the increase of project scale, flood risk caused by
rainstorm, etc.
(2) Operation problems of lift pumping station
The water lifting system consists of 13-level 22
hubs as 34 pumping stations set up along the way
with a total lift of 65 m. With a total installed
capacity of 160 pumps, the total installed flow is
4,447.6 m
3
/s and the installed power is 366,000 kW.
It is a modern pumping station group with the largest
number of large pumping stations in Asia and even
in the world. 13 cascaded pumping stations are
distributed along the river section to the south of the
Yellow River. For the north of the Yellow River
water can be transferred by gravity (Liu et al., 2020).
The pumping stations of the East Route project
are mainly characterized by low lift, large flow and
long operation time. Some pumping stations also
have waterlogging drainage tasks. Therefore, the
pumping stations are required to be flexible, efficient
and reliable. Affected by the operating conditions,
equipment quality and technical conditions, the water
lifting efficiency of the pumping station is reduced,
and the water lifting capacity cannot meet the
planning requirements
(Liu & Geng, 2010). The East
Route project partially uses the completed River
Water to North Diversion Project in Jiangsu
Province. The latter has operated for nearly 40 years,
so the pumping station is partially aging and the
motor power is partially attenuated, affecting the
water lifting efficiency; 3 stations in Huai'an should
be overhauled every year and before the flood
season, otherwise the water lifting efficiency will be
affected due to the change of working point of the
pumping station. Secondly, because some pumping
stations have flood control functions to ensure
normal operation in flood season, flood overtopping
has become one of the risks threatening the safety of
the pumping station project.
(3) Operation safety of water conveyance channel
The water conveyance channel is located in the
south of Dongping River, and the double line water
conveyance is mainly composed of the Canal Route
and Yunxi Route as auxiliary. After the two routes
meet at Nansi Lake, they enter Dongping Lake
through Liangji canal. After leaving Dongping Lake,
it is divided into two routes, one through the Yellow
River and the small canal to Datun reservoir in
Dezhou and the other route connected to the channel
from the Yellow River to Qingdao through Jiaodong
water diversion main route to supply water to
Jiaodong area.
Some water delivery channels undertake the
tasks of water supply, flood control and shipping and
always maintain high water level operation.
Therefore, high water level operation and floods are
the main problems faced by the water delivery
channel of the East Route project, which is
manifested in the failure of the safety and stability of
the river embankment. Its planned water delivery
function have not been achieved, thus affecting the
function of the water delivery channel. In addition,
90 km of the canal line of the East Route project
passes through the Tanlu fault zone near Zaohe-
Suqian-Luoma Lake in Northern Jiangsu
(Geng et
al., 2012), which may be affected by earthquakes
and other geological disasters.
(4) Operation safety of impoundment lake
system
The water storage system mainly refers to four
natural lakes along the water diversion route,
including Hongze Lake, Luoma Lake, Nansi Lake
and Dongping Lake. Before the water supply of the
East Route of the South-to-North Water Diversion
Project, the operation of the water storage system
can be mainly divided into flood season and non-
flood season; after the water was supplied, it is
mainly the flood season and the water diversion
period. The impoundment lakes have encountered
high water level for a long time and some
embankments, especially those in Xuzhou,
Zaozhuang, Jining and other coal mining subsidence
areas near Nansi Lake, may cause subsidence due to
the increased load.
4.2 Safety Problems of Water Quality
The first phase of the East Route project uses the
existing regulation and storage lakes and canals to
deliver water, undertaking the functions of shipping,
flood control, waterlogging drainage, aquaculture
etc. Under normal working conditions, the water
quality of the water diversion main route has
basically met the water diversion requirements.
However, once problems in the working conditions
of the pollution control and water quality assurance
system, such as the sudden increase of pollution load
input or the operation failure of the pollution control
project happen, it will result in sudden water
pollution accidents and the water quality of the East
Route may be threatened. According to the survey,
the natural risk source of the water quality of the
first phase of the East Route project is flooding in
Nansi Lake basin. If the first major flood in the four
lakes in Central and South China occurs in advance
during the operation and coincides with the water
diversion period with the rubber dam at each estuary
collapsing and discharging, the polluted water in the
river will be discharged together with the large flow