Measurement of height difference can be done
with a flat slope measurement tool, measuring the
height difference with a flat slope is the process of
determining elevation or finding a different height
between measured points (Masrul & Anjasmara,
2015). The role of the survey is to ensure that the
excavation area and/or work floor elevation are
following the plan. If the excavation has matched
with the design elevation plan, the geological team
will check to ensure that the excavated land as
compared to the specifications with planning design
by the geological team, height between measured
points (Masrul & Anjasmara, 2015). The role of the
survey is to ensure that the excavation area and/or
work floor elevation are following the plan. If the
excavation has matched with the design elevation
plan, the geological team will check to ensure that the
excavated land as compared to the specifications with
planning design by the geological team.
Stake out elevation and work floor marking,
stake out elevation is to determine the point that
will be the elevation limit of the work floor plan
if the excavation of the land has passed the
work floor plan design (Figure 5). In the
implementation of stake out, fixing and
checking reference points is the first step that
must be taken (TS-04, 2011). To fix the work
floor elevation limit, it can be fixed by using
measurement tools, i.e. a water pass, the
accuracy of deter- mining the size depends on
the tools used as well as on the accuracy of
measurement and what can be executed (Frick
& Heinz, 1984). After obtaining the work floor
elevation limit, the work floor boundary
marking is carried out to obtain the work floor
top cast. The implementation of stake out
elevation in the field is carried out using the
formula below, i.e:
Re f Ele(A)WP = Re f Ele(A) + Re f Signs(A) (1)
SignsRead(B) = Re f Ele(A)WP–CastTEle(B) (2)
The excavation situation was measured using
wa- ter pass and meter. Water pass is used to
get full cast from the work floor and work floor
bound- aries (Figure 6). Excavation situation
data is taken by cross technique taken per 1
meter. Through the measurement of the
excavation situation, it can be seen how the
cross-section of excavated land is through the
results of the profile lengthwise and the
transverse profile.
Figure 5: Stake out and work floor elevation marking
techniques.
Figure 6: Data retrieval technique for dredging situation.
The results of this measurement will be processed
to obtain the volume of work floor casting using the
cross-section method with the Mean Area equation
with the following formula (Adi & Aghsatya, 2017):
𝑉
𝐿 (3)
𝑉
𝐿 (4)
Where:
V
n
: nth section average volume (m
3
),
A
1
: Cross-sectional area 1 (m
2
),
A
2
: Cross-sectional area 2 (m
2
),
L : Distance between each section (m).
Figure 7 is the stage of the wall structure work,
which is the final stage in developing the energy
reducing construction. Stakeout and marked elevation
of the nth section from wall design, Stakeout
elevation or vertical stakeout is the measurement of
the main points position and the vertical details of the
building. The first step is, of course, the determination
of the foundation elevation at a predetermined
location through the measurement of horizontal
stakeholder outs. After determining the elevation of
the working wall plan, estimation of the volume of
concrete needed for casting can be estimated. If
landslides occur in the wall structure area, the need
for concrete for casting will increase. The landslide
result, fillings and/or dental casting are carried out to
cover the landslide area so that the initial concrete
requirements according to the plan based on the work
drawings are added to the volume of the landslide.
Calculating volume of the landslide, the survey team
took measurements of the situation of the landslide
area, in this measurement using a meter by calculating
the distance between the structure of the building and
the area affected by the landslide.