Earned Value Concept on Project: Delay Due Covid-19 Pandemic
Monika Natalia, Jajang Atmaja and Dini Sekar Putri
Construction Management, Department of Civil Engineering, Politeknik Negeri Padang, Indonesia
Keywords: Project Performance, Earned Value, Time Cost Trade Off.
Abstract: Earned value concept provides project performance cost and time estimates all project work. PIK Pulo Gadung
Flats Project East Jakarta Project experienced a deviation -12.70% on the 441th day from 569 days due to the
covid-19 pandemic. Resource delimitation, delimitation on the supply material, restrictions working time of
government agency cause administrative management not optimal, workers who will to come Jakarta cause
the arrival of workers not on time and others. The purpose research is to evaluation the performance PIK Pulo
Gadung Flats Project Stage 2 Tower 3A East Jakarta Project with the earned value concept using Microsoft
Project. The results estimated project time 666 days. The remaining duration to complete the remaining work
is 225 days with a projected final cost of IDR 56,862,527,165.17. There are a deviation of (-IDR
6,166,888,821.53) compared to the initial cost of IDR 50,696,438,343.64. Alternative acceleration with time
cost trade off method, work shifts, the project time becomes 656.7 days, cost of IDR 59,123,458,843.23.
Addition of overtime hours, the project completion time 659.7 days, cost IDR 59,144,617,761.56.
Recommended is work shift system because the completion time is 6 days faster than the addition overtime
and cost required is more efficient IDR 1,862,634,002.74.
1 INTRODUCTION
Construction project of activity that takes a limited
period of time, resources, to achieve results in the
form of buildings or infrastructure (Messah, 2013).
Deviation cost and time indicate poor project
management. Earned value is one of the tools used in
project management that integrates cost and time
(Septian, 2019). The concept of earned value can
analyze implementation performance and generate
cost and time estimates for completion of all project
work (Auzan, 2017).
The concept of earned value can be analyzed with
Microsoft project applications. Accelerating the
project completion time is an attempt to complete the
project earlier than the completion time under normal
circumstances. One method is to crash the program
with the time cost trade off method. There are four
factors that can be optimized to carry out acceleration
in an activity, namely including increasing the
amount of labor, scheduling overtime work, the use
of heavy equipment and changes to construction
methods in the field (Putri, 2018).
Silaosinan Bridge Construction project,
Mentawai, the planned completion time is 39 weeks
with a conctract value of 26, billion. In the 26
th
week
there was a deviation in the weight of the work of
3,28%, with a deviation of costs of IDR 685.220.700,-
and the estimated complation time being 42 weeks.
By applying the concept of earned value, the project
completion time is 39 weeks (according to the plan)
and the cost deviation is IDR 113,771,442.60.
Acceleration is carried out with overtime and
additional work shifts (Atmaja, 2019).
PIK Pulo Gadung Flats Project Stage 2 Tower 3A
East Jakarta Project consist of 16 floors, total
planning cost IDR 50,696,438,344,64,- with duration
569 days. This project started on januari 13, 2020.
Due to the rapidly spreading covid-19 pandemic in
Jakarta, large-scale social restrictions (PSBB) had to
be implemented, resulting in project implementation
performance deviating by up to 12.70% in March
2021, the day 441th (63rd week of implementation)
This research aims to measure the performance
PIK Pulo Gadung Flats Project Stage 2 Tower 3A
East Jakarta Project with the concept of earned value
using the Microsoft Project application. It can be
known the duration and costs needed on the
remaining work. The results of the earned
value analysis are used as a reference to provide
project acceleration solutions with the time cost trade
off method with the addition of additional working