Interpretive Structural Model-based for Analysis of Causes of Delays
in Construction Projects: The Portuguese Case
Amílcar Arantes
1a
and Luis Miguel D. F. Ferreira
2b
1
CERIS, CESUR, Instituto Superior Técnico, Universidade de Lisboa, Av. Rovisco Pais, Lisboa,1049-001, Portugal
2
Univ. Coimbra, CEMMPRE, Department of Mechanical Engineering, Pólo II,
Rua Luis Reis Santos, 3030-788 Coimbra, Portugal
Keywords: Construction Delays, Construction Industry, Project Management, Interpretive Structural Modelling.
Abstract: Delays are a common issue in construction projects worldwide, and they can frequently have an influence on
time and cost overruns, among other problems. This study aims to add to the knowledge on construction
project management theory and practice by identifying the leading causes of Delays in Construction Projects
(DCP) in Portugal, modeling their interrelationships, and determining their main causes. The study presented
herein adopted a two-phase methodology. First, based on the literature, the causes of DCP in Portugal are
identified. Then the hierarchical structure of the causes of DCP is determined, using integrated Interpretive
Structural Modelling (ISM), and an ISM-based Model is developed. The results show that the 16 causes of
DCP taken into consideration are hierarchized in six different influence levels. The causes Bidding and
contract award process and Lack of communication between parties are the most influential causes, and are
thus considered to be the root causes of DCP in Portugal. Additionally, the results show that the causes of
DCP can be divided into four different categories relating to Relationships and contract, Material, the
Developer, and the Contractor. Finally, these results provide fundamental insights for practitioners and
researchers to develop effective measures to mitigate the causes of DCP.
1 INTRODUCTION
Regardless of the type of construction project, delays
are a global problem. A delay in construction is an
overrun either past the date the contract parties agree
upon to deliver a project or past the conclusion date
stated in the contract. A project must be finished on
time and meet the cost and quality requirements.
Accordingly, the timely completion of a project is
regarded as a significant parameter for measuring a
project’s success. Projects are prolonged or hastened
to overcome delays, incurring unavoidable additional
costs (Oyegoke & Al Kiyumi, 2017). The complexity
of construction projects often makes it difficult to
identify the causes of delays, which are frequently
interrelated.
The Portuguese construction industry is no
exception here, and delays are a disturbance for a
significant number of construction projects.
Accordingly, Portuguese construction companies
a
https://orcid.org/0000-0003-1207-5854
b
https://orcid.org/0000-0003-0459-0020
must be alert to and comprehend the origins of delays.
Such delays can be the cause of late conclusion of
projects, reduced productivity, augmented costs, and
even termination of the contract, all of which
contribute to construction companies’ ability to
compete.
There has already been several studies on this
issue in the literature. However, depending on the
context, the origins of delays may differ. For
example, they may be due to differences in culture,
environment, construction methods, management
system, geography, organizations involved, public
policies, economic context, availability of resources,
and the political climate (Zidane & Andersen, 2018).
Additionally, for the most part, the existing studies
focus on determining and ranking the causes of delay
in construction projects and proposing some
mitigation measures, in doing so, failing to
understand the interrelationships. The main objective
of this study is, therefore, to hierarchize the causes of
366
Arantes, A. and Ferreira, L.
Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case.
DOI: 10.5220/0010315303660374
In Proceedings of the 10th International Conference on Operations Research and Enterpr ise Systems (ICORES 2021), pages 366-374
ISBN: 978-989-758-485-5
Copyright
c
2021 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
delays in construction projects according to levels of
influence and determine their root causes in the
Portuguese context, with a view to improving
construction project management.
This research project is structured as follows: first,
a review of the literature on the causes of delays in
construction projects is carried out; second, the
research methods are presented; in the third section,
the results are presented and analyzed; and fourth, and
lastly, the conclusions and implications are drawn.
2 LITERATURE REVIEW
Given that the construction project process is a very
complex one, incorporating the various stakeholders
priorities and concerns, covering numerous works,
and requiring a long period to conclude, the causes of
delays are multiple. Several researchers have studied
the causes of delays in construction projects. Odeh
and Battaineh (2002) concluded that the main causes
of delays were inexperienced contractors, owner
interference, delays in progress payments by the
developer, slow decision-making by the developer,
unsuitable planning, the low productivity level of the
labor force, and difficulties with subcontractors.
A study carried out by Assaf and Al-Hejji (2006)
showed that, in Saudi Arabia, contractors
acknowledged that the leading causes of delays had
to do with the developer, and developers and
consultants considered that the highest recurrent
cause of delay is the awarding of the contract to the
lowest bidder. However, they all agreed that the
developer changing orders during the construction
phase is a fundamental cause of delay.
Fallahnejad (2013) studied the causes of delays in
construction in Iran and concluded that the main
causes were: incapacity of the contractors to deliver
imported materials, questionable contract timelines
imposed by the developer, slow provision of
materials by the developer, time-consuming land
expropriation due to resistance from occupants and
changes to orders by the developer. For future
research, the author acknowledged the necessity to
define the root causes of delays and then develop
mitigation measures accordingly.
Ruqaishi and Bashir (2015) determined that the
main causes of construction project delays in the oil
industry in Oman were: reduced site management by
the contractor, difficulties with subcontractors, poor
scheduling and planning by contractors, delays in the
provision of materials, absence of proper
communication between project stakeholders and
little collaboration with vendors during the stages of
engineering and procurement.
Oyegoke and Al Kiyumi (2017) studied the
causes of delays and their effects on projects in
Oman. They found that the primary causes were:
selecting the lowest bid, the main contractor’s poor
financial situation, slow decision-making by the
developer, and inappropriate construction planning
by the contractor. As far as the major effects of the
delays are concerned, the authors pointed to
additional costs and project delays.
Zidane and Andersen (2018) researched the top
ten universal causes of delay in construction projects.
They compiled multiple studies conducted in
different countries on the causes and used a global
ranking index to select the “top ten universal delay
causes” from the top ten delay causes for 46
individual countries. The top ten universal delay
causes are changes to orders, late payments to the
contractor, weak planning and scheduling, poor site
management and control, poor design, inadequate
contractor experience and building processes,
contractor financial problems, developer financial
difficulties, resource rupture, and low labor
productivity and lack of skills.
More recently, Arantes and Ferreira (2020)
identified the causes and the main underlying causes
of delays in construction projects in Portugal. Six out
of the ten most important causes of delays are also in
the top ten universal delays (Zidane & Andersen,
2018). Factor analysis revealed six underlying
causes: improper planning, poor consultant
performance, inefficient site management, developer
influence, bureaucracy, and sub-standard contracts.
Based on the literature, the leading causes of
delays in construction projects reveal some variation
in accordance with the type of project and the
context/geography in which the project is carried out;
this is aligned with the opinion of other authors (Lind
& Brunes, 2015; Sambasivan & Soon, 2007; Sanni-
Anibire et al., 2020). While there is a certain degree
of consensus on the more significant causes of
delays, these authors did find different, although
related, sets of causes and present slightly different
rankings for the importance of causes. However,
some emerge as the most important causes (Zidane
& Andersen, 2018). Moreover, to the best knowledge
of the authors of this work, no studies consider the
root causes of the delays based on the
interrelationships between them.
The work presented here looks at the Portuguese
context and emphasizes owners, consultants, and
contractors in the construction industry. It intends to
contribute to project management by hierarchizing
Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case
367
the causes of delays in construction projects by
influencing factors, determining their root causes in
the Portuguese context.
3 RESEARCH METHOD
The present work adopted the two-phase
methodology presented in Figure 1. In the first phase,
the causes of Delays in Construction Projects (DCP)
in the Portuguese context are identified. And in the
second phase, it is established the hierarchical
structure of the causes of DCP using the ISM
methodology.
Figure 1: Methodology framework.
In phase I, a literature review is carried out on the
causes of DCP in order to identify the leading causes
of DCP in Portugal, as the focus group meeting
experts belong to Portuguese construction
companies.
In phase II, the ISM technique is used to identify
and evaluate the interrelationships between the
causes of DCP in Portugal, presenting a structural
map of the causes and the interconnections between
them, and highlighting the critical causes impelling
the generation of DCP.
The ISM methodology evaluates if and how the
multifaceted problem variables are linked, based on
the judgment of experts (Gan et al., 2018). These
judgments allow for the hierarchization of the
interrelationships between the variables, and the
translation of unclear mental models into visible and
well-defined systems.
In the literature there are three Multi-Criteria
Decision-Making (MCDM) techniques to develop
structural hierarchies: DEMATEL, Fuzzy Cognition
Map (FCM), and ISM. However, FCM and
DEMATEL have clear limitations in comparison to
the ISM methodology.
DEMATEL defines the ranking of alternatives
based on their dependency but does not take into
consideration all criteria, and the relative weights of
experts are not aggregated to personal decisions of
experts within the group assessments (Malek &
Desai, 2019). Moreover, FCM requires hard
optimization of all the membership functions’
parameters and, sometimes, converges towards an
undesired steady state. ISM overcomes these
constraints; it classifies the multifaceted problem in
various groups, which individually represent one
segment of the problem. This is obtained through the
practical experience and knowledge of the
specialists. ISM provides insight into the
interrelationships among different variables and
assists in understanding the hierarchical way those
variables are established, thus determining the order
and direction of the multifaceted relationships among
the variables of the complex system (Xu & Zou,
2020). These characteristics make ISM the most
frequently used method in the literature and a secure
approach for developing the hierarchy structural
model (Malek & Desai, 2019). Furthermore, ISM can
capture dynamic complexities, while other MCDM
methodologies have difficulty representing real-life
multifaceted problems and capturing dynamic
behaviors (Shahabadkar et al., 2012).
ISM has been recently adopted in several studies
related to the construction Industry. For example,
Alzebdeh et al. (2015) examined ISM as a practical
technique for modeling multifaceted
interrelationships between factors in cost overruns in
ICORES 2021 - 10th International Conference on Operations Research and Enterprise Systems
368
construction projects in the Sultanate of Oman. They
verified that the application of ISM makes it possible
to organize these factors in a hierarchical structure,
demonstrating their interrelationships. Four factors
were established as the root causes of cost overruns:
instability of the US dollar, changes in governmental
regulations, incorrect cost estimation, and weak
coordination among parties involved in projects.
Gan et al. (2018) realized that few studies
endeavored to investigate the complex
interrelationships among barriers to the transition
towards off-site construction in China.
Consequently, they adopted the ISM technique to
explore said interrelationships. The results show that
attention should be paid to inadequate policy and
regulations, lacking knowledge and expertise,
dominated traditional project process, and low
standardization. In particular, the findings provide
valuable information for policymakers on the overall
structure between barriers.
Sarhan et al. (2019) proposed a framework for
implementing lean construction strategies using the
ISM technique to improve performance levels in the
construction industry in Saudi Arabia. They
concluded that the framework constitutes
considerable progress over existing frameworks, as it
specifies the hierarchical relationships among the
different factors that contribute to the successful
implementation of lean construction, reflecting the
socio-cultural and operational contexts in the Saudi
Arabia construction industry. Therefore, based on the
above arguments, ISM was the chosen technique for
this research project.
The works of Shen et al. (2016) and Gan et al.
(2018) served as guide in the implementation of ISM.
In accordance with the aforementioned works, the
steps to develop ISM are as follows: (i) identification
and listing of the variables that comprise the system
to be studied; (ii) identification of the contextual
interrelationships by experts between each pair of
variables and registering them in a Structural Self-
Interaction Matrix (SSIM); (iii) translation of the
SSIM into an Initial Reachability Matrix (IRM),
which is a binary matrix representing the direct
interrelationships among the variables; (iv) checking
IRM for transitivity to also capture the indirect links
between variables, which will be transformed into the
Final Reachability Matrix (FRM), which considers
all the interrelationships (direct and indirect) among
the variables; (v) applying level partitioning to the
FRM, ranking the elements according to their levels;
(vi) drawing the ISM-based model by connecting the
variables at each level, based on their IRM
relationships; and lastly, (vii) presenting the ISM-
based model to experts to establish its consistency.
A Focus Group Meeting (FGM) was conducted
to implement the ISM. An FGM is defined as a
primary research technique that collects data through
group interaction on a subject set by the moderator
(Morgan et al., 1996). This qualitative research
approach provided detailed knowledge of a
phenomenon experienced by the FGM participants.
Care was taken to select experts with a view to
avoiding any bias within the group; the set of experts
was made up of two practitioners from each entity,
namely developers, consultants, and contractors. All
participants had more than ten years’ experience.
Furthermore, in the FGM, all experts had equal
weighting in the decision-making process, and their
opinions were only considered when the majority
were in agreement, as suggested by Shen et al.
(2016), in order to ensure consensus. The FGM was
moderated by one of the authors of this paper.
Particular attention was paid to the moderator’s role.
The moderator was well knowledgeable on
construction project management, and the discussion
advanced from the general to specific issues with a
view to stimulating sincerity and reducing bias
(Prince & Davies, 2001).
After implementing the ISM methodology, we
forwarded the hierarchical structure to the experts.
Later, ad hoc contacts were made with some of the
experts to ensure consistency of the results.
4 RESULTS AND DISCUSSION
4.1 Causes of DCP in Portugal
(Phase I)
A literature review was carried out to find and review
relevant literature on the causes of DCP in general,
and in Portugal in particular. The literature review
was also useful for defining descriptions for each
cause, which was central to guiding the FGM with the
experts. We selected the causes of DCP presented in
Arantes and Ferreira (2020), who analyzed the
Portuguese case. Of the 46 causes they studied, only
the 16 most important ones were selected for this
study. The selection criterion was having a median
value of the importance of the cause higher than the
threshold value of 4. The main causes are presented
in Table 1.
Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case
369
Table 1: Causes of DCP in Portugal.
No. Cause of DCP
C1 Slow decision making by the developer
C2 Change in orders
C3 Unrealistic schedule and specifications in the
contract
C4 Improper planning and scheduling
C5 Bidding and contract award process
C6 Delay in progress payments by the owner
C7 Delay in quality control
C8 Developer interference
C9 Increase in scope of work
C10 Mistakes and discrepancies in drawings
C11 Delay in obtaining permits from authorities
C12 Delay in the procurement of materials
C13 Changes in material specifications during
construction
C14 Delay in delivery of materials
C15 Disputes and negotiations between parties
C16 Lack of communication between parties
4.2 ISM Methodology (Phase II)
In the FGM, the experts were asked to make pair-wise
comparisons of the 16 causes of DCP in Portugal by
responding to the question, “Does cause i directly
influence cause j?” Four letters were used to represent
the direction of the interrelationship between each
pair of causes. “V” means that cause “i” influences
directly cause “j”; “A” means that cause “j”
influences directly cause I”; “X” means that causes
“i” and “j” influence each other; and “O” means that
there is no interrelationship between causes “i” and
“j”. However, different experts may judge the pair-
wise comparison of two causes differently.
Accordingly, when consensus was not reached in this
study, the interrelationships among the causes were
settled by the rule, “the minority gives way to the
majority” (Shen et al. (2016). The interrelationships
among the causes of DCP in the Portuguese context
are presented in the Structural Self-Interaction Matrix
(SSIM) (Table 2).
Next, the SSIM is transformed into the Initial
Reachability Matrix (IRM) by substituting “V”, “A”,
“X” and “O” in accordance with the following rules:
(i) if the (i, j) entry isV, then the (i, j) entry in the
IRM becomes “1” and the (j, i) entry becomes “0”;
(ii) if the (i, j) entry is “A”, then the (i, j) entry in the
IRM becomes “0” and the (j, i) entry becomes “1”;
(iii) if the (i, j) entry is “X”, then the (i, j) and (j, i)
entries in the IRM become1; and, (iv) if the (i, j)
entry is “O”, then the (i, j) and (j, i) entries in the IRM
become “0”. Finally, the IRM was then checked for
transitivity. Transitivity means that if cause “i” is
directly related to causej and causej is directly
related to cause “k”, then causes “i” and “k” are
indirectly related through cause j, and if the entry (i,
k) in the IRM is “0”, then it must be changed to a
“1*”. This process converts the IRM into the FRM
(see Table 3), which considers all interrelationships
among the causes (direct and indirect). Table 3 also
presents each cause’s driving and dependence
powers, which are the sum of the rows and columns
of the FRM, respectively.
Table 2: Structural Self-Interaction Matrix.
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16
C1
V O O O V V X A A V V A V V O
C2
O O O O V X X V V V V V V O
C3
A A V V V O O O V V V V O
C4
O V V A A A O V O A V O
C5
O O O O V O O O O V O
C6
A A A O O V O O V A
C7
A A A O O A A V O
C8
V V V V V O V O
C9
V V V V O V O
C10
V V A O V A
C11
V O O V A
C12
X O O A
C13
X V A
C14
V O
C15
A
C16
ICORES 2021 - 10th International Conference on Operations Research and Enterprise Systems
370
Table 3: Final reachability matrix.
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16
C1 1 1 0 1* 0 1 1 1 1* 1* 1 1 1* 1 1 0
C2 1* 1 0 1* 0 1* 1 1 1 1 1 1 1 1 1 0
C3 1* 1* 1 1* 0 1 1 1 1* 1* 1* 1 1 1 1 0
C4 1* 1* 1 1 0 1 1 1* 1* 1* 1* 1 1* 1* 1 0
C5 1* 1* 1 1* 1 1* 1* 1* 1* 1 1* 1* 1* 1* 1 0
C6 1* 0 0 1* 0 1 1* 0 0 1* 0 1 1* 1* 1 0
C7 1* 0 0 1* 0 1 1 0 0 1* 1* 1* 1* 1* 1 0
C8 1 1 1* 1 0 1 1 1 1 1 1 1 1 1* 1 0
C9 1 1 1* 1 0 1 1 1* 1 1 1 1 1 1* 1 0
C10 1 1* 1* 1 0 1* 1 1* 1* 1 1 1 1* 1* 1 0
C11 1* 0 0 1* 0 0 1* 0 0 1* 1 1 1* 1* 1 0
C12 1* 0 0 1* 0 0 1* 0 0 1* 0 1 1 1* 1* 0
C13 1 1* 1* 1* 0 1* 1 1* 1* 1 1* 1 1 1 1 0
C14 1* 1* 1* 1 0 1* 1 1* 1* 1* 1* 1* 1 1 1 0
C15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0
C16 1* 1* 1* 1* 0 1 1* 1* 1* 1 1 1 1 1* 1 1
Table 4: Level partitioning results.
Causes Reachability Set Antecedent Set Intersection Set Level
C1 1, 2, 4, 6, 7, 8, 9, 10, 11, 12, 13,
14
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 2, 4, 6, 7, 8, 9, 10, 11, 12, 13, 14 2
C2 2, 8, 9 2, 3, 5, 8, 9, 16 2, 8, 9 4
C3 3 3, 5, 16 3 5
C4 1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12,
13, 14
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12, 13,
14
2
C5 5 5 5 6
C6 6 2, 3, 5, 6, 8, 9, 16 6 3
C7 1, 4, 6, 7, 10, 11, 12, 13, 14 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 4, 6, 7, 10, 11, 12, 13, 14 2
C8 2, 3, 8, 9 2, 3, 5, 8, 9, 16 2, 3, 8, 9 4
C9 2, 3, 8, 9 2, 3, 5, 8, 9, 16 2, 3, 8, 9 4
C10 1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12,
13, 14
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12, 13,
14
2
C11 11 2, 3, 5, 8, 9, 11, 16 11 3
C12 1, 4, 7, 10, 12, 13, 14 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 4, 7, 10, 12, 13, 14 2
C13 1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12,
13, 14
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12, 13,
14
2
C14 1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12,
13, 14
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 16
1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 12, 13,
14
2
C15 15 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 15, 16
15 1
C16 16 16 16 6
After the FRM, level partitioning was carried out.
For each cause of DCP, the reachability set, the
antecedent set, and the intersection set were created
to measure each cause’s influence levels. The
reachability set of cause “i” comprises all causes that
are influenced by cause “i" (which are represented by
“1s” in the row of the FRM corresponding to cause
“i"); the antecedent set of cause “i“ comprises all
causes that influence cause “i" (which are
represented by “1s” in the column of the FRM
corresponding to cause “i”); plus, the intersection set
contains the common causes found in both the
reachability and antecedent sets. When the
intersection set is equal to the reachability set of a
Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case
371
particular cause, then that cause is allocated to the
level of that iteration. The causes assigned to one
level are then detached from the remaining
reachability and intersection sets for the next
iteration. The same process is applied until all the
causes are partitioned into levels. Table 4 shows the
level partitioning results of the 16 causes of DCP. All
causes were partitioned into levels after six iterations,
meaning now the ISM-based model can be
represented.
Finally, a digraph is drawn up by positioning the
causes vertically according to the level partitioning
(Table 3) and linking the causes according to the IRM
using arrows. The ISM-based model (Figure 2) shows
the hierarchical structure of the causes of DCP in
Portugal, emphasizing their interrelationships.
Figure 2 shows six different levels of influence.
The first level of the ISM-based model is comprised
of the cause Disputes and negotiations between
parties (C15).
The second level directly influences the first level.
It is comprised of the Slow decision making by the
developer (C1), Improper planning and scheduling
(C4), Delay in quality control (C7), Mistakes and
discrepancies in drawings (C10), Delay in the
procurement of materials (C12), Changes in material
specifications during construction (C13) and Changes
in material specifications during construction (C14).
The third level directly influences the second level
and comprises Delay in progress payments by the
owner (C6) and Delay in obtaining permits from
authorities (C11).
Figure 2: The ISM-based model of the causes of DCP in Portugal.
ICORES 2021 - 10th International Conference on Operations Research and Enterprise Systems
372
The fourth level of the ISM-based model directly
influences the third level and includes Developer
interference (C8), Change in orders (C2), and
Increase in scope of work (C9). The fifth level
contains Unrealistic schedule and specifications in
the contract (C3) and directly influences the fourth
level. Lastly, the sixth and final level of the ISM-
based model directly influences the fifth and the third
levels and has the most influence over the other
causes considered, comprising Bidding and contract
award process (C5) and Lack of communication
between parties (C16).
From the assessment of the ISM-based model, see
Figure 2, it became clear that the causes of DCP can
be divided into Relationships and contract-related
causes (C3, C5, C15, and C16), Material causes (C12,
C13, and C14), Developer-related causes (C1, C2,
C6, C8, and C9) and Contractor-related causes (C4
and C7).
4.3 Discussion
The six levels of causes of DCP presented in the ISM-
based model in Figure 2 make it possible to
understand their impact on DCP in the Portuguese
context. According to the ISM technique, measures
that lessen the causes originating at a higher level will
also help lessen the causes originating at a lower
level. However, corrective measures taken at lower
levels will have little to no effect at higher levels.
Therefore, stakeholders and practitioners from the
Portuguese construction industry must pay particular
care to the causes originating at level six when
developing mitigation measures to DCP, given that
said measures will mitigate those causes and also the
causes from other lower levels.
As a result, based on the ISM-based model
developed in this work, the causes of DCP that make
up the sixth level of the ISM-based model
i.e.,
Bidding and contract award process (C5), and Lack
of communication between parties (C16) are
considered to be most influential causes of DCP.
These causes have already been indicated as
important to DCP by other authors (Arantes &
Ferreira, 2020; Assaf & Al-Hejji, 2006; Fallahnejad,
2013; Ruqaishi & Bashir, 2015), and, as such, special
mitigation measures should be foreseen. This result
supports the consistency and value of the model
developed.
5 CONCLUSIONS
In this study, the interrelationships between 16 causes
of DCP in Portugal were modeled. The ISM
methodology was applied to structure the selected
causes into a hierarchy and divide them into six
different influence levels. Two root causes of DCP
were identified: Bidding and contract award process
and Lack of communication between parties. This
study also reveals how the causes of DCP affect each
other and provides guidelines for researchers and
practitioners to develop effective measures to
mitigate the causes of DCP. Moreover, the results
show that the causes of DCP are essentially of four
different types that can be related to Relationships
and contract, Material, the Developer, and the
Contractor.
Even though this paper contributes to the
discussion on the causes of DCP in Portugal, namely
the interrelationships between them, it also has
certain limitations. Firstly, the results are dependent
on the opinions of a small number of experts; and,
secondly, the results may not be generalizable to other
contexts. However, these limitations also constitute
future research opportunities.
REFERENCES
Alzebdeh, K., Bashir, H. A., & Al Siyabi, S. K. (2015).
Applying interpretive structural modeling to cost
overruns in construction projects in the sultanate of
Oman. Journal of Engineering Research, 12(1), 53–68.
Arantes, A., & Ferreira, L. M. D. F. (2020). Underlying
causes and mitigation measures of delays in
construction projects An empirical study. Journal of
Financial Management of Property and Construction.
https://doi.org/10.1108/JFMPC-03-2019-0029
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large
construction projects. International Journal of Project
Management, 24(4), 349–357.
https://doi.org/10.1016/j.ijproman.2005.11.010
Fallahnejad, M. H. (2013). Delay causes in Iran gas pipeline
projects. International Journal of Project Management,
31(1), 136–146.
https://doi.org/10.1016/j.ijproman.2012.06.003
Gan, X., Chang, R., Zuo, J., Wen, T., & Zillante, G. (2018).
Barriers to the transition towards off-site construction
in China: An Interpretive structural modeling approach.
Journal of Cleaner Production, 197, 8–18.
https://doi.org/10.1016/j.jclepro.2018.06.184
Lind, H., & Brunes, F. (2015). Explaining cost overruns in
infrastructural projects: A new framework with
applications to Sweden. Construction Management and
Economics ISSN:, 33(7), 554–568.
https://doi.org/10.1080/01446193.2015.1064983
Malek, J., & Desai, T. (2019). Interpretive structural
modelling based analysis of sustainable manufacturing
enablers. Journal of Cleaner Production, 238(117993).
https://doi.org/10.1016/j.jclepro.2019.117996
Morgan, D., Powell, R. a, & Single, H. M. (1996). Focus
Groups. International Journal for Quality in Health
Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case
373
Care, 8(5), 499–504.
https://doi.org/10.1093/intqhc/8.5.499
Odeh, M., & Battaineh, H. T. (2002). Causes of
construction delay: Traditional contracts. International
Journal of Project Management, 20(1), 67–73.
https://doi.org/10.1016/S0263-7863(00)00037-5
Oyegoke, A. S., & Al Kiyumi, N. (2017). The causes,
impacts and mitigations of delay in megaprojects in the
sultanate of Oman. Journal of Financial Management
of Property and Construction, 22(3), 286–302.
https://doi.org/10.1108/JFMPC-11-2016-0052
Prince, M., & Davies, M. (2001). Moderator teams: an
extension to focus group methodology. Qualitative
Market Research, 4(4), 207–216.
https://doi.org/10.1108/EUM0000000005902
Ruqaishi, M., & Bashir, H. A. (2015). Causes of Delay in
Construction Projects in the Oil and Gas Industry in the
Gulf Cooperation Council Countries: A Case Study.
Journal of Management in Engineering, 31(3),
05014017. https://doi.org/10.1061/(ASCE)ME.1943-
5479.0000248
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects
of delays in Malaysian construction industry.
International Journal of Project Management, 25(5),
517–526.
https://doi.org/10.1016/j.ijproman.2006.11.007
Sanni-Anibire, M. O., Zin, R. M., & Olatunji, S. O. (2020).
Causes of delay in the global construction industry: a
meta analytical review. International Journal of
Construction Management.
https://doi.org/10.1080/15623599.2020.1716132
Sarhan, J. G., Xia, B., Fawzia, S., Karim, A., Olanipekun,
A. O., & Coffey, V. (2019). Framework for the
implementation of lean construction strategies using the
interpretive structural modelling (ISM) technique: A
case of the Saudi construction industry. Engineering,
Construction and Architectural Management, 27(1), 1–
23. https://doi.org/10.1108/ECAM-03-2018-0136
Shahabadkar, P., Hebbal, S. S., & Prashant, S. (2012).
Deployment of Interpretive Structural Modeling
Methodology in Supply Chain Management An
Overview. International Journal of Industrial
Engineering & Production Research, 23(3), 195–205.
Shen, L., Song, X., Wu, Y., Liao, S., & Zhang, X. (2016).
Interpretive Structural Modeling based factor analysis
on the implementation of Emission Trading System in
the Chinese building sector. Journal of Cleaner
Production, 127, 214–227.
Xu, X., & Zou, P. X. W. (2020). Analysis of factors and
their hierarchical relationships influencing building
energy performance using interpretive structural
modelling (ISM) approach. Journal of Cleaner
Production, 272
(122650).
https://doi.org/https://doi.org/10.1016/j.jclepro.2020.1
22650
Zidane, Y. J. T., & Andersen, B. (2018). The top 10
universal delay factors in construction projects.
International Journal of Managing Projects in
Business, 11(3), 650–672.
https://doi.org/10.1108/IJMPB-05-2017-0052.
ICORES 2021 - 10th International Conference on Operations Research and Enterprise Systems
374