(11)
Where S is single pile foundation settlement; D is pile
diameter; Q is pile bearing capacity; L is pole length;
A
p
is pile cross-sectional area; E
p
is modulus of
elasticity of concrete pile material.
2.4 Static Loading Test
According to Hardiyatmo, 2002, the static loading
test was carried out with several objectives, such as:
Determine the graph of the load and settlement
relationship, especially in the load around the
expected design load.
Ensure that foundation failure will not occur
before the target load is reached. Its value is
several times the design load. This value is used
as a safety factor.
Determine the actual ultimate capacity, check
the results of the calculation of the pile capacity
obtained from the static and dynamic formulas.
The standard test method for deep foundations
under static axial compressive load consists of 7
procedures, one of which is the slow maintained test
load method.
The Slow Maintained test load Method (SM Test)
is recommended by ASTM D1143-81, this method is
generally used in field research before further work is
carried out, the testing procedure consists of:
a. Pile load is divided into eight equal stages,
namely 25%, 50%, 75%, 100%, 125%, 150%,
175% and 200% design load
b. Each increase in load must maintain the rate of
descent which must be less than 0.01 in/hour
(0.25 mm/hour)
c. Maintain 200% design load for 24 hours
d. After the required time is reached, reduce the
load by 25% with a gap of 1 hour between
reduction times.
e. After the load has been applied and removed,
reload the pile for load testing in increments of
50% of the design load, allowing 20 minutes for
additional load.
f. Then increase the load in increments of 10% of
the design load.
3 METHOD
The research stages are divided into several stages as
shown in Figure 3, and are described as follows:
a. Manufacture of mini pile specimens in the form
of a square cross section with a size of
12x12x250 cm, using 4Ø10 main reinforcement
and D6-200mm stirrup reinforcement as seen in
Figure 2. The composition of the mixture refers
to the regulation of the Minister of PUPR No. 28
of 2016 for the quality of K225. In addition,
several specimens of concrete cubes of
15x15x15 cm were also made to determine the
quality of the mini pile concrete.
b. Sondir testing was carried out at the location of
the mini pile to determine the cone resistance
data (q
c
) and cone side friction resistance (q
f
).
c. Calculate the amount of design load that will be
given to the mini pile during testing.
Determination of the carrying capacity of the
plan (Q
u
) using the Bagemann method by
analyzing the sondir test data.
d. Mini pile erection at a predetermined location
using a Drop Hammer (Figure 4). One point of
the foundation using two mini piles with steel
plate connection as shown in Figure 5. The
depth of the pile is 2x2.5 m but the embedded
depth of the mini pile is 4.5 m, which is 0.5 m
not embedded as the set up of loading test.
e. The loading test was carried out based on the
SM Test. Static load testing was carried out for
two days with a load of 25, 50 ,75 and 100% of
the design load. Then let stand for 24 hours and
the load was reduced gradually. This load was
given to determine the actual settlement that
occurs in the mini mile based on the carrying
capacity of the plan achieved. To facilitate load
application, two mini pile points were placed at