This study also assume that farmers able to plant
palawija (a kind of crop that does not need much wa-
ter in growing, such as beans, corn, chili, casava,
or sweet potato) 2 times within a year and it is pre-
dicted producing 2 tons per hectares. The farmer
can sale within IDR5,000 per kilogram of palaw-
ija. If the cost of plantation is approximately 35%
of the harvest’s value, so the revenue of two times
in harvest is 2 x 2 x 1000 x 0.65 x IDR5,000 =
IDR13,00,.000. Therefore, this study assumes the
farmer who has 5 hectares of field will result ap-
proximately IDR355,000,000 within a year (10 x
(IDR22,500,000 + IDR13,000,000)).
Analysis of fishery is an analysis to predict the
reservoir’s extraordinary result. This study assumes
that a pond within 1 m3 is optimum for approximately
10 fish and net profit from fishery is IDR30,000.00
within 8 months. According to the volume of reser-
voir aproximately 3,740 m
3
, the reservoir results
profit IDR112,200,000. Analysis of profit from recre-
ation activity, such as water tour, also can be predicted
and it is based on the number of reservoir’s visitor. If
there are 10 persons/each day and each of visitor has
to pay IDR2,000.00, therefore revenue from recre-
ation activity is approximately IDR7,200,000 within
a year.
Based on estimated project’s cost, the total of
initial project’s investment is IDR3,200,000,000 and
the project’s operation cost is IDR60,000,000 within
a year. This study also estimate the project’s
benefits and the estimation of reservoir’s result is
IDR474,000,000 within a year. The next step is to an-
alyze NPV, B/C ratio, dan IRR of project. Why is the
analysis impoartant? The project requires investment
and operating cost, but the project’s benefits only can
be acquired periodically after project’s building.
Table 2: The Economic Analysis of Embung Kedung Poh
No Discount
Rate (i)
NPV (IDR) B/C
Ra-
tio
IRR(%)
1 8% 1.834.573.580 1.467
13.62
2 10% 1.019.098.513 1.267
3 12% 398.169.008 1.107
4 14% (83.367.534) 0.977
5 16% (463.340.090) 0.871
The analysis of NPV, B/C ratio, and IRR need
assumptions as stated follow (Salsabiila, 2016): dis-
count rate up to 12%, the length time of the project
up to 25 years, the length time of constructing up to
1 year, the optimum estimated land developing after
10 years, the benefit increases during the term of the
time in line, 1 US$ = IDR10,000 and the bank’s in-
terest rate up to 12.00%. Based on that assumption,
the result of analysis is NPV = IDR398,169,008, B/C
ratio = 1.107, and IRR = 13.62% (see table 2).
The analysis of NPV determines the execution of
the project whether fixed or unfixed. If NPV > 0
means a project is fixed economically. According
to NPV analysis with bank interest rate up to 12%,
project results IDR398,169,008, so the project of Em-
bunng Kedung Poh has fixed economically. The anal-
ysis of B/C ratio reveals that the project is also fixed
economically, because the value of B/C ratio is more
than 1 (one). The analysis of IRR is based on discount
rate determination, which all future revenue possibil-
ity is predicted in certain discount rate. Therefore
this study calculates IRR’s value in some interest rate
schema, such as smallest positive NPV and smallest
negative NPV.
3.2 Sensivity Analysis
The second step of the analysis is a sensivity anal-
ysis that describes several economic result on sev-
eral assupmtions. This study applies present worth
(PW) method to capture the several possibility of eco-
nomic value. As an ilustration, this study determines
the interest rate i.=.12% , so the value of NPV is
IDR398,169,008. If this study determines the interest
rate i.=.14%, so the value of NPV is IDR- 83.367.534
(see tabel 2). This study also consider the value of
IRR up to 13.62%. If the value of IRR is higher than
market return that has interest rate up to 12 %, so the
project is economically eligible to execute.
This study also apply different schema of inter-
est rate to reveal different of economic result, such
as detailed in three schema. First, this study as-
sumes that cost increases up to 10% within stable
benefit, so the study reveals that the value of NPV
= IDR346,071,967 (positive), the value of B/C ratio =
1.092, and the value of IRR = 13.41%. Second, this
study assumes that the benefit of project decreases up
to 10% within stable cost, so this study reveals that the
value of NPV = IDR13,744,934 (negative), the value
of B/C ratio = 0.996, and the value of IRR = 11.94%.
Finally, this study assumes the cost increases up to
10%, but the benefit of project decreases up to 10%.
Therefore, the value of NPV = IDR65,841,976 (nega-
tive), the value of B/C ratio = 0.983, and the value of
IRR = 11.73%. This sensivity analysis indicates that
the optimum of IRR’s value approximately on 12%
interest rate, because the value of NPV and the value
of B/C ratio has lowest.
This study implements feasibility analysis on
reservoir’s project kedung poh (embung kedung poh)
at District Gunung Kidul and the analysis includes
The Feasebility Analysis of Public Investment: Evidence of Reservoir
51