented in the
form of a spider web diagram in Figure 3 can be
obtained that there is a process that is at level 4
(managed process), which is risk monitor. This can
be stated that the company in this process has been
in a managed process. This means that at that level,
the company has integrated the risk monitoring
process with the processes that are in the company.
Management has given the mandate to comply with
regulations on the risk monitoring process. In
implementing the risk monitoring process, the
company is already in accordance with the views of
the organization. In making a decision, the company
has used data. It also makes risk monitoring a
process with the highest level.
In contrast to the risk monitor in the risk
management plan process, identify risk, perform a
qualitative risk analysis, perform a quantitative risk
analysis, plan risk response, and implement risk
response, the company is only at level 1, which is
the initial process. This means that the company
does not yet have a standard and basic process in
implementing the six processes. This is caused by
the lack of awareness and understanding of
management related to the implementation of project
risk management.
Overall, based on PMMM, the risk level of the
company's project management is still at level 1,
which is the initial process. It can be concluded
because in determining the level of maturity must be
taken from the lowest level because to reach a level,
and then all criteria must be met. So that the
achievement level cannot move to the next level
before all criteria have been fulfilled (Crawford,
2015). The company needs a lot of improvement
1
1
1
11
1
4
0
1
2
3
4
5
Plan Risk
Management
Identify Risk
Management
Perform Qualitative
Risk Management
Perform Quantitative
Risk Management
Plan Risk Response
Implement Risk
Response
Monitor Risk
PROJECT RISK MANAGEMENT MATURITY LEVEL
ICONIT 2019 - International Conference on Industrial Technology
80
from many aspects to increase the level of maturity.
This is inversely proportional to the current
condition of the organization, which requires a high
level of project risk management maturity because
the projects that the organization is working on are
at the medium to a high level with contracts worth
hundreds of millions to billions of rupiahs, which
means it has many risks. All of these things will not
be achieved if there is no contribution from
management as well as the employees.
4.2.1 Plan Risk Management
In the plan risk management process, there are six
attributes that have been prepared based on the
maturity level, based on the results of the self-
assessment survey obtained that the company is
unable to meet the six attributes. It can be concluded
that in this process, the company is at level 1, which
is the initial process, where there is still a lack of
awareness of the company regarding the
implementation of risk management plans. This lack
of awareness means that the company has never
undertaken a risk management plan for the
undertaken projects and tends to ignore the
application of this process, thus creating no
document related to risk management that can be
used and accessed by the project team.
4.2.2 Identify Risk
In the identity risk process, there are six attributes
that have been arranged based on their level of
maturity. Based on the results of the self-assessment
survey, obtained that the company could fulfill three
attributes, including two attributes at level 1 and one
attribute at level 5, but the company remained at
level 1 which is the initial process because the
company was unable to meet the attributes at level 2
to level 4 even though the attribute at level 5 has
been fulfilled.
The company's inability to meet these attributes
is due to various things, namely:
The company does not have a process
document to identify risks so other projects
cannot use the process;
The company is more inclined to identify risks
in depth when these risks arise or when a
problem occurs;
In identifying risks, the company has not yet
done it on a project scale, so it is more likely
to only consider in terms of time and cost
alone.
The inability of this company also affects the
lessons learned less maximally.
4.2.3 Perform Qualitative Risk Management
In the perform qualitative risk analysis process, there
are six attributes that have been arranged based on
their maturity level. Based on the results of the self-
assessment survey obtained that the company can
meet two attributes, namely attributes at level 1 and
at level 4. It can be said that the company is at level
1, which is the initial process because the company
cannot meet the attributes at level 2 and level 3. The
company is at level 1 strengthened by the fulfillment
of attributes stating that when risks are identified,
the project manager will spontaneously speculate on
the impact of these risks without using any
procedures.
4.2.4 Perform Quantitative Risk
Management
In the quantitative risk analysis process, there are six
attributes that have been arranged based on their
level of maturity. Based on the results of the self-
assessment survey obtained that the company can
meet one attribute, namely the attribute at level 5.
However, it can be said that the company is at level
1, namely the initial process, because the company
cannot meet the attributes at level 1 and level 4.
In this process, the company is able to meet the
attributes at level 5 in the form of lessons learned to
improve handling. However, in the lessons learned,
there are shortcomings; namely, the content in the
document is less than the maximum due to the non-
fulfillment of the attributes at the previous level.
4.2.5 Plan Risk Response
In the plan risk response process, there are 11
attributes that have been prepared based on the
maturity level. Based on the results of the self-
assessment survey obtained that the company can
meet two attributes, namely, attribute at level 3. It
can be said that the company is at level 1, namely
the initial process, because the company cannot meet
the attributes at level 1 to level 5.
The company's inability to meet these attributes
is due to various things, namely:
The company is not able to meet the attributes
at level 1 that is because when planning the
risk response, the project team will carry out a
mitigation strategy when the risk has occurred.
The absence of mitigation strategies for future
events will cause the implementation of risk
responses not to be maximized. This
deficiency also reinforces the statement that
the company in this process is still at level 1;
Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a
Telecommunication Company in Indonesia
81
Next is company's inability to meet the
attributes at level 2 and level 3, it is caused by
the company not having standard procedure
documents in risk response planning so that
the project team does not have guidelines for
making or developing risk response planning;
At level 3 attributes, the company is able to
fulfill two of the five attributes that have been
prepared. Both of these attributes have been
fulfilled because in developing the company's
risk response it has an application that has
been integrated with the company's cost and
time management, but the company has not
yet integrated with the financial and
accounting systems, strategic planning
processes, and PMO which causes the
company cannot fulfill other attributes;
The last drawback is the company does not
have an allocation of the project contingency
costs, so it cannot be used to determine the
efficiency and effectiveness of the project.
4.2.6 Implement Risk Response
In the implementing risk response process, there are
six attributes that have been arranged based on their
maturity level. Based on the results of the self-
assessment survey obtained that the company can
only meet the attributes at level 3. So it can be said
the company is at level 1, namely the initial process,
because the company cannot meet the attributes at
level 1 to level 5.
The company's inability to meet these attributes
is due to various things, namely:
Company is not able to meet the attributes at
level 1 because the company does not do a
formal risk response planning so that no risk
response documents are planned and agreed
upon;
Company is not able to meet the attributes at
level 2 because the company does not have a
standard process in implementing the risk
response so that in the process of
implementing a risk the project team does not
use a standard process;
Next, the company does not have a risk
response implementation report document so
that the implementation process cannot be
analyzed and evaluated. Also, the absence of
lessons learned from the process of
implementing the risk response that the
implementation process cannot be improved.
4.2.7 Monitor Risk
In the monitor risk process, there are seven attributes
that have been arranged based on their maturity
level. Based on the results of the self-assessment
survey obtained that the company can meet five
attributes and two attributes that have not been
fulfilled, namely an attribute at level 4 and attributes
at level 5. So it can be said that the company is at
level 4, namely managed process even though there
is one attribute at level 4 that has not yet been
fulfilled, but most of it has been fulfilled, so the
company stays at level 4.
Attributes that are not fulfilled are attributes at
level 4, namely the risk control system is not
integrated with the monitoring program because the
company does not yet have a monitoring program,
but the company's risk control system has been
integrated with other organizational control systems
and the cost and time management program. The
next attribute that is not met is the attribute at level 5
that the company does not yet have lessons learned
that serve to increase risk monitoring efforts.
5 CONCLUSION
From the calculation of the level of maturity, it is
obtained that overall PBO is still at level 1, which is
the initial process. In general, the PBO does not have
a method or approach related to PRM, the PRM
process is only conducted on an ad hoc basis, and
management awareness regarding project risk
management is very low. Especially the most
highlighted is the risk management plan process,
which is at level 1, whereas based on calculations
using AHP, the risk management plan is ranked 1.
With project risk management at level 1, this
PBO is certainly very far from best practice in
project management, because level 1 is the lowest in
the available maturity level. The company itself
wants to continue to improve the quality of risk
management and the expectations of employees and
the project team to have special documents and
applications that discuss project risk management,
and then the company must improve and enhance
the maturity level of their project risk management.
It is highly recommended that PBO can provide
counseling guidance to company management on the
importance of risk management to the project. As a
result of this counseling, management can further
develop the implementation of risk management,
such as conducting training and workshops for
project management and the team. This is certainly
ICONIT 2019 - International Conference on Industrial Technology
82
done in order to improve performance in
implementing risk management projects to achieve
better results for undertaken projects. This
measurement is implemented to determine the
company's achievements for now and can be used as
an evaluation to help in the company's continuous
improvement.
In this research, it has been proposed an
improvement plan to increase the maturity level of
project risk management in accordance with the
current organizational level, which is at level 1,
namely the initial process. The organization can
understand more about the maturity level of project
risk management from this research. In addition, the
organization can also find out the strengths and
weaknesses of project risk management. However,
this research only measures project risk
management, and further research is needed to
determine the organizational maturity level of the
overall project management by measuring other
knowledge areas.
REFERENCES
Alifen, R. S., Setiawan, R. S., and Sunarto, A. (1999)
‘Analisa "What If" Sebagai Metode Antisipasi
Keterlambatan Durasi Proyek,' Dimensi Teknik Sipil,
1(2), pp. 103–113.
Brookes, N. et al. (2014) ‘The use of maturity models in
improving project management performance An
empirical investigation,' International Journal of
Managing Projects in Business, 8(4), pp. 679–695.
Crawford, J. K. (2015) Project Management Maturity
Model - Review, Project Management Journal. New
York: CRC Press.
Dixit, S. et al. (2018) ‘Construction Productivity and
Construction Project Performance in Indian
Construction Projects’, m(July).
Forman, E. H. and Gass, S. I. (2001) ‘The Analytic
Hierarchy Process — An Exposition CH RO NICLE
THE ANALYTIC HIERARCHY PROCESS — AN
EXPOSITION’, (October 2014).
Grant, K. P. and Pennypacker, J. S. (2015) ‘Project
Management Maturity: An Assessment of Project
Management Capabilities Among and Between
Selected Industries’, (March 2006). doi:
10.1109/TEM.2005.861802.
Hartono, B., Wijaya, D. F. N. and Arini, H. M. (2014) ‘An
empirically verified project risk maturity model:
Evidence from Indonesian construction industry’,
International Journal of Managing Projects in
Business, 7(2), pp. 263–284. doi: 10.1108/IJMPB-03-
2013-0015.
Kaming, P. F. and Setyanto, E. (2009) ‘Studi Mengenai
Kematangan Manajemen Proyek Pada Kontraktor’,
3(KoNTekS 3), pp. 6–7.
Labombang, M. (2011) ‘Manajemen Risiko Dalam Proyek
Konstruksi’, Jurnal SMARTek, 9, pp. 39–46.
Patel, D. R., Sharma, N. D. and Shah, R. A. (2016)
‘Development of Project Management Maturity Model
for Measuring Success of Construction Projects in
Surat City’, International Journal of Scientific
Development and Research, 1(5), pp. 149–152.
Pratami, D., Fadlillah, F. and Haryono, I. (2018)
‘Designing Risk Qualitative Assessment on Fiber
Optic Instalation Project in Indonesia’, 2(1).
Project Management Institute (2018) ‘PULSE OF THE
PROFESSION ® | 2018 - “Success in Disruptive
Times | Expanding the Value Delivery Landscape to
Address the High Cost of Low Performance”’, p. 35.
Available at: https://www.pmi.org/learning/thought-
leadership/pulse/pulse-of-the-profession-2018.
Saaty, R. W. (1987) ‘THE ANALYTIC HIERARCHY
PROCESS-WHAT AND HOW IT IS USED’, 9(3),
pp. 161–176.
Saaty, T. L. (2008) ‘Decision making with the analytic
hierarchy process Decision making with the analytic
hierarchy process’, (JANUARY 2008). doi:
10.1504/IJSSCI.2008.017590.
Yazdanifard, R. and Ratsiepe, K. B. (2011) ‘Poor Risk
Management as One of the Major Reasons Causing
Failure of Project Management’.
Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a
Telecommunication Company in Indonesia
83