Study of the Use of Drywall as the Wall Cover Material Reviewed
from Cost and Time Aspects
Ni Kadek Sri Ebtha Yuni, I Wayan Sudiasa and I Nyoman Suardika
Civil Engineering Department, Bali State Polytechnic, Bali, Indonesia
Keywords: Dry Wall, Cost, Time, Wall Work.
Abstract: To the date, a lot of wall works still use materials in the form of red bricks, light bricks, bricks, and panels.
Likewise, seen from research related to value engineering, most of them examine the use of these materials.
From the cost view, red brick material is cheaper than using lightweight brick and precast panels. Meanwhile,
in terms of labor productivity, precast panel is better than red bricks and light bricks. The rukom system
building uses a lightweight steel frame and fiber cement which is earthquake resistant. The application of the
use of lightweight steel frame materials and fiber cement is known as the drywall system. The purpose of this
study is to calculate the unit price of the work, namely the coefficient of project resources (materials, labor,
and tools). In this research, the method of drywall installation work is also developed, therefore the completion
time of the work can be determined. The long-term goal of this research is to examine the quality of the work
and compare it with other wall materials. This research begins by studying the shop drawing drawings, then
calculations are carried out to determine material requirements including the need for waste materials.
Furthermore, observations were made to determine the need for labor, the need for tools, the method of
installation. Through the installation method in the field, it can be seen the time needed to complete the work.
The result of this research is the cost required to install a double-installed drywall truss is Rp. 172,198.64 per
m2. For the installation of the layer using soundstop gypsum material, it is Rp. 121,641.74 per m2. Installation
of the wall layer with GRC including the installation of soundproofing is IDR 341,803.02 per m2. The price
includes materials, wages and fees as well as 5% overhead. For the tool does not use heavy equipment so that
the cost of the tool is Rp. 0.0. The total cost of drywall work per 1 m2 is Rp 635,643.41. This price does not
include finishing work such as painting. 2. To complete the drywall installation work with a module measuring
3 meters x 6 meters, it takes 1 day to install the frame, wall covering, wall covering each. The overall drywall
work with a volume of 6,068 m2 requires 30 days to complete the preparation and marking work, 90 days for
frame installation, 90 days for wall covering, 90 days for walls. So the total time needed to complete the
drywall work is 121 days.
1 INTRODUCTION
Wall material continues to develop along with the
demands of the need to achieve the most effective and
efficient cost, time, quality (Rori, 2020). Currently,
various types, brands and products of building
materials are circulating in the market. This is an
alternative, and make it to be easier for people to
determine the type of building material to be used and
also easier to control costs in the process of building
a house or building. The emergence of several brands
with various specifications is solely aimed at
producing better buildings with optimal cost, quality,
and time. In the past, people tended to use bricks or
red bricks for wall work, but now people are familiar
with lightweight bricks and precast panels (Yuni,
2018). Wall materials continue to develop along with
the demands of the needs in achieving the most
effective and efficient cost, time, quality. Currently,
in addition to lightweight brick which is quite popular
as a wall material, now there are other alternative
materials using drywall.
Drywall is a drywall work that does not involve
cement, sand and water. Drywall offers a lighter
system than conventional wall systems. The main
components of drywall are gypsumboard frames, J
Track, E-Stud. Additional components are
compound, sealant, insulation, spindle pin. The use of
drywall components is determined based on the
installation area. Wet areas such as bathrooms,
368
Yuni, N., Sudiasa, I. and Suardika, I.
Study of the Use of Drywall as the Wall Cover Material Reviewed from Cost and Time Aspects.
DOI: 10.5220/0010946000003260
In Proceedings of the 4th International Conference on Applied Science and Technology on Engineering Science (iCAST-ES 2021), pages 368-372
ISBN: 978-989-758-615-6; ISSN: 2975-8246
Copyright
c
2023 by SCITEPRESS Science and Technology Publications, Lda. Under CC license (CC BY-NC-ND 4.0)
kitchens, and walls will be selected for waterproof
gypsumboard materials. Furthermore, after the
drywall is installed, proceed with wall finishing.
Finishing can be in the form of paint, ceramic tile,
marble, and wallpaper (Plasterboard, 2018).
It is important to pay attention to the selection of
wall constituent materials because the decrease in the
foundation structure is also caused by the heavy load
of the walls(Plasterboard, 2018). Gypsum is one
example of a mineral with a dominant calcium
content in the mineral. Gypsum board consists of a
core of gypsum material wrapped with reinforcing
paper around it. The thickness of gypsum varies, the
average in the market is 9 mm, 12 mm and 15 mm for
the standard type of gypsum. Currently, in addition to
lightweight brick which is quite popular as a wall
material, now there is another alternative material,
namely using drywall. Based on research
(Madutujuh, 2016), when viewed from the strength of
the structure, buildings using light steel frames and
fiber cement are earthquake resistant.
Development engineering is basically an activity
based on an analysis of various aspects to achieve the
goals and objectives specific goals with results
optimally possible. To determine the cost of a unit of
work as part of project activities, a cost estimate is
carried out (Husen, 2011). In determining the project
resource requirements, the formula for the volume of
work multiplied by the unit price analysis coefficient
is used (Husen, 2011). The coefficient of analysis is
obtained through the calculation of the realization in
the field. For the labor coefficient, it is necessary to
calculate the productivity. In general, productivity is
defined as a comparison between the output and input
or output: input (Husen, 2011). The definition of
output includes volume and quality, while input
includes materials and energy, labor and capital
equipment. The labor coefficient is determined to
determine the amount of labor and the time used to
complete one work item with a certain volume
(Messah et al., 2013).
Project scheduling is one of the elements of
planning results, which can provide information
about the planned schedule and project progress in
terms of resource performance in the form of costs,
labor, equipment and materials as well as project
duration plans and time progress for project
completion. In the implementation of construction
projects, the availability of labor affects the
completion of construction projects (Messah et al.,
2013). The implementation schedule can be arranged
in the form of a barchart. The length of the beam
indicates the duration of the activity and usually the
activities are arranged according to the chronology of
the work (Messah et al., 2013). Completion of work
on a project can run according to the target time, cost,
quality and quality if it is supported by good
implementation and supervision methods (Messah et
al., 2013).
2 METHOD
The research method is field observation to obtain
field data in the form of material needs, tools, labor,
implementation time requirements and work methods
used. Secondary data in this study is shop drawings.
In addition, secondary data is also obtained from
reports/brochures about drywall that have been
implemented. Primary data obtained through field
observations. Observations were carried out by
directly observing field conditions. Determine the
productivity of workers who work in bulk units,
determine the type of heavy equipment used in the
work, look for material prices and wholesale prices
per unit of work. Furthermore, the data is analyzed to
Figure 1: Research Stage.
Star
t
Secondary data
Observation
Man, material,
machine
Data Analyze
Productivity Analyze
Coefficient Survey
Unit Price Analyze
Wo
r
k Completion
Schedule Anal
y
ze
En
d
Study of the Use of Drywall as the Wall Cover Material Reviewed from Cost and Time Aspects
369
determine the job index and resource requirements of
the project. The result is an analysis of the unit price
of work. Furthermore, to determine the duration of
work based on data on the ability of workers to
complete work per unit m2.
This research will be carried in as following steps:
1. Collecting data in the form of shop drawing.
From the shop drawing, the volume of work is
calculated, then the material requirements are
calculated.
2. Determine the productivity of workers who
work in bulk units. This productivity is to
determine the ability to complete work in one
piece.
3. Looking for material prices and wholesale
prices per unit of work. Furthermore, these
figures are made in the form of a work unit index
or an analysis of the unit price of work.
4. Calculating project resource requirements, tool
materials, labor based on field unit index. The
volume of resource requirements is the product
of the job index with the volume of work.
5. From the cost analysis above, it is obtained an
analysis of the unit price of the drywall
installation work per unit m2.
6. Prepare a work implementation schedule based
on labor productivity and field work methods.
3 RESULT AND DISCUSSION
Drywall is a dry wall covering job, meaning that it
does not involve water, cement and sand. In general,
wall coverings are in the form of red brick, light brick,
brick and precast panels. Drywall itself uses gypsum
material as a cover along with frames and other
accessories. The components of drywall are the
frame, covering and covering. The frame consists of
2 types, namely single frame and double frame.
A. Drywall Component
Installation of drywall consists of 3 stages, which use
components of different materials. The components
are the frame, the inner cover, and the outer cover.
The drywall specification in this study is to use a
double frame, the inner cover uses 12 mm Soundstop
gypsum, and the outer cover uses 12 mm GRC Board.
Figure 2: Drywall Section.
B. Material Requirement Survey
Drywall work has specifications that vary according
to the needs and the desired design. Material
requirements are the number of material components
needed in the installation of drywall in 1 m2. To
obtain these needs, the data obtained through direct
observation in the field. The observations were made
on the module or the drywall installation area with a
size of 6,000 meters x 3,000 meters. The drywall
studied in this study is for wall coverings outside the
building with the following specifications: The wall
thickness is 250 mm, using a double frame system
with a frame distance of 400 mm, installing gypsum
on 2 sides, 2 faces and 1 layer, using gypsum
soundstop with a thickness of 12 mm on the inside,
using 12 mm GRC on the outside, using rockwool
silencer.
C. Manpower Coeficient
Drywall works uses the wholesale system. One group
of contractors consists of 1 worker, 1 handyman and
1 foreman. Productivity is the ratio between the
volume done and the amount of time needed to do the
work. The average productivity per hour of drywall
frame installation using materials as described in the
truss component table using 1 worker, 1 handyman,
and 1 foreman is 2,250 m2/hour. Next is the
calculation of the labor coefficient. The coefficient of
unit price analysis is the numbers of the amount of
material and labor needed to do a job in a certain unit.
The average productivity per hour of installing
gypsum inside walls using 2 workers, 2 builders, and
1 foreman is 2,250 m2/hour. Next is the calculation
of the labor coefficient. The coefficient of unit price
analysis is the number of material and labor
requirements needed to do a job in a certain unit. The
average productivity per hour of external wall
installation using GRC using 2 workers, 3 craftsmen,
and 1 foreman is 2,250 m2/hour. Next is the
calculation of the labor coefficient. The coefficient of
iCAST-ES 2021 - International Conference on Applied Science and Technology on Engineering Science
370
unit price analysis is the numbers of the amount of
material and labor needed to do a job in a certain unit.
D. Project Resource Cost
Project resources consist of materials, tools, and
labor. The price of each project resource is obtained
through a field survey. The results of the following
material prices are obtained based on a survey of
several shops or suppliers of building materials and a
survey of wages for the foreman who works on
drywall.
E. Unit Price of Drywall Works
Based on the results of the need for wood materials
and the coefficient of labor can be calculated analysis
of the unit price of work. The specification of drywall
work to the installation of walls with gypsum without
finishing work. The workforce uses workers from
outside of Bali. Analysis of unit prices with
specifications for the installation of the frame using
bullet nails, hanging elbows, Metal Track 64 0.50 mm
BMT @ 3m, Metal Stud 64 0.50 mm BMT @ 3m,
Head track 64 0.50 mm BMT @ 3m, Screw 6 3/8,
Nails 3 cm concrete, and sealant. Harga per 1 m2
pekerjaan pemasangan rangka ganda drywall adalah
Rp 172,198.64. Harga tersebut sudah termasuk profit
dan overhead sebesar 5%.
Analysis of unit prices with the specifications for
interior wall installation is Gypsumboard Soundstop
12 mm, screw, paper tape, coumpond, sandpaper, and
sealant. The price per 1 m2 of interior wall
installation with gypsum is Rp 121,641.74. This price
includes 5% profit and overhead. Unit price analysis
with specifications for external wall installation
including sound suppression installation are GRC
Board 12 mm, screw, U list, sealant, Rockwool
density 60 kg/m3 t=5 cm, Spindle pin and glue. The
price per 1 m2 of external wall installation with GRC
is IDR 341,803.02. This total price includes 5% profit
and overhead.
Table 1: Drywall wall work unit price recapitulation.
No Item
Total
(Rp)/m2
11
Installation of double frame
drywall
172,198
22
Installation of inner play wall
with Gypsum Soundstop 12 mm
121,641
33
Installation of outer wall with
GRC inclusive of silencer with
rockwool
341,803
TOTAL
635,643
The cost required to install a double-installed
drywall wall truss is IDR 172,198 per m2. For the
installation of the cover using soundstop material, it
is Rp. 121,641 per m2. Installation of the wall layer
with GRC including the installation of soundproofing
is IDR 341,803 per m2. The price includes materials
and wages. For the tool does not use heavy equipment
so that the cost of the tool is Rp. 0.0. The total cost of
drywall work per 1 m2 is Rp 635,643.41
F. Work Completion Analysis
Drywall work started by installing the frame. The
components of wall frame installation are bullet nails,
hanging elbows, Metal Track 64 0.50 mm BMT @
3m, Metal Stud 64 0.50 mm BMT @ 3m, Head track
64 0.50 mm BMT @ 3m, Screw 6 3/8, Concrete Nails
3 cm, and sealants. Next step, continued with the
installation of the indoor wall covering with 12 mm
soundstop gypsum. The last step is the installation of
the outer wall with GRC includes a damper from
Rockwool. Based on the sequence of work above, the
completion time of drywall work can be determined.
The field or module observed is 6 meters x 3 meters
in size. To complete the work required 1 to 2 workers,
1 to 2 builders and 1 foreman.
The frame consists of mounting bullet nails,
hanging elbows, Metal Track 64 0.50 mm BMT @
3m, Metal Stud 64 0.50 mm BMT @ 3m, Head track
64 0.50 mm BMT @ 3m, Screw 6 3/8, 3 cm Concrete
Nails, and sealant takes 1 day or 8 hours. Similarly,
the installation of the wall covering with gypsum
takes 1 day or 8 hours. The wall covering including
rockwool also takes 1 day or 8 hours.The time to
complete the preparation and marking work is 30
days, frame installation 90 days, wall covering 90
days, wall 90 days. So the total time needed to
complete the drywall work is 121 days.
4 CONCLUSIONS
Total cost to install a double-installed drywall truss is
IDR 172,198.64 per m2. For the installation of the
cover using soundstop material, is Rp. 121,641.74 per
m2. Installation of the wall layer with GRC including
the installation of soundproofing is IDR 341,803.02
per m2. The price includes materials, wages and fees
as well as 5% overhead. For the tool does not use
heavy equipment so that the cost of the tool is Rp. 0.0.
The total cost of drywall work per 1 m2 is Rp
635,643.41. This price is not included with finishing
work (painting).
Study of the Use of Drywall as the Wall Cover Material Reviewed from Cost and Time Aspects
371
To complete the drywall installation work with
module size 3 meters x 6 meters, requires duration to
install the frame, inner wall cover, outer wall cover is
1 day for each work. The overall drywall work with a
volume of 6,068 m2 requires 30 days to complete the
preparation and marking work, 90 days for frame
installation, 90 days for indoor wall covering, 90 days
for. Therefore, total duration to complete drywall
work is 121 days. walls. So the total time needed to
complete drywall work is 121 days.
ACKNOWLEDGEMENTS
The authors thank to institutions that have supported
this research. The authors also thank project teams
that have been created to conduct research. Thanks
also to the research team who have always been
supported each other to complete this research
REFERENCES
Abrar, H. (2011). Manajemen Proyek, Perencanaan,
Penjadwalan, & Pengendalian Proyek. Yogyakarta:
Andi Yogyakarta.
Ibrahim, B. (1993). Rencana Dan Estimate Real Of Cost.
Jakarta: Bumi Aksara.
Madutujuh, N. (2016). Perencanaan Rumah Prefabrikasi
Tahan Gempa dengan Sistem Rangka Baja Ringan
dengan Dinding Papan Serat Semen (Rukom).
Bandung: Universitas Parahayangan.
Messah, Y., Sina, D., & Manubulu, C. (2013). Analisa
Indeks Biaya Untuk Pekerjaan Beton Bertulang Dengan
Menggunakan Metode Sni 7394-2008 Dan Lapangan
(Studi Kasus Pada Proyek Pembangunan Asrama Stikes
Chmk Tahap III).
Onibala, E. (2018). Metode Pelaksanaan Pekerjaan
Konstruksi dalam Proyek Pembangunan Sekolah SMK
Santa Familia Kota Tomohon. Jurnal Sipil Statik, 16.
Plasterboard, P. P. B. (2018). Technical Manual Jayaboard
Versi 5.
Rafik, A., Muhammad Humaidi, & Firman, R. (2018).
Pengaruh Penggunaan Bata Merah dan Bata Ringan
Terhadap Dimensi Pondasi dan Harga Rumah Tipe 54.
Jurnal Intekna, 18.
Rori, G. (2020). Analisis Perbandingan Biaya Material
Pekerjaan Pasangan Dinding Bata Merah dengan Bata
Ringan. Jurnal Sipil Statik. Jurnal Sipil Statik, 3.
Umar, H. (1998). Riset Sumber Daya Manusia Dalam
Organisasi. PT. Gramedia Pustaka Utama.
Yuni, N. K. S. E. (2018). Analisis Penerapan Rekayasa
Nilai pada Pekerjaan Dinding Ditinjau dari Aspek
Biaya dan Waktu Pelaksanaan. Prosiding Sentrinov
2018.
Waluyo, R. (2017). Pengaruh Resource Leveling Terhadap
Alokasi Tenaga Kerja Pada Proyek Konstruksi. Jurnal
Ilmiah Teknik Sipil, 21, 2.
Widiasanti. (2013). Manajemen Kontruksi. Bandung: PT
Remaja Rosdakarya.
iCAST-ES 2021 - International Conference on Applied Science and Technology on Engineering Science
372