Implementation Monte Carlo Simulation in Investment Evaluation:
Case Study - Gas Compressor Investment PLTG 4 x 25 MW
Maleo-Gorontalo
Abdollah Siregar
1a
and Sudarso Kaderi Wiryono
2
1
PT XYZ, Finance Manager, Batam Indonesia
2
School of Business and Management, Institut Teknologi Bandung, Indonesia
Keywords: Capital Budgeting, Investment Evaluation, Sensitivity Analysis, Monte Carlo Simulation, uncertainty.
Abstract: Investment evaluation is a crucial part before investment decision in order to measure will the project generate
profit for the company. This study is investment evaluation Gas Compressor Investment PLTG 4 x25 MW
Maleo Gorontalo. There are two investment evaluation method in this project Capital Budgeting and Monte
Carlo Simulation. Capital Budgeting technique used to measure this investment evaluation in this project
consist of Net Present Value (NPV), Internal Rate Return (IRR), Probability Index (PI) and Payback Period
(PBP). From the evaluation, it was obtained that a positive NPV of 500,444, an IRR of 11.50% greater than
the WACC of 9%, while the PI of 1.08 and PBP of 1.57 years was faster than the duration of the 2 (two) year
contract. Monte Carlo simulation applied to predict the financial feasibility of a project by considering risks
and uncertainties use to calculate Probability NPV<0 in this project, with use Capital Expenditure (CAPEX),
Lifetime Project and Debt: Equity Portion as the input variables. Monte Carlo simulation result probability
NPV <0 is 10,32 % mean while probability NPV >0 is 89,68%.
1 INTRODUCTION
1.1 Background
Electricity is a basic human need, which is an
inseparable part from daily life. According to report
second quarter of 2020 the data shows that the
development of the national electrification ratio has
reached 99.09%, as explained in the graph below:
Figure .1. Electrification Ratio
The electrification growth mentioned above
resulted an increase in electricity production in GWh
with an average annual growth of 5.62% while the
a
https://orcid.org/0000-0002-6599-3379
average annual increase in electricity sales in GWh
was 5.86% per year. The comparison between
production and sales in GWh is presented in the graph
below:
Figure .2. Production and Sales in GWh 2011-2019.
The transformation of PLN towards new and
renewable energy (EBT) is still emphasizing the
energy mix in coal and placing natural gas energy
sources as a transition energy to EBT. The following
is the energy mix target to generate electricity starting
at the end of 2025.
72
Siregar, A. and Wiryono, S.
Implementation Monte Carlo Simulation in Investment Evaluation: Case Study - Gas Compressor Investment PLTG 4 x 25 MW Maleo-Gorontalo.
DOI: 10.5220/0010935100003255
In Proceedings of the 3rd International Conference on Applied Economics and Social Science (ICAESS 2021), pages 72-79
ISBN: 978-989-758-605-7
Copyright
c
2022 by SCITEPRESS Science and Technology Publications, Lda. All rights reserved
Figure 3: Target of energy mixing end of 2025.
PT XYZ as a subsidiary of PT Pelayanan Listrik
Nasional Batam (PLNB) a state-owned company
electricity provider in Batam island. PT XYZ has
contributing to Optimizing Cost Efficiency in PT
PLN (Persero) group especially for gas infrastructure
and the first subsidiary specialize in gas pipeline in
PT PLN (Persero).
PT XYZ has received an offering letter from PT
PLN Gas Geothermal (“PLNGG”) as the owner of the
project to offer Investment in Gas Compressor for
PLTG 4 x 25 MW Maleo-Gorontalo.
Management of PT XYZ need to ensure the in-
vestment decision according to offering letter will
generate a profit margin to the Company.
1.2 Problem Statement
As described above, will investment in Compressor
for PLTG 4 x 25 MW generate profit to PT XYZ.
And questions related to this statement are:
a. What return are expected and how can manage-
ment maximize the return?
b. How are investment performing evaluated by
Capital Budgeting?
c. Which scenarios greatest financial risk or benefit?
d. Percentage of probability Net Present Value > 0,
as indicate of project success?
1.3 Objective
The main objectives of this paper are as follow:
a. To analyze investment evaluation of the project
with to the Capital Budgeting technique.
b. To identify the most sensitives variable key
changes input to capital budgeting indicator.
c. To perform assessment on sensitivity of uncer-
tainties factors in the investment decision with
Monte Carlo simulation to get profitability of suc-
cess of project.
2 LITERATURE REVIEW
2.1 Capital Budgeting
Capital budgeting is the process of evaluating and
selecting long term investment. This process intended
to achieve the firm’s goal of maximizing
shareholder’s wealth (Gitman, Lawrence, J_Zutter,
Chad J :2014).
2.1.1 Discounted Cash Flow
According to the Chan S. Park (2007: p.216)
Discounted Cash Flow (DCF) is a method of
evaluating an investment by estimating future cash
flow and taking into consideration of money. The
discounted cash flow (DCF) formula is as below:
𝑫𝑪𝑭𝒕 =
𝑵𝑪𝑭
𝒕
(𝟏 + 𝒓)
𝒕
Where:
DCFt = Net cash flow at the year of year t
r = Discount rate
t = Number of the year t = 0,1,2,3….t
2.1.2 Weight Average Cost of Capital
(WACC)
A method to calculating MARR is WACC approach
with assuming source of investment capital from debt
and equity. The expected return for equity investor
name cost of equity, the expected that lenders hope to
make on their investment named cost of debt. All
financing that the company takes on, the composition
of cost of financing will be a weighted average of the
cost of equity and debt, this weight cost name Weight
Average Cost of Capital (Damoradan 2011). WACC
formula as below:
𝑾𝑨𝑪𝑪 =
[
𝒓𝒅 ∗
(
𝟏−𝒕𝒂𝒙
)
∗𝑫/(𝑫+𝑬)
]
+[𝒓𝒆∗𝑬/(𝑫+𝑬)]
Where:
rd = cost of debt
re = cost of equity
D = Debt
E = Equity
2.2 Capital Budgeting Technique
2.2.1 Net Present Value (NPV)
NPV determines whether project is an acceptable
investment, NPV is the difference between the
present value of cash inflow and the present value of
Gas Bumi;
22,00%
EBT; 23,00%
BBM; 0,40%
Batubara;
54,60%
Implementation Monte Carlo Simulation in Investment Evaluation: Case Study - Gas Compressor Investment PLTG 4 x 25 MW
Maleo-Gorontalo
73
cash outflow (Chan S. Park 2007: p.216). NPV
formula as below:
𝑵𝑷𝑽 =
𝒕𝑵
𝒕𝟏
𝑵𝑪𝑭𝒕
(𝟏 + 𝒓)
𝒕
− 𝑰𝒏𝒊𝒕𝒊𝒂𝒍 𝑰𝒏𝒗𝒆𝒔𝒕𝒎𝒆𝒏𝒕
Where:
NCFt = Net Cash flow in t period
r = discount rate
N = life of the project
Decision criteria for NPV as follows:
If NPV ≥ 0, accept the project
If NPV ≤ 0, reject the project
2.2.2 Internal Rate of Return (IRR)
According to Gitman (2018: p.454) Internal rate of
return (IRR) is the discount rate that equates the NPV
of an investment opportunity with 0 (because present
value of cash inflow equals the initial investment).
IRR formula show as below:
𝟎=
𝑪𝑭𝒕
(𝟏 + 𝒓)
𝒕
𝒏
𝒕𝟏
− 𝑪𝑭𝒐
−—
Where:
CFt = Cash flow in period t
r = Discount rate
N = lifetime of the project
IRR = Internal rate of return of the project
When IRR is used to make accept reject decision,
the decision are as follows:
If the IRR > Discount Rate, accept the project.
If the IRR < Discount Rate, reject the project.
2.2.3 Profitability Index (Pi)
According to Ross, et. AI, (2010) profitability index
is ratio accumulation net present value, net cash flow
after initial investment divided by initial investment.
𝑫𝑷𝑰 =
𝑵𝑪𝑭𝒕
(𝟏 + 𝒓)
𝒕
𝒕𝑵
𝒕𝟏
−𝒃 ±
𝒃
𝟐
−𝟒𝒂𝒄
𝑰𝑶
Where:
NCFt = Net Cash flow in period t
r = Discount Rate
IO = Initial Investment
N = project lifetime
DPI criteria for independent project as follow:
If DPI ≥ 0, then project can be accepted
If DPI ≤ 0, then reject the project
2.2.4 Payback Period Analysis (PBP)
Payback period analysis is when the period of time
over which cash flow from investment are expected
to recover the initial outlay (Erich A. Helfert: 2001
p.444), with formula as follow:
𝑷𝑩𝑩 = 𝑵𝑪𝑭𝒕
𝒕𝑵
𝒕𝟏
𝟎
Where:
PBP = Payback period (PBP)
NCFt = Net Cash flow in t period
N = life of the project
Criteria in PBP indicator:
If the PBP < cut off time the project, accept the project
If the PBP > cut off time the project, reject the project
2.3 Sensitivity Analysis
Sensitivity analysis is the process of tweaking one
key input or driver in a financial model and seeing
how sensitive model is to the change in that variable
(Danielle Stein Fairhurst: 2017: p.160). In this
sensitivity analysis used to identify how significant
each variable impact to investment analysis
parameter of the project. The main uncertainty factors
in this project are:
1. Capital cost
2. Inflation
3. Interest
4. Capital expenditure (CAPEX)
5. Operational expenditure (OPEX)
6. Lifetime project (month)
3 RESEARCH MODEL
3.1 Conceptual Framework
Proper decision in investment will generate benefit to
company. The future is certainly not exact, however
capital budgeting technique will be making better
decision in investment evaluation as economic
decision. This paper project output will be used as an
input to company management in order to investment
evaluation.
The framework of this final project shown as
below:
ICAESS 2021 - The International Conference on Applied Economics and Social Science
74
Figure 4: Conceptual Framework.
4 ANALYSES
4.1 Defining Assumption
Project cooperation concept use in this final project is
Build, Operate, Own (BOO), with project lifetime 2
(two) years according to the Letter of Intent (LOI)
from user with an option will be extended until 5 (five)
years.
4.2 Project Investment Cost
Total investment cost of for this project USD
7.118.174, -, according to bill of quantity and
engineering team calculation consist of:
Table 1: Investment Cost.
4.3 WACC
WACC calculation for this project using Regulation
of Badan Pengatur Migas No. 8 tahun 2013, article 14.
Calculation and Reference and show as below:
Table .2. WACC.
Authors use PT Perusahaan Gas Negara (PGN)
with listed code in Jakarta Stock Exchange PGAS as
data to calculated ꞵ(beta) detail provided in Appendix
3-1, assume Gas Compressor use for PLTG 4 x 25
MW in Maleo is part of Gas Infrastructure. Then
WACC output calculation below:
Table .3. WACC Calculation.
4.4 Revenue
Projected revenue of this project divided in 2 (two)
streams:
Cost Capital Recovery (CCR)
Operation Maintenance Recovery (OMR)
1 PROJECT MANAGEMENT 1 LS 115.468
2 ENGINEERING 1 LS 156.970
3 MAIN EQUIPMENT 1 LS 4.255.619
4 PIPING & VALVES 1 LS 547.430
5
C. INSTRUMENT CONTROL, SAFETY
DEVICE & ELECTRICAL
1 LS 465.038
6 CIVIL WORKS 1 LS 575.596
7 SITE CONSTRUCTION 1 LS 277.978
8 PRE COMMISSIONING & COMMISIONING 1 LS 34.302
9 INSURANCE 1 LS 42.667
6.471.067
647.107
7.118.174
PRICE (USD)
SUB TOTAL
PPN 10%
TOTAL
NO ITEM DESCRIPTION QTY UNIT
Implementation Monte Carlo Simulation in Investment Evaluation: Case Study - Gas Compressor Investment PLTG 4 x 25 MW
Maleo-Gorontalo
75
Total CCR and OMR during lifetime project show
as table below:
Table .4. revenue projection.
4.5 Operating Expenditure (OPEX)
To operating a gas compressor facility, required
operating cost that consist of fixed cost and variable
cost:
Table .5. fixed and variable cost/annum
4.6 Capital Budgeting Analysis
Analysis result according to the investment
evaluation analysis rule show as table below:
Table .6. Investment Analysis Result.
From table 5 above, it shown that Investment in
Compressor for PLTG 4 x 25 MW Maleo, Gorontalo
has positive value of NPV USD 500.444 with IRR
11,50% greater than WACC 9% and Payback Period
1,57 years. This parameter described that investing in
Gas Compressor for PLTG 4 x 25 MW feasible and
will generated profit for PT XYZ.
4.7 Sensitivity Analysis
According to Stein Fairhurst, Danielle (2017:140)
Sensitivity analysis is the process of tweaking one
key input variable which lead to the greatest decrease
or increase of the output variables when changes. In
this project sensitivity analysis used to identify how
significant each variable changes impact to
investment analysis parameter of the project NPV,
IRR, PI and PBP. The main uncertainty factors in this
project shown in this table below and output will be
presented in bar chart comparison to evaluate
sensitivity level
Table .7. Sensitivity Parameter.
4.7.1 NPV Sensitivity Analysis
Changes in variable CAPEX, LIFETIME PROJECT
and DEBT: EQUITY PORTION are the most
sensitive parameter to NPV indicator show in the
NPV Sensitivity analysis chart below:
Figure .5. NPV Sensitivity analysis
From figure 5 shows above explain that:
A1). If CAPEX low under budget -10% in this project
will impact to increase NPV USD 968.869,
meanwhile if CAPEX high over budget +10% NPV
value will decrease to USD 32.019,20 or -93,60%
from BASE assumption.
B1). If LIFETIME PROJECT (MONTH) high with
extended 6 (six) month from 24 (twenty-four) month
become 30 (thirty) month NPV will increase to USD
879.563 or increase 75,76% from BASE assumption,
No. Years CCR (USD) OMR (USD)
Total Revenue
(USD)
1
2021 1.829.001 438.973 2.267.974
2 2022 5.472.010 1.314.336 6.786.346
3 2023 3.643.009 876.368 4.519.377
10.944.020 2.629.676 13.573.697
Total
A Operation & Maintenance
1 Man Power 1 LS 599.825 per annum
2 Supporting 1 LS 160.089 per annum
3 Spare Parts & Consumable 1 LS 546.010 per annum
4 O&M all risk Insurance 1 LS 7.397 per annum
Total 1.313.322
PRICE (USD) NoteNO ITEM DESCRIPTION QTY UNIT
No. Sensitivity Focus Low Base High
1 Capital Expenditure (CAPEX) -10% Base +10%
2 Operating Expenditures (OPE
X
-10% Base +10%
3 Interest Rate 4,53% 5,24% 5,92%
4 Inflation Rate 1,32% 2,77% 3,61%
5 Life Time Project (month) 18 24 30
6 Debt : Equity Portion 80% : 20% 70% : 30% 60% : 40%
968.869
500.444
522.355
500.444
93.955
655.908
32.019
500.444
479.459
500.444
879.564
350.429
500.444
500.444
500.444
500.444
500.444
500.444
CAPEX OPEX INTEREST
RATE
INFLATION
RATE
LIFE TIME
PROJECT
(MONTH)
DEBT :
EQUITY
PORTION
Low High Base
A1
B1
C1
ICAESS 2021 - The International Conference on Applied Economics and Social Science
76
meanwhile if with shortened 6 (six) month NPV will
drop to USD 93.995,36 (-81,23%) from BASE
assumption.
C1). DEBT: EQUITY PORTION, with low
assumption 80% Debt: 20% Equity will impact to
NPV project USD 655.907,88 or increase 31,07%
from NPV BASE assumption as impact of changes in
WACC from 9% become 7,31%, meanwhile with high
assumption 60% Debt: 40% Equity NPV become
USD 350.428,60 or decrease 29,98% as impact
changes in WACC from 9% become 10,70%. Others
parameter has less sensitive to NPV calculation
4.7.2 IRR Sensitivity analysis
Changes in variable CAPEX and LIFETIME
PROJECT are the most sensitive parameter to IRR
indicator as show in the IRR Sensitivity analysis chart
below:
Figure .6. IRR Sensitivity analysis
From figure 6 above explain that:
A2). If CAPEX low under budget -10% will impact
to IRR 19,91%, meanwhile if CAPEX high over
budget +10% will impact to decrease IRR 2,85%
lower than WACC 9% or decrease -75,24% from
BASE assumption with IRR 11,50%.
B2). Additional LIFETIME PROJECT (MONTH) 6
(six) month from BASE assumption 24 month
become 30 months will increase IRR to 15,13%,
meanwhile with decrease LIFETIME PROJECT
(MONTH) 6 (six) from 24 month to 18 month will
decrease IRR to 4,78%.
Other’s parameter has less sensitive to IRR
calculation.
4.7.3 Profitability Index (PI) Sensitivity
Analysis
Changes in variable CAPEX and LIFETIME
PROJECT are the most sensitive parameter to PI
indicator as show in the PI Sensitivity analysis chart
below:
Figure .7. PI sensitivity analysis
From figure 7 above explanation that:
A3). If CAPEX low under budget -10%, this project
show PI 1,17 meanwhile if CAPEX high over budget
+10% PI will be decrease to 1,00.
B3). Additional LIFETIME PROJECT (MONTH) 6
(six) month from BASE assumption 24 month
become 30 months will impact to PI from 1,08 to 1,14
meanwhile decrease LIFETIME PROJECT
(MONTH) 6 (six) month become 18 months will be
decrease PI to 1,02.
Other’s parameter has less sensitive to PI calculation.
4.7.4 Payback Period (PBP) Sensitivity
Analysis
Changes in variable CAPEX and LIFETIME
PROJECT are the most sensitive parameter to PBP
indicator as show in the PBP Sensitivity analysis
chart below:
Figure .8. PBP sensitivity analysis
From figure 8 above explain that:
A4). if CAPEX lower under budget -10%, this
project show PBP 1,43 years (equal to 1 year 6 month)
but when the CAPEX high over budget +10% PBP
will be decrease to 1,72 year (equal to 1 year 9 month).
19,91%
11,50%
11,36%
11,50%
4,78%
11,65%
2,85%
11,50%
11,64%
11,50%
15,13%
11,35%
11,50%
11,50%
11,50%
11,50%
11,50%
11,50%
CAPEX OPEX INTEREST
RATE
INFLATION
RATE
LIFE TIME
PROJECT
(MONTH)
DEBT :
EQUITY
PORTION
Low High Base
A2
B2
1,43
1,57
1,58
1,57
1,45
1,57
1,72
1,57
1,57
1,57
1,72
1,58
1,57
1,57
1,57
1,57
1,57
1,57
CAPEX OPEX INTEREST
RATE
INFLATION
RATE
LIFE TIME
PROJECT
(MONTH)
DEBT :
EQUITY
PORTION
Low High Base
A4
B4
1,17
1,08
1,08
1,08
1,02
1,11
1,00
1,08
1,08
1,08
1,14
1,06
1,08
1,08
1,08
1,08
1,08
1,08
CAPEX OPEX INTEREST
RATE
INFLATION
RATE
LIFE TIME
PROJECT
(MONTH)
DEBT :
EQUITY
PORTION
Low High Base
A3
B3
Implementation Monte Carlo Simulation in Investment Evaluation: Case Study - Gas Compressor Investment PLTG 4 x 25 MW
Maleo-Gorontalo
77
B4). High assumption with additional LIFETIME
PROJECT (MONTH) 6 (six) month from BASE
assumption 24 month become 30 months will impact
to PBP from 1,45 years (equal to 1 year 7 month) to
1,72 years (equal to 1 year 9 month) as impact of
extended period which impact to second higher NPV
USD 879.563,73 meanwhile decrease LIFETIME
PROJECT (MONTH) 6 (six) month become 18-
month impact to PBP 1,45 years (equal to 1 years 6
month), with negative impact to NPV USD 93.955,36.
Other’s parameter has less sensitive to PBP
calculation.
According to the sensitivity analysis Capital
Expenditure (CAPEX), Lifetime Project and Debt:
Equity Portion are the most sensitive variable key
input.
4.8 Scenario Analysis
According to the result of sensitives analysis
calculation above, author provide Scenario analysis
as below:
Table .8. Scenario Analysis.
4.9 Monte Carlo Simulation
After getting the results of investment decisions using
the deterministic method as described in table 7 above,
there are still weaknesses in predicting future
conditions, because cash flows are built based on
input from certain estimated values, when in fact
there are uncertainties that may differ in future values.
R. Flage et al (2013) and J. Li et al (2017) explained
that to mitigate uncertainty, it can be done by making
uncertainty values in certain probability distributions.
S. Grey at all (1995) explained that the simulation
method is a method that can accommodate
quantitative risk and uncertainty assessments in
determining project investment. Monte Carlo
simulation is one of the most applicable methods.
According to M. Marseguerra and E. Zio (2009:
180-186) Monte Carlo simulation method is based on
iteration of repetition of random numbers and is
usually used to obtain forecasts of certain probability
models in solving a problem. Referring to the
explanation above, the Monte Carlo simulation can be
applied to predict the financial feasibility of a project
by considering risks and uncertainties.
4.9.1 Monte Carlo Simulation Steps
The risk analysis simulation steps in the project's
financial feasibility based on the Monte Carlo
simulation technique are as follows:
1. Identification of input variables key changes with
the greatest impact to the NPV. According to the
sensitivity analysis Capital Expenditure
(CAPEX), Lifetime Project and Debt: Equity
Portion are the most sensitive variable key input.
2. Identify the NPV output calculation.
3. Define related assumptions to assign probability
distribution to the input variables. Authors use
probability distribution for the input variables:
Table .9. Probability distribution.
No.
Input
Variables
Probabilit
y
Distribution
Explanation
1 CAPEX Uniform
distribution
With the
minimum and
maximum value
2 Lifetime
Project
Uniform
distribution
With the
minimum and
maximum value
3 Debt:
Equity
Portion
Triangular
distribution
With the
minimum, most
likely and
maximum value
4.9.2 Monte Carlo Simulation Result
Monte Carlo simulation result with 1.000 iteration as
follows:
Table .10. Statistic data from NPV Simulation Result.
According to the table 10 above, Probability NPV<0
in this project is 10,32% meanwhile NPV>0 is
89,68%, NPV Monte Carlo Normal Distribution
shown as below:
Worst Case
Scenario
Base Case
Scenario
Best Case
Scenario
Payback Period (PBP) - Years 1,62 1,57 1,68
Net Present Value (NPV) 199.076,29 500.444,15 1.239.436,89
Profitability Index (PI) 1,03 1,08 1,20
Internal Rate Return (IRR) 9,1% 11,50% 19,91%
Criteria
Statistic Value
Mean 474.346,30
Median 481.496,58
Standar Deviation 375.428,74
Skewness (0,03)
Kurtosis (0,56)
Minimum (449.661,21)
Maximum 1.434.177,00
Probability NPV <0 10,32%
ICAESS 2021 - The International Conference on Applied Economics and Social Science
78
Figure .9. NPV Monte Carlo Normal distribution Simula-
tion.
5 CONCLUSIONS
5.1 Capital Budgeting
Based on Investment Analysis calculation use Capital
budgeting technique in table 5 above, it shown that
Investment in Compressor for PLTG 4 x 25 MW
Maleo, Gorontalo has positive value of NPV USD
500.444 with IRR 11,50% greater than WACC 9%
and Payback Period 1,57 years. These parameters
described that investing in Gas Compressor for PLTG
4 x 25 MW recommended to executed assume project
will generate profit for PT XYZ.
5.2 Sensitivity Analysis
Sensitivity analysis shown that Capital Expenditure
(CAPEX), Lifetime Project and Debt: Equity Portion
are the most sensitive variable key input changes with
the greatest impact to the NPV.
5.3 Monte Carlo Simulation
In this paper, for performing Monte Carlo simulation
author use Capital Expenditure (CAPEX), Lifetime
Project and Debt: Equity Portion as the input
variables. The result shown that Probability NPV<0
is 10,32% and project success is NPV>0 is 89,68%
as explain in figure 9.
This paper is still limited in getting the right
variable input data. Expert opinion and historical data
review methods should be applied, not just based on
theoretical calculations
REFERENCES
Park, Chan S., 2007. Contemporary Engineering Econom-
ics. Pearson Education, Inc, New Jersey: 14th Edi-
tion.p.216.
Gitman, Lawrence J. Zutter, Chad J., 2018. Principles of
Managerial Finance. Pearson Education. Global edi-
tion: 14th edition: p.454
Ross, S.A., Westerfilemd, R.W. and Jaffe, J.F .2010 Corpo-
rate Finance. McGraw – Hill. New York 10th edition.
Helfert, Erich A., 2001. Financial Analysis Tools and Tech-
nique. McGraw-Hill. USA p.444.
Stein Fairhurst, Danielle., 2017, Financial Modelling in Ex-
cel. Jhon Wiley & Son, Inch. New Jersey: p.160.
R. Flage, P. Baraldi, Z. Enrico and T. Aven 2013. Probabil-
ity and Possibility Based Representation of Uncertainty
in Fault Tree Analysis. Risk Analysis 33 (1), P:121-133
J. Liu, F. Jin, Q. Xie and M. Skitmore, .2017 Improving
Risk Assessment in Financial Feasibility of Interna-
tional Engineering Project: A Risk Driver Perspective,
International Journal of Project Management. p:204-
211
S. Grey. 1995. Practical Risk Assessment for project Man-
agement. Jhon Wiley & Sons Ltd.
M. Marseguerra and E. Zio. 2009, Monte Carlo Simulation
for Model Based Fault Diagnosis in Dynamic System,
Reliab. Eng. Syst. Sf 94 (2). p:180-186
Peraturan BPH MIGAS Nomor 8 tahun 2013, pasal 14 Ap-
pendix
Implementation Monte Carlo Simulation in Investment Evaluation: Case Study - Gas Compressor Investment PLTG 4 x 25 MW
Maleo-Gorontalo
79