Application of Project Management Tools in the Enterprise
Jiongjie Liu
1,a,*,†
, He Sun
2,b,*,†
and Shizhuo Sun
3,c,*,†
1
School of Electrical and Electronic Engineering, Huazhong University of Science and Technology,
Wuhan, Hubei, 430070, China
2
School of Economic and Management, Tiangong University, Tianjin, 300000, China
3
School of Mechanical Engineering, Nanjing Institute of Technology, Nanjing, Jiangsu, 213000, China
These authors contributed equally
Keywords: Project Management, Project Progress Management Method, Critical Path Method, Plan Evaluation and
Review Technology, Time-cost Trade-off.
Abstract: To ensure the successful implementation of the project and the orderly progress of the project progress for
more economic benefits, companies need to invest in resources, time, and other costs and join the scientific
and technical guidance of the project progress management system theory. This paper focuses on the basic
knowledge and related project management theories, with the critical path method, PERT and Time-cost trade
as the tools. It systematically discusses how to forecast and control the project duration through project
schedule management methods and supports achieving refined project management. Also, the tools in this
thesis apply to the project management practices of enterprises in various fields.
1 INTRODUCTION
1.1 Project Management Research
Background
With the development of the knowledge economy,
the world's economy is changing from high growth to
high-quality development, which requires enterprises
to further develop and implement a more professional
project management process. Scholars generally
believe that a project refers to using limited resources
and time to achieve specific goals for specific users
according to a specific life cycle. Project
management is the overall monitoring and
management of activities related to realising a series
of objectives (Liu 2020). Project management uses
expertise, skills, tools and methods to plan, organize,
implement and control project activities. The main
challenge is the need to accomplish all project
objectives within the established constraints. These
constraints include project scope, completion time,
quality, and budget (Tan 2019). Project progress
management is the process of using the relevant
theoretical knowledge of the project risk
management, formulating the corresponding plans
for the different stages and combining with the
enterprise resources, and determining the
corresponding objectives to monitor the progress
project's objectives can be summarized into three
aspects: progress, cost and quality, which jointly
drive the project management process. Among them,
the management of progress objectives is usually
regarded as the priority objective in the process of
project implementation, and the management of cost
and quality objectives is often carried out based on
the progress management system, such as earned
value management and the determination of quality
control points (Tan 2019).
At present, China's economy is in a critical period
of transformation from high growth to high-quality
development. Therefore, it is more necessary for
enterprises to further explore and practice a more
professional project management process.
To conclude, project management can be seen as
a way to deal with the strategy of the organization, a
means of survival and development in the changing
and relentless market competition, and it should be
more widely used. The realization of project
management and the development of project
management cannot be separated from the
modernization of management ideas, management
organizations, management methods and means,
which is the inevitable trend of project management
development. Facing the rapidly changing market
Liu, J., Sun, H. and Sun, S.
Application of Project Management Tools in the Enterprise.
DOI: 10.5220/0011301900003437
In Proceedings of the 1st International Conference on Public Management and Big Data Analysis (PMBDA 2021), pages 101-112
ISBN: 978-989-758-589-0
Copyright
c
2022 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
101
and the fierce competition among enterprises, our
only choice is to innovate and grasp the pulse of
management.
1.2 Current Status of Project
Management Research
There are many methods for risk analysis of
engineering project progress. Still, the PERT (Plan
Evaluation and Review Technology) based on
CPM(Critical Path Method) Network technology is
the most common use with the fastest development.
From the original classic PERT network program to
various improvements to the PERT approach today,
the researchers remain unenthusiastic and applied to
various engineering fields (Wu 2016). Network
Planning Technology was introduced in the early
1960s by the famous mathematician Professor Hua
Luogeng. In his book "Coordinating Method
Translation and Supplement" (Hua 1965), PERT
technology is introduced and dedicated to promoting
PERT technology.
In 1981, Project Management Institute(PMI)
launched the "Project Management Standardization"
study, named PMBOKProject Management Body
of Knowledge, and registered and published 15
years later. The Chinese Project Management Body
of Knowledge (CPMBOK) is based on PMBOK (Ma
2013) and consists of 38 processes. However, the
current situation of many project management
knowledge systems also shows that project
management is still a young discipline and is still
developing and improving (Yin 2003).
Munns A K & Bjeirmi B F identify the overlap
between the project and project management
definition and discuss how the confusion between the
two may affect their relationship. It identifies the
different individuals involved in the project and
project management and their objectives,
expectations, and influences. It demonstrates how a
better appreciation of the distinction between the two
will increase project success (Munns, Bjeirmi 1996).
In "A Study on Project Cost Management System
Based on Project Management Theory", Bi Xing
pointed out that project management is different from
general business management, with its unique
characteristics: activity-oriented, non-repetitive,
complex implementation and life-cycle risks, thus
making project management more challenging. In
addition, the definition and meaning of project cost
management are explained (Bi 2007).
Zhou Yongjun, in "Research on the Current
Situation and Development of Project Management",
studies the development history of project
management in China, points out the characteristics
of engineering project management in China and
makes suggestions for its scientific development
(Zhou 2006).
In "Discussion on the use of modern project
management theory in engineering management",
Yang Guang proposes improvement methods for
modern project management in the project
management process to reduce costs (Yang 2021).
1.3 Thesis Organization
In this paper, we analyze a new product design and
market launch project for a domestic company that
plans to design and develop a new model of product
and needs to move forward with the project as soon
as possible to capture the current market share, win
in the market and make a profit.
Based on the initial data, this thesis plans to
analyze the project duration and optimize it using the
CPM (Critical Path Method), PERT (Plan Evaluation
and Review Technology) and TT (Time-cost Trade-
off) methods. In the first part of the thesis, project
management research's background and current
status are synthesized, the second part analyses each
of the three methods used in project management, and
the third part discusses the results. The fourth part
concludes and explores the general applicability of
the findings.
2 METHOD
The thesis intends to use a research method
combining theoretical deduction, case induction
method and quantitative analysis method to analyze
theoretical analysis through literature collection and
collation, to analyze the current situation of domestic
and foreign research, to collect domestic and foreign
research results on project duration risk evaluation
and dynamic control, and to explore the theoretical
application of engineering project duration risk
management, especially engineering project duration
risk evaluation and dynamic control. Identify the
influencing factors of project duration risk, and then
complete the research on project duration risk
evaluation and dynamic control by combining with
actual engineering projects. The specific technical
route is as follows.
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
102
Figure 1: Method Roadmap.
2.1 Data
The case data of this thesis is provided by the project
department of a domestic manufacturing company,
and the private information of the company involved
has been blurred to protect the company data. At
present, the company plans to launch a new product.
The project manager gives a description of the
project, the activities and their time give estimates as
shown in table 1, from which a network diagram can
be drawn to find the critical path.
Table 1: Project Schedule Worksheet.
ACTIVITY
Required
Time/Weeks
Immediate
Predecessors
Slack Time
/Weeks
A Research and Manufacturing
A1 Project Launch Phase 2 None 1
A2 R&D Design 5 A1, B1 0
A3 Material Information Integration 5 A2 3
A4 Equipment Purchase 6 A3, B6 0
A5 Layout of equipment 4 A4 0
A6 Order external parts 1 B10 0
A7 Assembly and production 5 A6 0
A8 Produce products 7 A7 0
B Marketing
B1 Market Positioning 3 None 0
B2 Product introduction information 10 B1 3
B3 Product property protection 10 B2 3
B4 Identify promotional vendors 3 B1 2
B5 Trial Promotion 4 A2,B4 0
B6 Review & Decision Making 4 B5 0
B7 Price Analysis 7 None 15
B8 Define market strategy 4 B7,C3,C4 3
B9 Run test market 8 A5,B3.B8 0
Application of Project Management Tools in the Enterprise
103
Table 1: Project Schedule Worksheet (cont.).
ACTIVITY
Required
Time/Weeks
Immediate
Predecessors
Slack Time
/Weeks
B10 Evaluate sales data and revise 5 B9 0
B11 Promote strategy 8 B10 5
C Advertising and Promotion
C1 Determine the communication program 4 B1 8
C2 Evaluation& Decision Stage 2 C1 8
C3 Cooperate with promotional agencies 5 B2,C2 4
C4 Purchase promotion materials 6 B2 3
Considering the uncertainty of the project, the
company also used a more accurate estimation
method for each activity of the project - PERT. The
corresponding Pessimistic, Most Likely, Optimistic
time for each activity is given in Table 2 below,
allowing for a more accurate project estimation.
Table 2: PERT Original Data.
ACTIVITY Predecessor
TIME REQUIRED (WEEKS)
Pessimistic Most Likely Optimistic
A1 None 3 2 1
A2 A1, B1 7 5 4
A3 A2 6 5 4
A4 A3, B6 8 6 4
A5 A4 5 4 3
A6 B10 3 1 0.5
A7 A6 7 5 4
A8 A7 9 7 4
B1 None 5 3 1
B2 B1 12 10 6
B3 B2 13 10 6
B4 B1 6 3 1
B5 A2,B4 6 4 1
B6 B5 6 4 2
B7 None 9 7 4
B8 B7,C3,C4 8 4 3
B9 A5,B3.B8 10 8 5
B10 B9 6 5 3
B11 B10 9 8 5
C1 B1 6 4 3
C2 C1 4 2 0.5
C3 B2,C2 7 5 3
C4 B2 8 6 3
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
104
In addition to the project duration estimation, it is
necessary to use cost-effective methods to reduce the
project duration to minimize project expenditures,
considering that the earlier the project is completed.
Below (Table 3) is the list of activities that potentially
could be completed faster, together with the original
and “crashed” time for each activity and the cost for
crashing. Time and cost values between those shown
may be estimated using linear interpolation. For
example, the duration of A3 can be reduced by 1
week at the cost of $1050.
Table 3: TIME-COST TRADE-OFF Original Data.
Activity ID
Original
Time(weeks)
Crashed
Time (weeks)
additional
cost
Slope
Maximum
Crash Time
A3 5 3 2100 1050 2
A4 6 3 3900 1300 3
A7 6 4 7000 3500 2
B2 10 8 3200 1600 2
B5 4 3 1700 1700 1
B6 4 3 3400 3400 1
2.2 CPM
As a network planning technique, the critical path
method cannot be ignored in practical project
management. The critical path is the logical path in a
design with the longest delay from input to output.
Optimizing the critical path is an effective way to
improve the speed of design work. Generally, the
delay from input to output depends on the path with
the largest delay through which the signal travels,
independent of other paths with small delays. The
critical path method can be used repeatedly in the
optimization design process until it is impossible to
reduce the critical path delay (Pan 2010). The critical
path method is mainly a kind of network diagram
based on single-point time estimation with strict
order. It has emerged as an important aid for projects,
especially for providing a graphical display of the
project and its major activities. This quantitative
information provides an extremely important basis
for identifying potential project delay risks (Du
2007). Li-Li-Ping, Zhao-Xue in "Implementation of
Critical Path Method" explained in detail how to get
the earliest start time(ES), earliest finish time(EF),
latest start time(LS), and latest finish time(LF) by
using Forward Pass and Backward Pass (Li 2005),
which will not be repeated in this paper. Tan Zetao
explained the application of the critical path method
in schedule management in detail in "Research on
project schedule management based on critical path
method" (Tan 2019).
In this thesis, under the condition that the initial
data of the case is known, the critical path method is
used to draw the network flow diagram and get ES
EF LS LF according to the principle that the
SLACK of activity on the critical path equals 0. The
project duration can be obtained for the subsequent
optimization.
2.3 PERT
Planning review technology is another network
planning technology that is basically consistent with
the principles of the key path method. They all
arrange their project plans as a network map. The
main difference is the time estimation for each
operation. In the critical path method, the estimated
time of each operation is determined. Still, it is
difficult to accurately estimate the duration of each
operation in a project, such as some unheard of
projects or during the project, uncertain due to other
external factors, which will complicate the whole
project. Planning review technology provides a good
solution for this situation (Wu 2016).
In the classical PERT, the duration of each project
operation is a random variable and cannot give its
accurate time value, but its three time estimates can
be given, namely optimistic estimated time 𝑎, most
likely estimated time 𝑚 and pessimistic estimated
time 𝑏. The following assumptions are made: each
operation is independent of each others with no
correlation; the duration of the operation follows the
slice distribution.
The classical PERT approach assumes that all
operations are independent with no correlation.
Therefore, it does not consider critical operations on
Application of Project Management Tools in the Enterprise
105
Figure 2. Activity-on-node Network.
Figure 3: Activity-on-node Network with ES, EF, LS, LF.
non-critical operations and the expected mean 𝐷
ij
for the duration of each operation. And the variance
𝜎

is calculated by the following formula.
ij
(4 )
6
amb
D
++
=
(1)
2
2
()
36
ij
ba
σ
=
(2)
The expected mean D
ij
And the variance 𝜎

were
calculated for each operation., The proposed method
transforms the problem of uncertain construction
period into a definite problem that can be solved by
the CPM method. For a given line, the expected
duration 𝐸(𝑇
) and variance 𝜎
are calculated.
()
nij
ET D=
(3)
22
nij
σσ
=
(4)
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
106
The completion probability 𝑃(𝑡 𝑇
) under the
planned construction period 𝑇
is calculated with the
following formula.
2
2
1
()
2
0
1
()
2
S
S
n
tT
T
S
n
Pt T e dt
σ
σπ
≤=
(5)
Based on the initial data, PERT is calculated as
follows.
Table 4: PERT Calculation Results.
ACTIVITY
Predessor
TIME REQUIRED (WEEKS)
Pessimistic Most
Likely
Optimistic Te Var ES EF LS LF SLACK
A1 None 3 2 1 2 0.111 0 2 1 3 1
A2 A1, B1 7 5 4 5.16 0.25 3 8.166 3 8.166 0
A3 A2 6 5 4 5 0.111 8.166 13.16 11 16 2.833
A4 A3, B6 8 6 4 6 0.444 16 22 16 22 0
A5 A4 5 4 3 4 0.111 22 26 22 26 0
A6 B10 3 1 0.5 1.25 0.173 38.66 39.91 38.66 39.91 0
A7 A6 7 5 4 5.16 0.25 39.91 45.08 39.91 45.08 0
A8 A7 9 7 4 6.83 0.694 45.08 51.91 45.08 51.91 0
B1 None 5 3 1 3 0.444 0 3 0 3 0
B2 B1 12 10 6 9.66 1 3 12.66 6 15.66 3
B3 B2 13 10 6 9.83 1.361 12.66 22.5 16.16 26 3.5
B4 B1 6 3 1 3.16 0.694 3 6.166 5 8.166 2
B5 A2,B4 6 4 1 3.83 0.694 8.166 12 8.166 12 0
B6 B5 6 4 2 4 0.444 12 16 12 16 0
B7 None 9 7 4 6.83 0.694 0 6.833 14.66 21.5 14.66
B8 B7,C3,C4 8 4 3 4.5 0.694 18.5 23 21.5 26 3
B9 A5,B3.B8 10 8 5 7.83 0.694 26 33.83 26 33.83 0
B10 B9 6 5 3 4.83 0.25 33.83 38.66 33.83 38.66 0
B11 B10 9 8 5 7.66 0.444 38.66 46.33 44.25 51.91 5.583
C1 B1 6 4 3 4.16 0.25 3 7.166 10.25 14.41 7.25
C2 C1 4 2 0.5 2.08 0.340 7.166 9.25 14.41 16.5 7.25
C3 B2,C2 7 5 3 5 0.444 12.66 17.66 16.5 21.5 3.833
C4 B2 8 6 3 5.83 0.694 12.66 18.5 15.66 21.5 3
END A8,B11 0 0 0 0 0 51.91 51.91 51.91 51.91 0
PERT has the same fundamentals from CPM in
that CPM gives the determined duration of the
operation, which determines the start and end time of
each job, and determines the maneuver time on each
line through the earliest start time and the earliest and
latest end time, thus determining the key line and the
key operation. However, PERT is based on some
uncertainties in the project. Each job gives H time
estimates, respectively optimistic time estimate 0, the
most likely time estimate m, pessimistic time
estimate A, and then calculates the expected value of
the construction period according to the PERT
calculation method, thus transforming into the CPM
algorithm.
The advantages of PERT plan review technology
are mainly reflected in the following aspects:
(1) PERT is an effective method of prior control;
(2) Head at all levels can, through the project time
network analysis, not only can understand the whole
project construction process, understand the task
responsible for the status in the construction process,
enhance the overall view, also can make them more
clear their work focus, the mind on the key points that
Application of Project Management Tools in the Enterprise
107
need to take corrective measures, make the control
work has better results;
(3) PERT is a planning optimization method (Xie
2015).
2.4 TIME-COST TRADE-OFF
First, the time cost is the cost of not reaching a
specific agreement, and it is also the loss of market
opportunity during the waiting time. If a project does
not have a good time-cost trade-off, it is very likely
that the project will not achieve the company's
expected results, which makes time cost trade-offs
particularly important.
Next, we discuss the time cost trade-off method,
combining the critical activity in CPM with the
crashed time and additional cost of the trade-off
activity, following the following pattern"1" prioritize
the critical activity with the lowest single-day
addition cost
"2" Prioritize the critical activity with the longest
trade-off time. "3" prioritize the critical activity that
has the least impact on the critical path of the entire
project process.
These three priority principles are used to analyze
and trade-off the entire project process and carefully
select the critical activities that are needed and worth
trade-offs to ensure the optimal solution for the trade-
off costs.
As we all know, the process and schedule of a
project is never static. Perhaps there is no process in
our project that can satisfy the priority principle "3"
so that in our time-cost trade-off process, the number
of critical paths will most likely increase as the time
of some critical processes changes, which means that
in our step-by-step analysis process, we need to
simultaneously This means that the number of
processes that need to be traded off will also increase
as we move through the analysis. This means that the
number of processes that need to be traded off at the
same time increases as we move through the analysis.
Therefore, when there are too many processes in a
project, and the processes are too closely linked, we
can create an Excel spreadsheet to trade off the
project day by day, process by process.
We list all the paths and the time required for the
paths in the table, bold the font size of the critical
paths, and record the extra cost and the duration of
the tradeoff according to the priority principle
mentioned earlier. And observe whether new critical
paths appear.
For this tradeoff, we chose the A3 process that
followed all three priorities and reduced its time by 3
wks.
Table 5: TIME-COST TRADE-OFF Step 1-3.
Paths Length
A1-A2-A3-A4-A5-B9-B10-A6-A7-A8 48
A1-A2-A3-A4-A5-B9-B10-B11 43
A1-A2-B5-B6-A4-A5-B9-B10-B11 46
A1-A2-B5-B6-A4-A5-B9-B10-A6-A7-A8 51
B1-A2-A3-A4-A6-A7-A8 32
B1-A2-A3-A4-A5-B9-B10-A6-A7-A8 49
B1-A2-A3-A4-A5-B9-B10-B11 44
B1-A2-B5-A4-A6-A7-A8 35
B1-A2-B5-B6-A4-A5-B9-B10-A6-A7-A8 52
B1-A2-B5-B6-A4-A5-B9-B10-B11 47
B1-B4-B5-B6-A4-A6-A7-A8 33
B1-B4-B5-B6-A4-A5-B9-B10-A6-A7-A8 50
B1-B4-B5-B6-A4-A5-B9-B10-B11 45
B1-B2-B3-B9-B10-A6-A7-A8 49
B1-B2-B3-B9-B10-B11 44
B1-B2-C3-B8-B9-B10-A6-A7-A8 48
Table 5: TIME-COST TRADE-OFF Step 1-3 (cont.).
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
108
Paths Length
B1-B2-C3-B8-B9-B10-B11 43
B1-B2-C4-B8-B9-B10-A6-A7-A8 49
B1-B2-C4-B8-B9-B10-B11 44
B1-C1-C2-C3-B8-B9-B10-A6-A7-A8 44
B1-C1-C2-C3-B8-B9-B10-B11 39
B7-B8-B9-B10-A6-A7-A8 37
B7-B8-B9-B10-B11 32
Steps Alternatives Decision Extra
Cost
New Duration
1) A4,A7,B5,B6 Crash
A4
1300 51
1300350017003400
2) A4,A7,B5,B6 Crash
A4
1300 50
1300350017003400
3) A4,A7,B5,B6 Crash
A4
1300 49
1300350017003400
Note: In a project, the benefit of weighing one
process alone may be less than weighing multiple
processes at the same time, so we can achieve time-
cost trade-offs by weighing different processes in
different critical paths.
In this figure, we can see that if we want to shorten
the project duration, we can choose to trade-off A7 or
both B2 and B5. In the comparison table between the
trade-off process and its additive cost
We can find that the extra cost needed to weigh B2
and B5 at the same time is smaller than the extra cost
needed to weigh A7. To follow the first priority
principle, we choose to weigh B2 and B5 at the same
time and record the duration of the weighed items and
the extra cost needed for this tradeoff at the bottom
of the table.
Let's skip to the last tradeoff.
Table 6: TIME-COST TRADE-OFF Step 6.
Paths Length
A1-A2-A3-A4-A5-B9-B10-A6-A7-A8 48 47 46 45 44
A1-A2-A3-A4-A5-B9-B10-B11 43 42 41 40
A1-A2-B5-B6-A4-A5-B9-B10-B11 46 45 44 43 42
A1-A2-B5-B6-A4-A5-B9-B10-A6-A7-A8 51 50 49 48 47 46
B1-A2-A3-A4-A6-A7-A8 32 31 30 29 28
B1-A2-A3-A4-A5-B9-B10-A6-A7-A8 49 48 47 46 45
B1-A2-A3-A4-A5-B9-B10-B11 44 43 42 41
B1-A2-B5-A4-A6-A7-A8 35 34 33 32 31 30
B1-A2-B5-B6-A4-A5-B9-B10-A6-A7-A8 52 51 50 49 48 47
Application of Project Management Tools in the Enterprise
109
Table 6: TIME-COST TRADE-OFF Step 6 (cont.).
Paths Length
A1-A2-A3-A4-A5-B9-B10-A6-A7-A8 48 47 46 45 44
A1-A2-A3-A4-A5-B9-B10-B11 43 42 41 40
A1-A2-B5-B6-A4-A5-B9-B10-B11 46 45 44 43 42
A1-A2-B5-B6-A4-A5-B9-B10-A6-A7-A8 51 50 49 48 47 46
B1-A2-A3-A4-A6-A7-A8 32 31 30 29 28
B1-A2-A3-A4-A5-B9-B10-A6-A7-A8 49 48 47 46 45
B1-A2-A3-A4-A5-B9-B10-B11 44 43 42 41
B1-A2-B5-A4-A6-A7-A8 35 34 33 32 31 30
B1-A2-B5-B6-A4-A5-B9-B10-A6-A7-A8 52 51 50 49 48 47
3 RESULTS AND DISCUSSION
3.1 CPM
Analyzing the network diagram, we can find out the
critical path according to SLACK=0 and get the
project cycle time of 52 days. The activities on the
critical path will affect the completion time of the
whole project, so we can optimize the activities on
the critical path to advance the project completion
time.
3.2 PERT
Various risk factors in the construction of the project
are identified and given sufficient analysis. We can
better prevent and control the construction period
delay.
For this project, the subsequent analysis for
probability of completion of construction period
before node
D
and deviation value of normal
distribution
Z
are calculated using the formula of
normal distribution.
2
()D
Z
μ
σ
=
(6)
2
DZ
μ
σ
=+ (7)
It can be calculated that the time required to
complete 90% of the project cycle is 121.973074; the
proportion of projects that can be completed within
130 days is 0.999878867.
3.3 TIME-COST TRADE-OFF
When we find that there are no more processes to be
weighed after a tradeoff, or that the processes to be
weighed are no longer critical activities, the tradeoff
ends. The sum of the extra costs under each table is
calculated, which is the total extra cost needed for
this time cost tradeoff. The item at the bottom of the
penultimate table duration is the total duration of the
project after the time cost tradeoff.
In the case of this project, we can find that it is not
common to find a critical path that can satisfy all
three priority principles at the same time, so we
ranked the three priority principles following their
importance in the time cost tradeoff at the same time,
priority principle 1 is more important than priority
principle 2, and priority principle 2 is more important
than priority principle 3.
Table 7: TIME-COST TRADE-OFF Results.
Number of weeks by which the project can be
shortened
Decision PROJECT DURATION
/Weeks
EXTRA COST
52
1 A4 51 1300
2 A4 50 2600
3 A4 49 3900
4 B2&B5 48 7200
5 A7 47 10700
6 A7 46 14200
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
110
3.4 Discussion of Improvement Points
In view of the above research results, we can find that
the company still has room for optimization and
improvement in the process of project
implementation, and first put forward the following
suggestions:
3.4.1 Equipment Purchase Cycle Is Long
In the project start stage, after the project team is
established, and the project objectives, scope and
basic data are concluded, the project procurement
leader can be invited to intervene, fully understand
the specific needs of the project, and arrange
experienced professional suppliers to intervene in
advance from the existing qualified supplier database
according to the situation. If the resources are
insufficient in the existing supplier information
database, the procurement leader shall conduct high-
quality supplier sourcing and evaluation selection.
According to the project needs, the procurement
leader develops potential suppliers through various
ways to form the Supplier Situation Survey Form.
The procurement leader shall organize demand
department/project responsible department, quality
control department and other relevant departments to
conduct a joint review of potential suppliers, focus on
their basic situation, enterprise matching degree,
quality management, technical ability, delivery
ability, cost control, sustainability, etc., conduct
objective and comprehensive evaluation, form a
complete New Supplier Review Report and signed by
the joint review team, and be listed as potential
qualified suppliers.
The project leader shall formulate a project plan,
confirm key nodes, responsibilities, track and
monitor the supplier performance under agreed terms
and standards, implement positive and negative
incentives to motivate suppliers to cooperate actively
to improve performance level to avoid penalty; the
project team shall obtain management approval to
avoid supplier loss or form negative reputation of
illegal operation.
3.4.2 Equipment Assembly Time Is Lengthy
After project acceptance and delivery, the
procurement leader shall timely organize the relevant
core team and departments to conduct a performance
evaluation of suppliers, including quality
management, cost control, technical ability,
sustainable development, delivery ability, etc., make
comprehensive, specific and objective performance
evaluation scores for suppliers, and form supplier
performance feedback, communicate with the senior
level of suppliers and make targeted project summary
and improvement. As an important part of the
supplier information database, 2, supplier
performance evaluation should form closed-loop
management, continuous dynamic update, and form
a qualified and preferred supplier database. At the
same time, develop and develop supplementary
quality suppliers according to the situation, with a
virtuous cycle.
The value of procurement lies in building an
efficient supply chain, ensuring timely delivery of
purchased raw materials/production equipment by
quality, ensuring smooth production, realising price
reduction of the product life cycle, and succeeding by
making other departments succeed. Supplier
management covers many aspects of supply source
search, contract management and supplier
relationship management. It is the main task of
procurement involving supplier base rationalizations,
supplier selection, coordination, performance
evaluation, potential development and long-term
collaboration where appropriate.
3.4.3 Project Input into the Preliminary
Market Work Needs to Be Optimized
Specific optimization directions are given as follows.
(1) Opportunity Studies. Seek investment
opportunities and identify the investment direction
(2) Preliminary feasibility study. Determine
whether the project has vitality, macro necessity,
construction conditions, profit, etc. Project proposal:
implementation necessity and basis of the project;
product plan, proposed scale and construction site;
preliminary analysis of resources, construction
conditions, cooperative process and equipment;
investment estimate and financing plan; schedule;
preliminary estimate of economic effects and social
benefits
(3) Detailed feasibility study. Detailed technical
and economical demonstration, select the optimal
scheme based on multiple comparisons. The project
feasibility study is based on the project proposal and
the approval documents: whether technical
feasibility; whether significant economic and social
benefits; whether financial profit, human, material
and natural resources; how long the construction is
required; how much investment is required; whether
to raise funds, etc.
(4) Economic evaluation and decision-making.
Reduce and avoid investment risks, give full play to
investment benefits, and improve investment
decisions' scientific level. Financial evaluation is an
Application of Project Management Tools in the Enterprise
111
important basis for investment decisions, loans and
approval for national economic evaluation. Based on
the current financial system, current prices and
relevant regulations, predict the investment project,
solvency, and foreign exchange balance financial
status and determine the project's financial
feasibility.
3.4.4 Promotion Test Has a Large Room for
Improvement
The application of emerging social software and the
new product launch attempts held on the field can be
used as a new direction of promotion to reduce the
unnecessary time and capital cost brought by
traditional promotion methods.
In the preparation stage, I divide the material into
several directions; prepare 3-5 materials and art for
each direction. Select 3 materials from each direction,
three materials in each direction; prepare a landing
page for each direction or a general landing page.
During the test stage, each direction should ensure a
univariate test; more than three accounts in the same
channel. In the re-test stage, the test results in a good
direction, optimize the corresponding landing page,
expand more materials, try different copywriting,
other colleagues with good test results. Finally,
through the review, the reasonable and promotion of
publicity.
4 CONCLUSION
This thesis utilizes three tools, CPM, PERT, and TT,
which are used in the project management process to
predict and manage the cycle time of a case project.
It can be found that these three tools can contribute to
a great extent to the development and advancement
of projects.
In addition, the project management methods
discussed in this thesis are universally applicable.
Whether it is the launch of a new product in the food
industry, the development of a new product in the
industrial manufacturing industry, or the
implementation of a construction project, the
methods and tools discussed in this thesis can be used
for effective project management in all industries.
REFERENCES
Bi Xing. Research on cost management system of
engineering projects based on project management
theory[D]. Tianjin University, 2007.
Du Wenqiang. Application of critical path method in
project management [J]. Civil Construction Academic
Library,2007,8(00):342-343.
Hua Luogeng. Plain talk on integrated methods and
supplements [M]. Beijing: China Industrial Press,
1965.
Li Liping, Zhao Xueying. Implementation of critical path
method[J]. Journal of Hebei Software Vocational
Technology College, 2005, 7(4):61-64.
Liu, Jing. Research on project schedule management
method - critical path method [J]. Marketing World,
2020(16):158-160.
Ma Zunwu. Comparative analysis of Chinese and
American project management knowledge systems
based on process sequencing [J]. Project Management
Technology,2013,11(03):42-45.
Munns A K , Bjeirmi B F . The role of project management
in achieving project success [J]. International Journal
of Project Management, 1996, 14(2):81-87.
Pan Song. EDA Technology and Verilog HDL: Tsinghua
University Press, 2010
Tan Zetao. Research on project schedule management
based on critical path method[J]. Construction
Economics, 2019(9).
Tan Zetao. Research on project schedule management
based on critical path method [J]. Construction
economics, 2019(9).
Tan Zetao. Research on project schedule management
based on the critical path method [J]. Construction
Economics, 2019(9).
Wu Fei Fei. Research on project schedule risk evaluation
and dynamic control based on PERT [D]. Tianjin
University of Technology.
Wu Fei Fei. Research on project schedule risk evaluation
and dynamic control based on PERT [D]. Tianjin
University of Technology, 2016.
Xie WJ. Software development project schedule
management based on PERT and CCPM methods[D].
Zhejiang University of Technology,2015.
Yang Guang. Discussion on the application of modern
project management theory in engineering
management [J]. Engineering Construction and
Design,2021(06):223-224+227.
Yin Yilin, Zhu Junwen. Research on the development of
project management knowledge system[J]. China Soft
Science,2003(08):103-105+95.
Zhou Yongjun. Research on the status and development of
project management [D]. Northeast Normal University,
2006.
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
112