Analysis Scheduling XYZ Project using Critical Path Method (CPM)
and Program Evaluation and Review Technique (PERT) at PT. NOV
Profab
Rohilatul Khazanah
and Sri Zuliarni
Applied Business Administration, Politeknik Negeri Batam, Jl. Ahmad Yani, Batam, Indonesia
Keywords: CPM, PERT, Scheduling, Project.
Abstract: This study aims to test the scheduling of the XYZ project at PT. NOV Profab uses CPM and PERT methods.
From this research, we will get the estimation of scheduling time and find the critical path of each method.
This study uses data collection techniques by means of direct interviews with the project engineer and
documentation data in the form of project schedule attachments. This study was structured with mixed
methods. Each method has 3 critical paths, the result of scheduling the CPM method for 52 days, according
to the real schedule of the XYZ project and the PERT method for 51 days, faster with the real schedule of the
XYZ project.
1 INTRODUCTION
1.1 Research Baground
In this study, the object under study is the XYZ
project. It is known that the XYZ project is a piping
type project. The method used for scheduling a
project is to use the Critical Path Method (CPM) and
Program Evaluation and Review Technique (PERT).
The CPM method is a method that has 2 stages (two
passes) in its calculation, namely forward calculation
and backward calculation. According to Nurjaman
(2014) PERT method is a project scheduling method
that has three estimates of time for each activity, with
these three times the probability of completing a
project can be known.
In this study, the researcher wants to analyze the
XYZ project if it is scheduled using the CPM and
PERT methods which will later be known how long
an XYZ project can be carried out and get the critical
path. Researchers want to research related to project
scheduling because the place of research is carried out
in a fabrication construction company where the
production process is producing projects and each
project has its own schedule, and the XYZ project is
the object of this research. This research was
conducted using two methods, namely CPM and
PERT, where the method is a project scheduling
method and can find out the comparison of project
scheduling time with each method so that the final
results of the research are more complex when using
two methods, namely CPM and PERT.
From the results of CPM and PERT can find out
how long a project can be completed and get the
critical path. From the description above, the
researcher will analyze and take the research title
"Analysis of XYZ Project Scheduling Using Critical
Path Method (CPM) and Program Evaluation and
Review Technique (PERT) at PT. NOV Profab
2 LITERATURE REVIEW
2.1 Scheduling
According to Husen (2009), scheduling is the process
of placing time in carrying out the stages of working
on a project until it is completed by estimating
existing limitations for optimal results. According to
Ginting (2009), scheduling has a goal, namely,
increasing the use of resources and reducing waiting
times, so that work can be reduced and productivity
increases, reducing delays in work that have
deadlines, assisting in making decisions about the
required capacity plan to avoid additional costs.
Khazanah, R. and Zuliarni, S.
Analysis Scheduling XYZ Project using Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) at PT. NOV Profab.
DOI: 10.5220/0010861200003255
In Proceedings of the 3rd International Conference on Applied Economics and Social Science (ICAESS 2021), pages 179-183
ISBN: 978-989-758-605-7
Copyright
c
2022 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
179
2.2 Project Management
Project management is the application of knowledge,
skills, tools and techniques used to fulfill project
activities (K.H., 2013). In the book A Guide to The
Project Management of Knowledge, by Rose (2013)
there are five stages or processes, that’s Initiating,
Planning, Executing, Monitoring and controlling,
Closing
2.3 Networking
According to Muhardi (2011), network planning is a
project plan and control, which describes the
dependencies between each job described in the
Network diagram. Network symbols:
Table 1: Symbol Networking.
3 METHODOLOGY
3.1 A Research Framework
The framework of thought in this research is a
theoretical concept that explains the relationship
between variables. However, in this study there is
only one variable, namely project scheduling.
Therefore, the framework of thought in this research
is as follows:
Figure 1: A Research Framework.
3.2 Population and Sampling Methods
The population used is in the form of data related to
scheduling the XYZ project in 2021 and interview
data obtained from interviews with the project
engineer department, especially with the Senior
Project Engineer. The population used is in the form
of data related to scheduling the XYZ project in 2021
and interview data obtained from interviews with the
project engineer department, especially with the
Senior Project Engineer.
3.3 CPM Method
1. Forward Pass
ES (early start) is obtained from the EF results in the
previous activity.
Formula 1: Early Finish.
(Source: Stevenson, 2009)
2. Backward Pass
To determine the LF (latest finish) with the smallest
LS in the previous activity.
Formula 2: Latest Start.
(Source: Stevenson, 2009)
ICAESS 2021 - The International Conference on Applied Economics and Social Science
180
3. Slack
Slack value to find the critical path if the slack value
= 0
Formula 3: Slack.
(Source: Stevenson, 2009)
3.4 Pert Method
1. Optimistic Time (a)
Optimistic time is the estimated time if a schedule
does not experience constraints and the execution is
as expected.
Formula 4: Optimistic Time.
(Source: Nurhayati, 2010)
2. Pesimistic Time (b)
Pessimistic time is the estimated time if a schedule
has problems and the process can take longer.
Formula 5: Pessimistic Time.
(Source: Nurhayati, 2010)
3. Realistic/ most likely (m)
Realistic time is when it actually happens.
Formula 6: Realistic/Most Likely Time.
(Source: Nurhayati, 2010)
4. Expected Time Activity (te)
Expected Time Activity is the expected time for
scheduling to be completed by calculating 3 time
estimates.
Formula 7: Expected Activity Time
(Source: Nurhayati, 2010)
4 ANALYSIS AND RESULT
4.1 Schedule Xyz Project
Table 3: Schedule XYZ Project.
Analysis Scheduling XYZ Project using Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) at PT. NOV
Profab
181
4.2 Networking and Results CPM
Method
Picture 2: CPM Networking.
Table 4: Counting CPM Method.
Based on the results of the research that has been done
regarding the scheduling of the XYZ project using the
CPM method, the results obtained for 52 days which
means that the scheduling of the XYZ project using
the CPM method is the same as the real time schedule
of the XYZ project. The critical path in the CPM
method is the Slack value = 0. There are 3 critical
paths or the longest path, namely the first path, Start-
A-B-D-F-G-H-U-V-W-Finish; second line, Start-A-
B-I-J-L-M-N-O-U-V-W-Finish; and the third track,
Start-A-B-I-K-L-M-N-O-U-V-W-Finish.
4.3 Networking and Results PERT
Method
Table 5: Counting PERT Method.
ICAESS 2021 - The International Conference on Applied Economics and Social Science
182
Picture 3: PERT Networking.
Based on the results of research that has been done
related to scheduling the XYZ project using the PERT
method, taking into account 3 estimated times, the
results are 51 days, which means that the scheduling
of the XYZ project using the PERT method is 1 day
faster than the real time schedule for the XYZ project.
and there are 3 critical paths, namely the first path,
Start-A-B-D-F-G-H-U-V-W-Finish; second line,
Start-A-B-I-J-L-M-N-O-U-V-W-Finish; and the third
line, Start-A-B-I-K-L-M-N-O-U-V-W-Finish
5 CONCLUSIONS
Based on the results of the study it can be concluded:
1. The results of the calculation of the XYZ project
scheduling using the CPM method with a duration
of 52 days, which means that the scheduling is in
accordance with the real schedule of the XYZ
project for 52 days. And scheduling using the
PERT method was obtained for 51 days, which
means 1 day faster than the real schedule of the
XYZ project.
2. In the scheduling network using the CPM method,
there are 3 critical paths and each has a duration
of 52 days, namely path 1, Start-A-B-D-F-G-H-
U-V-W-Finish; lane 2, Start-A-B-I-J-L-M-N-O-
U-V-W-Finish; lane 3, Start-A-B-I-K-L-M-N-O-
U-V-W-Finish. In the network using the PERT
method, there are 3 critical paths for 51 days,
namely lane 1, Start-A-B-D-F-G-H-U-V-W-
Finish; lane 2, Start-A-B-I-J-L-M-N-O-U-V-W-
Finish; lane 3, Start-A-B-I-K-L-M-N-O-U-V-W-
Finish.
REFERENCES
Ginting , R. (2009 ). Penjadwalan Mesin . Yogyakarta :
Graha Ilmu .
Husen , A. (2009). Manajemen Proyek(Perencanaan
Penjadwalan dan Pengendalian Proyek). Yogyakarta :
Andi .
K.H., R. (2013). A Guide to the Project Management Body
of Knowladge (PMBOK Guide) Fifth Edition.
Pennslyvania: Project Management Institute.
Muhardi. (2011). Manajemen Operasi . Bandung : Refika
Aditama .
Nurhyati. (2010). Manajemen Proyek . Jogjakarta: Graha
Ilmu .
Nurjaman kadar, D. H. (2014). Manajemen Proyek . CV.
Pustaka Setia .
Stevenson , J. (2009). Operations Management . America :
McGraw Hill Companies .
Analysis Scheduling XYZ Project using Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) at PT. NOV
Profab
183