Research on Construction Project Management: Take Nanchen
Community Construction Project in Xingcun Town, Sishui County as
an Example
Yichi Jia
School of Beijing University of Civil Engineering and Architecture, Beijing, China
Keywords: Construction Project Management, Critical Path Method, Construction Efficiency, Project Quality.
Abstract: Project management is of great value in practice in many industries. In the construction process of the
construction industry, it has a key impact on the entire construction project to effectively analyze the critical
path and manage the construction schedule. This paper takes the Nanchen community construction project
as an example to study the construction project management, applies critical path method to the project
process to find the critical tasks in construction. It is found that almost all construction tasks are critical
activities and some problems affecting the progress of project need to be solved. Finally, there are some
suggestions given to help to improve the construction efficiency and quality, and finally complete the
project within the schedule time and funds.
1 INTRODUCTION
Construction project management is the general
term for supervision, coordination, and guidance
throughout the entire construction process of a
construction project. The construction contract is
used as the management basis to comprehensively
control the resource allocation, cost, schedule
arrangement, and construction safety of construction
projects. Construction project management of
construction projects mainly includes four aspects:
construction quality, construction progress,
construction safety and project investment,
respectively. Construction quality is the basic goal
of construction project management; construction
progress is its important aspect; construction safety
is its essential requirement and project investment is
its key indicator (Zhu 2021).
In the past 30 years, China's project management
has made great achievements and initially formed a
set of systematic management theories and methods.
There has been a series of construction-related
regulations being formulated. In 2018, the Ministry
of Housing and Urban-Rural Development approved
the technical standard of construction site
supervision information system for construction
projects as an industry standard, helping to
supervise and manage the quality, safety,
environment, and workers on-site (JGJ/T434-2018).
In 2016, the Ministry of Housing and Urban-Rural
Development updated the construction quality
evaluation standards for construction projects and
put forward strict quality evaluation standards for
each part of construction projects (GB/T50375-
2016). However, due to the influence of traditional
management models, many problems exist in project
management in China. It is still common to
underestimate project quality and delay the project
in many projects. Especially in recent years, the
more frequent occurrence of major engineering
accidents has brought a great threat to the safety of
life and property of the country and people. The
important reasons for the quality problems of
construction projects are inadequate management,
imperfect market, unprofessional managers, and
imperfect legal system.
So far, many scholars have conducted research
and discussion on construction project management
methods. Zhu Lei has introduced the concept of
construction project management, analyzed the
problems in construction project management in the
new period, and finally given improvement
strategies (Zhu 2021). Both Chen Liangming and
Wang Juan have done research on the problems in
the site management in construction project
management and correspondingly proposed
Jia, Y.
Research on Construction Project Management: Take Nanchen Community Construction Project in Xingcun Town, Sishui County as an Example.
DOI: 10.5220/0011305200003437
In Proceedings of the 1st International Conference on Public Management and Big Data Analysis (PMBDA 2021), pages 125-132
ISBN: 978-989-758-589-0
Copyright
c
2022 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
125
optimized measures to improve the management
level (Chen, Wang 2021)). Wang Xiong has studied
the technology application of project management in
construction, analyzed the important technologies
needed in construction, and given application
methods (Wang 2021). While, Yang Yu has
proposed an intelligent management method for
construction projects, explained the construction and
control methods of an intelligent management
system in detail, and proposed an innovative
application of intelligent management methods to
transform old urban communities (Yang 2021). It
can be seen that in the above journals, except for the
application examples mentioned by Yang Yu in the
paper, most of the current researches are
comprehensive and theoretical. Still, there is less
analysis about real projects.
This paper discusses the construction project
management of construction projects with a real
project. The organizational structure is as follows:
The first part introduces the meaning of construction
project management, the research background and
current research status. The second part takes the
Nanchen Community construction project in
Xingcun Town, Sishui County, as an example for
construction schedule planning analysis. The third
part analyzes the results from the data analysis and
gives the suggestions of optimization measures to
avoid delaying the construction progress.
2 RESEARCH METHODS AND
DATA ANALYSIS
This paper adopts scientific research methods in the
process of engineering case research, such as case
analysis method, quantitative analysis method,
comparative analysis method, and literature research
method. In addition, this paper also uses the critical
path method for data analysis.
2.1 General Methods
The case analysis method refers to the method of
analyzing a single object in combination with
literature data and deriving the general and universal
laws of things. This paper analyzes the Nanchen
community construction project.
The quantitative analysis method refers to the
method of appreciably, systematically and
quantitatively describing the obvious content of
various documents. This paper quantitatively
analyzes and describes the construction progress of
the Nanchen community construction project.
Comparative analysis refers to the method of
comparing objective things to understand the nature
and laws of things and make correct evaluations.
This paper compares the planned construction
progress and actual construction progress of the
Nanchen community construction project.
The literature research method refers to the
method of collecting, identifying, and collating
literature and forming a scientific understanding of
facts through the study of the literature. This paper
researches construction project management through
the study of industry standards and academic papers.
The ideological line that formed this paper is
shown in Figure 1. Because project management is
widely applied in the construction industry and the
technology is more complex, this paper takes
construction project management of construction
engineering as the research object, based on an
actual engineering case. First, determine the
research goal, which is to analyze the factors and
reasons that affect the project's construction
progress, and give advice. Then, understand the
research background through the study of literature
and industry standards. Then, analyze the project
case information, analyze the problems occurring,
analyze the reasons for the problems, and finally
give reasonable advice for improvement.
Figure 1: Idea flow chart.
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
126
2.2 Critical Path Method
2.2.1 Definition of Critical Path Method
The critical path refers to the logical path with the
longest delay from input to output in the design.
Optimizing the critical path is an effective way to
increase the speed of design work. Generally, the
delay from input to output depends on the path with
the longest delay the signal traverses and has
nothing to do with other paths with short delays. In
the optimisation design process, the critical path
method can be used repeatedly until it is impossible
to reduce the critical path delay (Zakia and Febrianti
2021).
2.2.2 Data Sources
The project discussed in this paper is constructing
resettlement buildings for villagers in Nanchen
Village, Xingcun Town. The planned total
construction area is 49,200 square meters, including
46,200 square meters for residential buildings and
garages, 2,000 square meters for commercial
buildings and 1,000 square meters for public
buildings. After the completion of the project, it will
greatly improve the current living standards and
improve the appearance of the village and the living
environment of the villagers.
This project is an EPC(Engineering Procurement
Construction) project (Qi 2021). The construction
enterprise is a member of the EPC project general
contracting consortium. The construction enterprise
needs to cooperate with the design enterprise to
complete the bidding, design, construction and
management of the whole process of the project.
Due to the large scope and complex content of the
whole process management, this paper selects the
important part, construction project management,
for analysis. The data is obtained from on-site
surveys and interviews with managers.
The project will be constructed for 672 days,
from January 28, 2021, to November 30, 2022. The
schedules for different parts of the construction
process are shown in the table below. And the
sequence is shown in the figure 2.
Table 1: Construction Time Schedule. (Unit: day).
ID Activity Duration Predecessor
A
Construction Preparation 30 -
B
Pile Foundation Construction 60 A
C
Earth Excavation 40 B
D
Cushion Construction 20 C
D1
Scaffolding 262 D
D2
Hydropower Reserve and Pre-
b
urie
d
262 D
E
Foundation Construction 35 D
F
Underground Structure Construction 65 E
G
Construction of the Main Structure 1-6 Floors 56 F
G1
Foundation Acceptance 30 F
G2
Backfill Construction 30 G1
H
Construction of the Main Structure 7-13 Floors 56 G
I
Masonry and Secondary Structure Construction 56 G
J
Spring Festival Holida
y
30 H, I
K
Masonry Structure Construction 20 J
L
Main Body Maintenance and Acceptance 30 D1,K,G2,D2
L1
Roof Construction 30 L
L2
Installation and Construction of Water, Electricity and
Heating
115 L
M
Plastering of Interior Walls 40 L
N
Floor Construction 40 L1, M
N1
Door and Window Installation 110 L1, M
N2
External Wall Insulation 45 L1, M
N3
Exterior Wall Finishing Construction 65 N2
O
Wall and Ceiling Scraping Putt
y
35 N
P
Ceiling Installation 35 O, L2
Research on Construction Project Management: Take Nanchen Community Construction Project in Xingcun Town, Sishui County as an
Example
127
P1
Outdoor Water Dispersing and Step Construction 35 O, L2
Q
Roof Surface Construction 20 N1,N3,P,P1
R
Final Cleanup 30 Q
R1
Installation and Debugging 30 Q
S
Completion Acceptance 30 R, R1
Figure 2: Process flow chart.
2.2.3 Critical Path Analysis for Schedule
This paper uses the critical path method to analyze
the above data. The formula used in critical path
analysis is as follows.
EF=ES+Duration (1)
Where ES represents the earliest start time, EF
represents the earliest finish time. Duration
represents the time it takes to finish the task based
on experience.
If the activity is a merge activity, the ES of the
activity is the longest finish time among all the
preceding activities.
LS=LF-Duration (2)
Where LF represents the latest finish time, LS
represents the latest start time.
If the activity is a burst activity, the LF of the
activity is the shortest start time among all the
subsequent activities.
Slack=LF-EF (3)
or
Slack=LS-ES (4)
Where Slack represents the maximum amount of
time, a task can be delayed beyond its early start
without delaying project completion.
For example, there is no predecessor of A, so the
ES of A is 0. The EF equals 0 plus 30 days, which is
30 days. The last task is S, so the LF equals its EF,
672 days. The ES equals 672 days minus 30 days,
which is 642 days. The Slack of G1 equals 382 days
minus 280 days or 352 days minus 250 days and
finally equals 102 days.
The data analysis is shown in the table below.
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
128
Table 2: Critical Path Analysis. (Unit: day).
ID Predecessor Duration ES EF LS LF Slack
A
- 30 0 30 0 30 0
B
A 60 30 90 30 90 0
C
B 40 90 130 90 130 0
D
C 20 130 150 130 150 0
D1
D 262 150 412 150 412 0
D2
D 262 150 412 150 412 0
E
D 35 150 185 150 185 0
F
E 65 185 250 185 250 0
G
F 56 250 306 250 306 0
G1
F 30 250 280 352 382 102
G2
G1 30 280 310 382 412 102
H
G 56 306 362 306 362 0
I
G 56 306 362 306 362 0
J
H, I 30 362 392 362 392 0
K
J 20 392 412 392 412 0
L
D1,K,G2,D2 30 412 442 412 442 0
L1
L 30 442 472 452 482 10
L2
L 115 442 557 442 557 0
M
L 40 442 482 442 482 0
N
L1, M 40 482 522 482 522 0
N1
L1, M 110 482 592 482 592 0
N2
L1, M 45 482 527 482 527 0
N3
N2 65 527 592 527 592 0
O
N 35 522 557 522 557 0
P
O, L2 35 557 592 557 592 0
P1
O, L2 35 557 592 557 592 0
Q
N1,N3,P,P1 20 592 612 592 612 0
R
Q 30 612 642 612 642 0
R1
Q 30 612 642 612 642 0
S
R, R1 30 642 672 642 672 0
3 RESULTS AND SOLUSIONS
3.1 Results of Data Analysis
According to the analysis results, the Slack of most
construction tasks is 0. The Slack is 0 means the
construction task is a critical activity. The paths
excluding foundation acceptance(G1), backfill
construction(G2), and roof construction(L1) are all
critical paths during the entire construction process.
And the construction tasks except for these three
tasks are critical parts of the construction process,
which means they can not be delayed. However, in
view of the importance of foundation acceptance and
backfill construction, these two tasks are normally
not postponed. Therefore, it can be seen that the
construction process is tightly arranged, and more
efficient construction project management is also
required to ensure that the project is carried out in
high efficiency and high quality as planned. And the
problems affect the progress should be found and
solved in time.
3.2 Problem Analysis in Construction
Some problems are happening during the
construction of this project, which have a certain
impact on the progress and quality of the project.
Among the parts that have been completed currently,
the progress of the construction of 1-6 floors of the
main body was greatly affected by the problems.
The following will describe the problems in detail.
Research on Construction Project Management: Take Nanchen Community Construction Project in Xingcun Town, Sishui County as an
Example
129
3.2.1 Shortage of Staff
It is still under the condition of the COVID-19
epidemic during the construction period, so the
progress of the project is affected by the epidemic to
a certain extent. The range of optional labor
subcontracting teams has been reduced, and most of
which are local teams, resulting in a reduction in
available workers. And their practical ability them
cannot be guaranteed. There are few on-site workers,
and some workers have the poor practical ability,
resulting in a lag in construction progress.
3.2.2 Lack of Communication between
Design Enterprise and Construction
Enterprise
The design enterprise and construction enterprise of
this project are not in the same city. Affected by the
epidemic, there are not enough staff of design
enterprise in the construction site. When the design
enterprise is needed, it is easy to be absent, which
leads to the lack of communication between the
design enterprise and the construction enterprise.
Sometimes the staff of the design enterprise at the
construction site cannot completely solve the
problem, so they need to connect the design
enterprise online to get the solution. Low
communication efficiency affects project progress.
3.2.3 Difference between the Design and the
Reality
Due to the lack of a sufficient investigation of the
building materials market, the design enterprise
changes some materials and related techniques, and
the construction difficulty and cost are increased.
The original design drawings plan to use non-
clay sintered bricks with strength MU20 in the
bottom frame structure of the multi-storey building.
But during the construction process, there are not
these types of bricks produced in local and nearby
cities. Then the construction enterprise
communicates with the design enterprise, after the
owner's consent, finally changes the strength from
MU20 to MU15, and at the same time increases the
size of the upper structural column and the number
of steel bars at the corresponding position of the
bottom frame column.
3.2.4 The Safety Awareness and Technology
of Staff Need to Be Improved
Some on-site workers have irregular construction
operations, and they misunderstand regulations and
safety signs. The failure to observe labor discipline
and safety regulations during construction operations
would endanger the personal safety of workers. In
addition, some workers are not professional enough,
and there is a phenomenon of focusing on the
progress and neglecting data at the construction site.
3.2.5 Quality Defects
Affected by the poor local woodworking technology
and other factors, some units had mold expansion
and slurry running during concrete pouring.
Honeycomb pitted surface, and rotten roots appeared
after concrete pouring, and then they were repaired.
Due to insufficient vibration, a honeycomb pitted
surface appeared in some parts. Because the bottom
is not cleaning thoroughly before pouring concrete at
the junction of the two parts of the stairs, the bad
connection and slag inclusions are caused. These
quality defects do not have much impact on the
building's bearing capacity, but it is still necessary to
avoid them during the construction process.
3.2.6 Mediation of Local Relations
Because this project is the resettlement house for
villagers in Nanchen Village, the original houses
need to be demolished. The demolition matters and
demolition compensation need to be communicated
with the villagers. Therefore, it takes some time to
negotiate, which affected the previous demolition
work and delayed the total duration.
3.3 Reasonable Solution
These problems have affected the construction
progress of the project, and also the quality of the
project to a certain extent. Therefore, it is necessary
to strengthen all aspects of management to ensure
that the project is carried out on schedule with
expected quality.
3.3.1 Strengthen Communication among All
Enterprises
The construction enterprise should strengthen
communication with the design enterprise. When
preparing detailed constructional drawings,
construction technicians should communicate with
the design enterprise to ensure that the nodes are
accurate and the drawings are feasible. Technicians
should check the finished drawings comprehensively
at the drawing review and confession stage, striving
to find problems in time and handle them properly.
PMBDA 2021 - International Conference on Public Management and Big Data Analysis
130
The communication among the construction
enterprise, the supervision enterprise, and the design
enterprise should be strengthened to ensure that the
project construction and coordinating the external
environment. The materials and machines should be
checked and accepted timely when entering the
construction site to avoid missing anything.
3.3.2 Construction Material Management
Construction enterprises should adopt effective
material management methods to avoid material
problems that will affect the construction progress.
They should conduct research in advance on the
building materials market where the project is
located to ensure that the building materials actually
purchased are the same as the materials in design.
The procurement link is the first link of material
management. Before purchasing materials,
construction enterprises must learn the supply
capacity and reputation of suppliers. At the same
time, construction enterprises must thoroughly check
the material specifications and qualification
certificates to not affect the construction progress
due to the difference between the actual and required
specifications.
When storing materials, workers must follow the
material storage specifications. In addition,
managers should timely sample the incoming
materials and submit them for inspection according
to the criterion. During the use of the materials,
managers should check the materials again, laying
the foundation for improving the quality of the
construction project.
3.3.3 Construction Safety Management
It makes sense to improve the quality of construction
only while ensuring the safety of workers.
Therefore, the construction enterprise should
improve safety education for workers so that
everyone can raise safety awareness and correctly
understand the terms and signs of the construction
management system.
Besides the workers, the managers should also
raise their safety awareness. Firstly, they should
improve their ability to manage, organize and
coordinate everything. Also, they should do the
security check on every construction procedure
workers do in a timely manner. Once there is a
safety hazard, it must be eliminated in time. Thirdly,
managers should check the situation of personnel
protective equipment worn by the workers on the
construction site. If some workers do not wear
personnel protective equipment at the construction
site, managers should remind them in time.
3.3.4 Construction Quality Management
To shift the post-inspection of project quality to pre-
control and achieve the goal of "prevention first", it
is necessary to strengthen the quality control of the
construction process.
To make the early quality control more
effectively, first, workers must strictly follow the
process. The process is the basis for construction
operations and the prerequisite to ensure quality.
Workers should be trained in advance and
supervised to strictly complete each process.
Second, the quality of conditions that affect the
process, including the operators, materials,
machines, methods and environment, also needs to
be controlled. And finally, on-site managers should
timely proofread the drawings, check the
construction quality and improve workers' awareness
of construction according to drawings. They should
count and analyse the quality data in time, eliminate
weaknesses of the project quality, and finally reduce
the phenomenon of focusing on progress and
neglecting data (Chen 2021).
4 CONCLUSIONS
This paper studies the application of project
management in the construction industry.
This paper applies the critical path method to the
construction management, analyzes the construction
schedule of the Nanchen community project, and
finally gets the following conclusions.
(1) Almost all construction tasks are critical
activities in the critical paths which means there is
little time for this project to delay, so the problems
affecting the progress should be paid more attention
to.
(2) There are some problems that affect the
construction schedule, such as the quality defects,
shortage of staff and poor communication in the
construction process.
(3) Nanchen community project should
strengthen the communication and improve material,
safety and quality management to ensure that
problems can be solves and project continues
successfully.
It is expected that the Nanchen community
project could improve the construction condition and
efficiency through the research in this paper.
Research on Construction Project Management: Take Nanchen Community Construction Project in Xingcun Town, Sishui County as an
Example
131
At present, there have been many studies on the
progress, cost and resource optimization of the
project at the early stage, but there are still many
problems about construction period and quality in
the actual construction process. The actual
construction situation is not exactly same as the
theoretical analysis. It is hopeful that there will be
more researches on reasons and solutions for the
differences between actual situation and theoretical
analysis, and also how to control cost and avoid
these problems during the construction process,
which can quote typical cases for illustration.
REFERENCES
Chen Liangming. (2021). Construction Site Management
and Optimization Measures in Construction Project
Management. Intelligent City, 2021(14):74~75.
Chen Xuekuan. (2021). Research on the Content of Civil
Engineering Project Management and Its Optimization
Measures. Management Exploration, 2021(09):25~27.
GB/T50375-2016, Construction Quality Evaluation
Standard of Building Engineering.
JGJ/T434-2018, Technical Standards for Construction Site
Supervision Information System of Building
Engineering.
Qi Qiang. (2021). Research on the optimization of
construction project management under EPC General
contracting Mode. Residence, 2021(24):121~122.
Wang Juan. (2021). Construction Site Management and
Optimization Measures in Construction Project
Management. Management, 2021(7):12~13.
Wang Xiong. (2021). Research on the Application of
Project Management Technology in Civil Engineering
Construction. Engineering Construction
Standardization, 2021(14):114~116.
Yang Yu. (2021). Research on the Application and
Practice of the Intelligent Management Mode of
Construction Projects. Real Estate World,
2021(14):107~111.
Zakia and Dian Febrianti. (2021). The Critical Path
Method in Construction Project Rescheduling. IOP
Conference Series: Earth and Environmental Science,
2021, 832
Zhu Lei. (2021). Construction Project Management. Green
Building Materials, 2021(7):143~144.