Adaption Agile Project Management Methodology in Alteration and
Addition Work: Study Case 105 Years Hotel Doulos Phos
Prastiwo Anggoro
Project Manager PT CSK Insulation Engineering.
Keywords: Complexity, 105 Years, Ship, Ship Hotel, S Curve
Abstract: One of aspects plays key important to deliver successful of projects is Project Management. More than 75%
project failed due to the complexity in of the project which are determines how the work should be done and
what the best methodology to implemented. Science and Engineering has been changes from industry 1.0
when the discovery of the steam engine to industry 4.0 as marked as an artificial intelligent engine.
Construction of Hotel Ships that have been more than 105 years old (sailing over the world), required
combination project management methodology to create shipbuilding into an onshore hotel with additional
rooms and other supporting facilities such as reclamation land, swimming pools, massage rooms, Carpark.
Located in Bintan - Lagoi, the application of agile methodology into project implementation becomes
important to break the deadlock in work methods that result in deviations in the S-Curve. Daily monitoring
into work sub-items with analysis per hotel room becomes an important milestone to raise the actual S-curve
close to the S-curve plan.
1 INTRODUCTION
1.1 Background
PT CSK Insulation Engineering, as integrated EPC
contractor, specializes services provision of
mechanical & electrical installation, including
insulation and architectural, and construction for
commercial building awarded HVAC, Fire Protection
System, and Plumbing A&A Doulos Phos Hotel. MV
Doulos is a retired cruise ship, the ship has previously
been known as the SS Medina ordered 1913 and
launched 1914 (two years after legendary Titanic ship
was sinking in the North Atlantic Ocean). As-built
weight around 5,426 Gross register tonnage and
conversion into hotel weight raise to 6,818 Gross
tonnage.
Holding the Guinness World Records as The
“World’s Oldest Active Ocean Going Passenger
Ship”, in 2009 end of cruising service and become
scrap ship at dry dock Singapore. Until 2010, MV
Doulos had new owner Mr. Eric Shaw director and
chief executive of BizNaz Resources International Pte
Ltd in Singapore. She renamed as Doulos Phos means
Servant of Light and converting to a luxury hotel. In
2015, with the budget around USD $25 Million,
construction of hotel resort started in reclamation land
around 2,16 acre and consist of 104 rooms, swimming
pools, Jet Spa, Beach Club, Massage cabin,
Amphitheatre, Piano Lounge, and Restaurant.
Project start in august 2017 and planned to be
finished in December 2018. Consist of two area
which are External area and Internal Area. Sequence
of works from external area (exterior phase) and in
parallel certain part of internal area (majority at 1st
floor and Corridor area) , last part is room area
including finishing works called as interior phase. In
first 6 month progress running as per plan (S Curve),
each progress controlled using weekly plan, and
second 6 month progress running more slowly and
create gap at S- Curve.
The complexity occurred at Alteration and
Addition works of Doulos Phos hotel project when
progress reach interior phase. Each room was unique,
there are no similar rooms within 104 rooms,
decoration, bed location, furniture arrangement, and
even utilities at toilet . Because the interior rooms
perception of owner, consultant and contractor is not
in same line, makes progress even worse.
Projects stop almost more than 3-month, cause
delay, standby workers and increase stress constraint.
As Project manager, reverse project management
methodology needs to enforce. One of project
328
Anggoro, P.
Adaption Agile Project Management Methodology in Alteration and Addition Work: Study Case 105 Years Hotel Doulos Phos.
DOI: 10.5220/0010357303280330
In Proceedings of the 2nd International Conference on Applied Economics and Social Science (ICAESS 2020) - Shaping a Better Future Through Sustainable Technology, pages 328-330
ISBN: 978-989-758-517-3
Copyright
c
2021 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
management methodology called Agile management
means adaptive and developing solutions through the
collaborative effort.
1.2 Methodology
Project management institute introduces PM BOK
(project management body of knowledge) covered 5
processes, 10 knowledge area and 47 ITTO (Inputs,
Tools and Techniques, Outputs). Project schedule
controlled by S-Curve, which contains the percentage
each sub-items. Percentage of sub-items calculated
from the value of cost divide by overall cost. Each
works constructed by sequence and distributed as
Waterfall diagram. Using Empirical process (finish to
start concept), Time Cost and Quality described as
Triangle Line.
Agile management comes with defined process
with the stages consist of Envision, Speculate,
Explore, adapt and Close. Envision consist of Project
chapter, Team collaboration tools and Team Norms.
This is the foundation of agility. Triangle proses
Speculate, Explore and adapt are routine activities
described as a sprint. Retrospectives will be the end
of agility stage, this is called as Close stage
1.3 Problems
There are two main issues as described below:
a) Converting process from water fall to agile
b) Agile adaptation into ongoing projects
2 ANALYSIS
2.1 Type of Research
This study uses qualitative and quantitative research.
Qualitative data aim to understanding behavior of
workers and the reason that govern such behavior.
Quantitative data examine to statistical analysis of S-
curve progress.
2.2 Data-Data Collected
a. Duration: 2017 until 2019
b. Budget: Rp. 13.583.899.550,00
c. Manpower:
Indirect Cost: 1 Nos
Direct cost: 15 workers
Batam Team: 6 workers
Tj Uban Team: 9 workers
d. Scope of Works:
e. Plumbing works
f. Sprinkler System
g. Exhaust System
h. AC VRV System
i. Supply Chain
j. Consumables
Tj Uban Shop
Batam Shop
Main Materials
Batam Shop
Singapore Shop
k. Project Management
l. Water-Fall Methodology
m. Period: August 2017 - August 2018
n. Item of Works:
60% of Plumbing works
60 % of Sprinkler system
70% of AC VRV system
100% of Plumbing works at external area
100% of Plumbing works at spa toilet
100% of Plumbing works at Satay Club
toilet
100% of Plumbing works for Rainwater
Pipe + Pantry club
100% of Material Underground Hydrant
Pipe (BS SCH 40)
100% of Plumbing Works at SPA
Cabana
0 % of Supply and Install AC di B Deck
40% of Plumbing works at Semi Dining
Kitchen
100% of Exhaust + FAD Di kitchen
100% of AC at Boat Deck
100% of Water chamber
100% of Pump House
o. Agile Methodology
p. Period: December 2018 - Mei 2019
q. Item of Works:
r. 40% of Plumbing works
40 % of Sprinkler system
30% of AC VRV system
0% of Plumbing works at external area
0% of Plumbing works at spa toilet
0% of Plumbing works at Satay Club
toilet
0% of Plumbing works for Rainwater
Pipe + Pantry club
0% of Material Underground Hydrant
Pipe (BS SCH 40)
0% of Plumbing Works at SPA Cabana
100 % of Supply and Install AC di B
Deck
Adaption Agile Project Management Methodology in Alteration and Addition Work: Study Case 105 Years Hotel Doulos Phos
329
60% of Plumbing works at Semi Dining
Kitchen
0% of Exhaust + FAD Di kitchen
0% of AC at Boat Deck
0% of Water chamber
0% of Pump House
Figure 1.
3 CONCLUSIONS
An idle time occurred due to lack of coordination and
complexity in each room, the progress of works going
slow within 4-month cause manpower cost and gap of
S-Curve plan and actual wider. Agile methodology
creates a unique spring for each event, which is each
event consist of multiple teams. The converting from
waterfall to agility need commitment all stakeholder
and 4 basic monitoring control should adopt it daily
basis. As Project Manager identify the problems, find
the ways to solve it, change it the ways to do so and
even create a reverse methodology to meet the
triangle of project goals
REFERENCES
Mc Connell Dowell. 2015. Doulos Phos Maritime Lifestyle
Destination M&E Above Ground Fitout Works
Package Specification. Singapore.
Project Management Institute. 2017. Project Management
Body of Knowledge 6 th Edition. PMI
Elaine Pulalos and Robert B. Kaiser. 2020. To Build an
Agile Team, Commit to Organizational StaTeam,
Harvard Business School Publishing Corporation
Linkedln. 2018. Become an agile project manager.
Linkedln learning
ICAESS 2020 - The International Conference on Applied Economics and Social Science
330