Identification of Risks in Making Decision for Overseas Expansion by
Indonesian State-owned Construction Enterprise
Jeffrey Limas Lim
1a
, Ayomi Dita Rarasati
2b
and Mohammad Ichsan
2c
1
Department of Civil Engineering, Faculty of Engineering, Universitas Indonesia, Depok, Indonesia
2
Management Department, Business School Undergraduate Program, Bina Nusantara University, Jakarta, Indonesia
Keywords: Risk, Overseas, Construction, Stated-owned Enterprise.
Abstract: Construction markets in ASEAN countries, Africa, Middle East, and Timor Leste are the main targets of
Indonesian state-owned construction enterprises in developing their business internationally. But the
international construction market can be described as complex, uncertain, and risky. Project risk greatly
affects the expected profit. Thus, companies must identify risks and how to deal with them before operating
abroad. The main goal of conducting this research is to identify risks in making decisions for overseas
expansion. This study uses a quantitative approach by distributing closed questionnaires about overseas
construction risks to experts and respondents and the data will be analyzed by descriptive statistics. This
research analyzed international projects and 10 highest risks have been identified. These risks are unbalance
cash flow (0.72), late construction (0.72), currency exchange rate fluctuation (0.56), unclear requirements
(0.56), funding shortage (0.56), productivity decreases (0.56), unclear boundaries of work (0.56), revolution
(0.40), complex planning and permit procedures (0.40), and inconsistencies in design / construction (0.40).
This research has positive implications for Indonesian state-owned construction enterprises in developing
their business overseas. The implication is to provide an overview of the risks that may occur hence Indonesian
state-owned construction enterprises can formulate strategies to overcome them.
1
INTRODUCTION
Construction is an important component to drive the
economy both nationally and internationally. The
industry of construction is considered one of the most
profitable business sectors. So that in addition to the
national construction market, many national
construction companies are also developing their
business to reach overseas markets. Globalization
brings a lot of benefits, and one of them is that it
creates good opportunities for the construction
company to enter attractive international project
markets (Wang, 2019).
Globalization creates a climate of openness in the
economy that allows local companies to take
advantage of opportunities to enter overseas markets
(Utama, et al, 2014; Wang, 2019). For example, the
Malaysian construction industry has generated high
market competition due to internationalization
a
https://orcid.org/0000-0001-8970-954X
b
https://orcid.org/0000-0002-7272-461X
c
https://orcid.org/0000-0001-7221-5172
pressures. However, the highly competitive domestic
market has encouraged much Malaysian construction
companies to expand their business abroad (Sarpin, et
al., 2019). It is undeniable that taking part in
international projects is a difficult and challenging
assignment (Sarpin, et al., 2019). The intensity to
expand their business into international markets for
Indonesian contractors has only recently begun.
Several projects in the ASEAN, Africa, and the
Middle East have continued since 10 years ago
(Utama, et al., 2014).
The global construction markets that are attractive
to national construction companies are the markets in
ASEAN, Africa, South Asia, and the Middle East.
This is in line with research conducted by Utama, et al.
(2014) who concluded that national construction
companies are very interested in the construction
market in ASEAN, Africa, and Middle East regions.
Utama, et al. (2014) explained that the Southeast
206
Lim, J., Rarasati, A. and Ichsan, M.
Identification of Risks in Making Decision for Overseas Expansion by Indonesian State-owned Construction Enterprise.
DOI: 10.5220/0010748100003113
In Proceedings of the 1st International Conference on Emerging Issues in Technology, Engineering and Science (ICE-TES 2021), pages 206-212
ISBN: 978-989-758-601-9
Copyright
c
2022 by SCITEPRESS – Science and Technology Publications, Lda. All rights reserved
Asian market represented by Timor Leste and Brunei
Darussalam had a high demand for Indonesian
construction services. There is easy access to market
access in Southeast Asia because there are cultural
similarities, ease of language, and historical relations
that are under the auspices of ASEAN (Utama, et al.,
2014). Markets in the Middle East and Africa are in
great demand due to the similarity of religions and
beliefs as well as the moral relationship between
governments (Utama, et.al., 2014). Ofori (2013) states
that the selection of project locations abroad depends
on the competitive advantage the company has
(Utama, et. al., 2014).
Since the 1990s, national construction companies
have been expanding overseas with high motivation
and seeing the broad construction market. The
national state-owned construction enterprise
represented by PT Hutama Karya worked on road
infrastructure projects in Malaysia from 1990 to
1993. Followed by PT Adhi Karya, and PT Waskita
Karya. Until finally PT Wijaya Karya has been
working on construction projects overseas the most to
date. This is in line with research conducted by Utama,
et al. (2014), that 6 Indonesian national construction
companies are active in the foreign construction
market, namely, PT Hutama Karya, PT Waskita
Karya, PT Wijaya Karya, PT Pembangunan
Perumahan, PT Adhi Karya, and PT Duta Graha
Indah from the private sector.
So many international projects are undertaken, but
in fact, international construction projects do not
always generate high revenues, contrary to what is
generally expected from risk international efforts
(Han, et al., 2007). The international construction
market can be described as risky, uncertain, and
complex (Gunhan & Arditi, 2005). Doing
construction projects overseas tend to have various
risk factors that can reduce the project’s profitability
(Han, et al, 2007).
Theoretically, doing construction service work
abroad has no difference from doing construction
service work in the home country. Minor differences
in local policies and regulations were confirmed to
exist but did not significantly differ from domestic
employment. But in reality, most large-scale
construction companies in Indonesia experienced
difficulties and even experienced losses during
conducting overseas construction work.
Conducting overseas construction projects is one
of the activities that are vulnerable to global issues
such as politics, economy, finance, social, culture,
and law. These projects are also pressured by various
kinds of business risks, such as inflation, interest rates,
currency exchange, and credit (Utama, et. al, 2019).
Expanding construction business to overseas market
has many risks and are exposed to more complex
problems compare to domestic projects. There is no
standardization for studies related to decision-making
to expand into the construction market overseas (Han
& Diekmann, 2001). Zhi (1995) has stated that
construction work abroad is categorized as a high-
risk business due to lack of information on the
workplace environment and lack of experience.
Various risk factors affect project cash flows,
especially for the international project domain, which
often fluctuates due to a myriad of external and
internal uncertainties (Han et al, 2014).
International projects face more varied and
difficult risks than domestic projects (Wang, 2019).
These risks exist at every stage of the implementation
of an overseas construction project, any negligence
will bring serious economic losses (Feng, et al.,
2014). Project risk greatly affects the expected profit
(Li, et al, 2020). Many companies experience large
losses when completing the project, so the estimation
of risk factors in overseas projects is very important
(Lin, 2016). Due to the wide range of complexities
and uncertainties, the decision to enter overseas
construction is complicated (Wang, 2019).
To enter foreign markets, the first thing we have
to do is identify the construction environment and
then make an initial assessment of the risks.
Reasonable selection of countries and territories can
also help reduce the possibility of unforeseen risks.
After winning the project tender, we must conduct a
detailed evaluation of the initial, intermediate, and
subsequent stages for it, then analyze the risks that
may occur (Lin, 2016).
The problem of risk management for overseas
construction projects is difficult (Liao, 2019). So that
ignoring this risk mitigation is an act of irresponsible
action and could cause making wrong decisions (Zhi,
1995). And if risk mitigation is not carried out
properly, it will have a big impact, namely only
getting a small profit, not getting a profit or even loss
(Han & Diekman, 2001). For this reason, risk
management is becoming more
emphasized and
systemized in international projects
to improve the
quality of difficult decisions which usually include
higher levels of risk exposure (Han, et al, 2008).
Construction companies are expected to be able to
make good decisions in carrying out international
construction projects by considering the main risk
factors at each stage of the project (Han, et al.,
2008). A new comprehensive solution will be
provided to avoid risks and difficulties in previous
overseas construction projects, and improvements
will immediately identify whether the general project
Identification of Risks in Making Decision for Overseas Expansion by Indonesian State-owned Construction Enterprise
207
management method is suitable for project
management purposes. (Liao, 2019).
There are so many possible risks in international
construction that can be reduced or avoided by
adopting an appropriate project implementation
strategy (Han & Diekman, 2001). For this reason,
companies engaged in the construction sector can
continue to expand overseas by mitigating risks and a
strategy to increase the number of market gains for
construction work abroad (Gunhan & Arditi, 2005).
To do business successfully in the overseas market,
construction companies need reliable risk analysis
and decision-making tools to make consistent
strategic entry decisions (Han & Diekman, 2001).
There are so much researches on the risks of
overseas projects, but there is no research on the risks
faced by Indonesian state-owned construction
enterprises in developing their business abroad.
Hence, the main goal of conducting this research is
to
identify and analyze the risks in making decisions
for
overseas expansion by Indonesian state-owned
construction enterprises. Research on risk
identification is in line with PMI (2017) which states
that risk identification is the second process in risk
management after risk management planning.
This research is limited to one of the most
advanced construction companies because it can
provide a real risk picture for other companies. This
research is expected to become the basis for
construction companies in carrying out risk
management before developing their business abroad.
2
METHODS
2.1 Research Design
In order to achieve the purpose of this research, the
methodology was designed with the quantitative
approach. The research object is Indonesia’s most
experienced state-owned construction enterprise in
handling the overseas project.
2.2 Research Variables
The variables that would be examined in this
research are based on Zhi (1995) namely nation risks
(X1), construction industry risks (X2), company
risks (X3), and project risks (X4). There were also
15 sub-variables and 65 indicators as follows:
1.
Political Situation (X1.1)
2.
Economical and Financial Situation (X1.2)
3.
Social Environment (X1.3)
4.
Market Fluctuations (X2.1)
5.
Law and Regulations (X2.2)
6.
Standards and Codes (X2.3)
7.
Contract Systems (X2.4)
8.
Employer/Owner (X3.1)
9.
Architect (X3.2)
10.
Labor and Sub-Contractor (X3.3)
11.
Material & Equipment (X3.4)
12.
Internal (X3.5)
13.
DefectivePhysical Works (X4.1)
14.
Schedule Delay (X4.2)
15.
Cost Overrun (X4.3)
2.3 Research Stages
The first stage of this research was an expert
judgment by asking the opinions of the experts to the
risks with distributing closed questionnaire with
Guttman scale. The second stage was doing the
respondent survey to assess and give engineering
judgment to the probability and the impact of the
risk.
The instrument was a closed questionnaire with
a Likert
scale.
After getting the data, the data were tested by
several tests such as validity test, reliability test, and
normality test. Then the further analysis was carried
out by analyzing risk value, risk level, and risk
ranking with descriptive analysis. The detail of
research stages is shown in Figure 1 below.
Figure 1: Stages of The Research.
2.4 Research Respondent
According to Sugiyono (2018), non-probability
sampling was used to selecting the samples of
experts and respondents. The requirements of the
samples were:
1.
The experts were minimum of 3 persons
ICE-TES 2021 - International Conference on Emerging Issues in Technology, Engineering, and Science
208
2.
The survey respondents were minimum of 30
persons
3.
The educational background should be a
bachelor degree
4.
The respondents should have experience and
expert in project risks
5.
The respondents should be an academician,
professional association member, and
practitioner in the overseas project for 5 years
minimum. The practitioner should be a project
management qualification.
The expert's profile is shown in Table 1 below:
Table 1: Experts Profile.
No Position
Experience
(Years)
Education
1
Director of
O
p
erations
35
Master Degree
2
Head of Overseas
Division
24
Master Degree
3
Head of Overseas
Branches
25
Bachelor
Degree
2.5 Research Instrument
In making a research instrument, a potential risk
analysis is developed to obtain primary data. Primary
data is data that directly provides data to data
collectors (Sugiyono, 2017). Primary data to answer
research questions is nominal data and ordinal data
that comes directly from respondents which will then
be processed.
The measuring scale used in the instrument to
answer the research question was the Guttman Scale,
and Likert Scale. Guttman scale was used for
expert
judgment questionnaire to get the opinion yes
or no to
the risk variables. The Likert scale was used to assess
the risk probability and risk impact. The Likert scale
would be converted to the probability and impact
matrix with the scoring scheme developed by PMI in
2017.
2.6 Data Analysis
The data that had been obtained through expert
judgment survey and survey respondents were then
analyzed using descriptive analysis. Analysis for
expert judgment by looking at the answer mode of the
experts. However, to analyze the survey results,
respondents must go through validity tests,
instrument reliability tests, and data normality tests to
conclude the survey results. To get the risk value is to
multiply the value of risk possibility and the value of
risk impact and then it was categorized and ranked.
3
RESULTS AND DISCUSSION
3.1 Expert Judgement Result
The risk indicators were examined and validated by
the experts of overseas construction (See Table 1.).
Base on the expert judgment analysis result shows
that only 2 risk indicators were validated by the
experts. They were X1.2.2 Incompatible GNP Per
Capita and X1.3.8 Brotherhood. For the other 63 risk
indicators, more than 65% of experts were agreed and
validated.
3.2 Respondent Survey Result
Based on the results of an analysis of 30 respondents
who are involved in overseas projects, it shows that
most of the respondents have a master education
(70%) and 30% are undergraduate, 67% staff and
33% are managers, and have experienced 5-10 years
80% and 20% 11-15 years. The detailed analysis is
shown in Table 2.
The data on the possibility of risk were tested by
reliability testing and showed that the level of
reliability was very high (Cronbach's Alpha 0.971>
0.8). The data homogeneity test was also carried out on
the education, position, and experience categories and
the results showed that all risk indicators were
homogeneous (Asymp. Sig.> 0.05). In addition, the
data normality test was also carried out to determine
the normality of the data so that the results could be
used as a basis for concluding. The results of the data
normality test showed that all the data obtained were
not normal (sig. <0.05), so that the conclusion of
possible risks was drawn based on the median value.
Table 2: Respondents Characteristics.
No Category
A
Education
1 Bachelor 9 30%
2 Master 21 70%
Total Sam
p
les 30
B Position
1 Manager 10 33%
2 Staff 20 67%
Total Samples 30
C Ex
p
erience
1 5 - 10 Years 24 80%
2 11 - 15 Years 6 20%
Total Samples 30
Identification of Risks in Making Decision for Overseas Expansion by Indonesian State-owned Construction Enterprise
209
Table 3: Top Ten High-Risk Indicators.
Code Risk Indicator Score
Risk
Level
Risk
Rank
X3.5.1
Unbalance Cash
flow
0.72 High
1
X4.2.2
Late Construction
0.72 High
2
X1.2.5
Currency
Exchange Rate
Fluctuation
0.56
High
3
X3.1.1
Unclear
Requirements
0.56 High
4
X3.1.2
Funding Shortage
0.56 High
5
X3.5.4
Productivity
decreasses
0.56 High
6
X4.3.1
Unclear
boundaries of
works
0.56 High
7
X1.1.2 Revolution 0.4 High
8
X2.2.2
Complex
p
lanning
and permit
prochedures
0.4 High
9
X2.3.1
Inconsistencies in
design/
construction
0.4 High 10
The data on the impact of risk were tested by
reliability testing and showed that the level of
reliability was very high (Cronbach's Alpha 0.971>
0.8). The data homogeneity test was also carried out on
the education, position, and experience categories and
the results showed that all risk indicators were
homogeneous (Asymp. Sig.> 0.05). In addition, the
data normality test was also carried out to determine
the normality of the data so that the results could be
used as a basis for concluding. The results of the data
normality test showed that all the data obtained were
not normal (sig. <0.05), so that the conclusion of
possible risks was drawn based on the median value.
The conclusion of the possibility and impact of the
risk is then multiplied to obtain a risk value. The result
of the analysis shows that 222 risk indicators are high,
36 risk indicators are moderate and 4 risk indicators
are low. Table 3 shows the top ten high- risk
indicators which must be controlled.
The results of the international project risk
analysis that has been carried out show that 10 high
risks have been identified. These risks are unbalance
cash flow (0.72), late construction (0.72), currency
exchange rate fluctuation (0.56), unclear
requirements (0.56), funding shortage (0.56),
productivity decreases (0.56), unclear boundaries of
work (0.56). , revolution (0.40), complex planning
and permit procedures (0.40), and inconsistencies in
design / construction (0.40). Details of the results of
the international project risk assessment analysis can
be seen in Table 3 above.
3.3 Discussion
The main motivation of construction companies to
develop their business internationally is mainly to
increase its profitability (Utama, et al., 2019). But the
international construction market can be described as
risky, uncertain, and complex (Zhi, 1995; Gunhan &
Arditi, 2005; Wang, 2019). Li, et al. (2020) stated that
project risk greatly affects the expected profit (Li, et
al, 2020).
International projects are particularly vulnerable to
economic and financial problems. Therefore poor cost
control is a problem in project risk management (Liao,
2019) because it can cause the highest risk, namely
unbalanced cash flow (Zhi, 1995). Determining
payment terms and conditions and the financing
schedule is the main key related to estimating the
project cash flow situation before the project starts.
However, there are a variety of risk
factors that affect
project cash flows, particularly for
the international
project domain, which often fluctuates due to a
myriad of external and internal uncertainties (Han, et
al, 2014) such as currency exchange rate fluctuations
(Zhi, 1995; Utama, 2019).
The imbalance of cash flows can cause a very high
risk, namely a lack of funds to finance project
operations (Zhi, 1995). In addition, without sufficient
financing, it will create new risks such as difficulty
finding reliable skilled workers (Zhi, 1995; Sarpin,
2019). If the project is not supported by skilled
personnel, it will cause productivity to decrease (Zhi,
1995) and in the end, the project will be late (Zhi,
1995). All of this includes a very high risk to an
international project which must be managed
properly because it will greatly affect cost and time
performance. And in the end, it will affect the
profitability of the project.
Based on research conducted by Utama (2019)
which states that politics is also one of the highest
project risk. Zhi (1995) previously stated that politics
is one of the project risks, one of which is revolution.
This is also closely related to the economic stability
of the host country where the project is constructed.
Overseas engineering construction project faces
high risks, as these risks are inherent at every stage of
project construction (Han, et al., 2008; Feng, et al.,
ICE-TES 2021 - International Conference on Emerging Issues in Technology, Engineering, and Science
210
2014). At the time of signing the contract, for
example, the contractor must carefully read, translate
and understand every contract clause, because the
clarity of the contract is an important thing that affects
the work of international projects (Utama, et al.
2019). In line with this statement, the result shows that
unclear requirements and unclear
boundaries of works
contained in the contract clause
are considered high
risks.
Apart from the foregoing, project complexity is
also one of the problems in international construction
projects (Han & Diekman, 2001; Utama, et al., 2019).
The complexity of the project is not only the type of
project but also complex planning and permit
procedures (Zhi, 1995). And in the construction
implementation process, design changes often occur,
causing a very high risk of inconsistencies in
design/construction (Zhi, 1995).
It will have a big impact such as getting a small
profit, or even loss (Han & Diekman, 2001). These
can also lead to increased costs and project delays
resulting in decreased project time and cost
performance. And all of these risks can be a
consideration in making decision regarding overseas
expansion (Han, et al., 2008; Liao, 2019).
4
CONCLUSIONS
Based on the results of the analysis that has been
done, several things can be concluded from this study.
There are 10 highest risk indicators with risk value
between 0.40 – 0.72 on the variable examined as
follows:
1.
Unbalance Cash flow (0.72)
2.
Late construction (0.72)
3.
Currency exchange rate fluctuation (0.56)
4.
Unclear requirements (0.56)
5.
Funding shortage (0.56)
6.
Productivity decreases (0.56)
7.
Unclear boundaries of work (0.56)
8.
Revolution (0.40)
9.
Complex planning and permit procedures
(0.40)
10.
Inconsistencies in design/ construction (0.40)
This research has positive impact for Indonesian
state-owned construction enterprises in developing
their business overseas. The implication is to provide
an overview of the risks that may occur hence
Indonesian state-owned construction enterprises can
formulate strategies to overcome them.
This research can be developed in further research
by analyzing preventive and corrective actions to
reduce the risk value. The risks in this study can be
used as a basis for advanced research on the strengths,
weaknesses, opportunities, and threats of the company
in dealing with these risks, and in the end, strategies
can be formulated to manage the risks hence the
overseas business development becomes an
opportunity that benefits the company.
ACKNOWLEDGEMENTS
The authors would like to thank The Overseas
Division of PT. Wijaya Karya (Persero), Tbk. for
permitting us to carry out this research and to
support morally.
REFERENCES
Feng, X., Lin, S., Hao, H., & Wei, Z. (2014). Quantitative
Solution of Overseas Project Risk Management by
Knowledge Engineering. Sustainable Development of
Critical
Infrastructure. Doi:10.1061/9780784413470.016 Gunhan,
S., & Arditi, D. (2005). International Expansion
Decision for Construction Companies. Journal of
Construction Engineering and Management, 131(8),
928–937.
Han, S. H., & Diekmann, J. E. (2001). Making a Risk- based
Bid Decision for Overseas Construction Projects.
Construction Management and Economics, 19(8), 765–
776. Doi:10.1080/01446190110072860
Han, S. H., Park, H. K., Yeom, S. M., Chae, M. J., & Kim, D.
Y. (2014). Risk-Integrated Cash Flow Forecasting for
Overseas Construction Projects. KSCE Journal of Civil
Engineering, 18(4), 875–886. Doi:10.1007/S12205-
014-0464-8
Han, S. H., Park, S. H., Kim, D. Y., Kim, H., & Kang, Y.
W. (2007). Causes of Bad Profit in Overseas
Construction Projects. Journal of Construction
Engineering and Management, 133(12), 932–943.
Doi:10.1061/(Asce)0733-9364(2007)133:12(932)
Han, S. H., Park, S. H., Kim, D. Y., Kim, H., & Kang, Y.W.
(2007). Causes of Bad Profit in Overseas Construction
Projects. Journal of Construction Engineering and
Management, 133(12), 932–943. Doi:10.1061/(Asce)
0733-9364(2007)133:12(932)
Li, G., Zhang, G., Chen, C., & Martek, I. (2020). Empirical
Bid or No Bid Decision Process in International
Construction Projects: Structural Equation Modeling
Framework. Journal of Construction Engineering and
Management, 146(6), 04020050. Doi:10.1061/(Asce)
Co.1943-7862.0001830
Liao, L. (2019). a Proposed Comprehensive Analysis and
Solution for Overseas Construction Project
Management, 2nd International Symposium on Social
Science and Management Innovation (SSMI 2019),
Identification of Risks in Making Decision for Overseas Expansion by Indonesian State-owned Construction Enterprise
211
Advances in Social Science, Education and Humanities
Research, Volume 375, 481-485
Lin, C. (2016). the Risk Management under Conditions of
Contract for EPC in Overseas Projects. 2016
International Conference on Logistics, Informatics and
Service Sciences (LISS). Doi:10.1109/Liss.2016
.7854480
PMI. (2017). Project Management Body of Knowledge.
Project Management Institut, Inc. : Pennsylvania
Sarpin, N., Chia, Y. L., Kasim, N., Mohd Noh, H., Omar,
R., & Zainal, R. (2019). Key Strategies in Undertaking
International Construction Project: Contractors’
Perspective. MATEC Web of Conferences, 266, 03019.
Doi:10.1051/Matecconf/201926603019
Sugiyono. (2018). Metode Penelitian Kuantitatif
Bandung: Alfabeta Utama, W. P., Chan, a. P. C., Zahoor,
H., & Gao, R. (2014). Indonesian Contractors in
Overseas Construction Projects: Southeast Asia, the
Middle East and Africa. ICCREM 2014. Doi:10.1061/
9780784413777.063
Utama, W. P., Chan, a. P. C., Zahoor, H., Gao, R., & Jumas,
D. Y. (2019). Making Decision toward Overseas
Construction Projects. Engineering, Construction, and
Architectural Management. Doi:10.1108/Ecam-01-
2018-0016
Wang, C., Loo, S. C., Yap, J. B. H., Dan Abdul-Rahman,
H. (2019). Novel Capability- based Risk Assessment
Calculator for Construction Contractors Venturing
Overseas. Journal of Construction Engineering and
Management, 145(10), 04019059.
Doi:10.1061/(Asce)Co.1943-7862.0001696 S
Zhi, H. (1995). Risk Management for Overseas
Construction Projects. International Journal of Project
Management, 13(4), 231–237. Doi:10.1016/0263-
7863(95)00015-I
ICE-TES 2021 - International Conference on Emerging Issues in Technology, Engineering, and Science
212