2.2 Determine of Probability of Failure
(PoF)
Determination of the probability of Failure
(Probability of Failure), is done by evaluating the
parameters of the damage by considering the
percentage of each possible hazard that occurs. The
scoring system is carried out following the
requirements of the installation system. Parameters
and percentages used in the determination of PoF
such as
2.2.1 Corrosion Factor (30%)
Corrosion factors can cause a reduction in thickness
or a possible hazard to the walls of the installation
equipment (pipes and pressure vessels). A reduction
in thickness can be caused by the interaction of pipe
walls and pressure vessels with the products/fluids
contained in pipes and pressure vessels. To determine
the value of the corrosion factor, there are several
variables as follows: Inspection frequency (20%),
equipment service life (20%), external protection
(15%), equipment material (15%), fluid impact
(15%), water impact (15%).
2.2.2 Operating Condition Factor (25%)
In operating conditions, some factors may allow the
installation facility to fail. Factors that can cause
Failure are leaks in the installation equipment. To
determine the operating factor value, there are several
variables as follows: Excess flow (25%), excess
pressure (30%), pressure shift (15%), level shift
(15%), and temperature shift (15%).
2.2.3 Electrical Failure (5%)
In addition to leading equipment such as pipes and
pressure vessels, the ORF installation also includes
electrical instruments. As for the possibility of
damage that can occur to the electrical system caused
by internal factors (electrical equipment inspection
frequency) (55%) and external factors (history of
being struck by lightning ) (45%).
2.2.4 Leakage Factor (10%)
ORF installations have the highest design pressure of
2300 PSIG and an operating pressure of up to 1200
PSIG. Under these operating conditions, it can cause
erosion-corrosion and lead to leakage failure. To
determine the leakage factor value, there are several
variables as follows: Leakage history (40%), flange
management (30%), and valve inspection interval
(30%).
2.2.5 Third-Party damage (10%)
On the third party, factors indicate the extent of
activity or distraction from the third party to the ORF
installation. Third-party interference, in this case, is
the history and possibility of sabotage of the ORF
installation operation
2.2.6 Equipment Design (10%)
In the equipment system design factor, an assessment
is carried out on the suitability of the equipment
design with applicable codes and standards both
nationally and internationally.
2.2.7 Construction Factor (10%)
In the construction factor of the equipment, an
assessment of the suitability of the equipment with
the as-built drawing is also carried out and its
supervision.
2.3 Determine of Consequence of
Failure (CoF)
The consequences of Failure are determined based on
the risk parameters applied by the company by
considering the weight of each consequence factor on
the possible events that occur during operational
activities. The calculated consequence parameters
described as below.
2.3.1 Safety Factor (30%)
The variable of the safety factor is the level of fatality
that can occur in the Onshore Receiving Facility
Installation in the event of an operation failure. The
safety level is rated the size of the leak diameter. The
safety variable weights 30% of the total consequences
of installation failure.
2.3.2 Environmental Factor (25%)
The environmental impact variable is reviewed by the
level of pollution or damage caused by the installation
equipment if it experiences Failure or leakage. On the
consequences of environmental damage, an
assessment of the type of fluid service (40%),
flammability (30%), and population density (30%)
are carried out. The environmental damage variable
weighs 25% of the total consequences of installation
failure.