Analysis of Worker Productivity at Construction Projects in Highlands: A Case Study from the Development of Penanjakan Viewpoint at Bromo Tengger Semeru National Park in East Java

Kusnul Prianto, Mega Ayundya Widiastuti

2018

Abstract

One of the leading tourist destinations in East Java is Mount Bromo. This destination is included in the top 10 tourist channels that have received support from various parties including UNESCO and administratively under the Balai Besar of Bromo Tengger Semeru National Park. The increasing number of tourists has also increased the need for public facilities supporting the tourist area. The construction of the viewing tribune is a form of attention to the increasing number of tourists every day. The major work of this tribune is stone masonry, which is nearly 40 percent of the total work done. From the field observational data, the calculation of the standard completion time for each m3 of river-stone foundation is 202.086 minutes/m3 or 3.3681 hours/m3, meaning that the productivity of 2 workers and 3 workers in one day is 2.375 m3. Based on the calculation of the unit price of river-stone foundation installation in the contract, it is obtained the price of wages for installing river-stone foundation/m3, which is Rp 365,125.-. According to observations in the field, the installed price is the amount of wages in 1 day (8 hours), which is Rp 1,010,000.-. For 1 m3, it takes 3,3681 hours, so in 1 m3, direct costs in the field is (Rp. 1,010,000 / 8 hours) x 3.3681, or Rp 425,222. There is a difference as many as Rp 60,097.- in wages for every m3 of river-stone foundation

Download


Paper Citation


in Harvard Style

Prianto K. and Widiastuti M. (2018). Analysis of Worker Productivity at Construction Projects in Highlands: A Case Study from the Development of Penanjakan Viewpoint at Bromo Tengger Semeru National Park in East Java. In Proceedings of the Built Environment, Science and Technology International Conference - Volume 1: BEST ICON, ISBN 978-989-758-414-5, pages 139-147. DOI: 10.5220/0008904400002481


in Bibtex Style

@conference{best icon18,
author={Kusnul Prianto and Mega Ayundya Widiastuti},
title={Analysis of Worker Productivity at Construction Projects in Highlands: A Case Study from the Development of Penanjakan Viewpoint at Bromo Tengger Semeru National Park in East Java},
booktitle={Proceedings of the Built Environment, Science and Technology International Conference - Volume 1: BEST ICON,},
year={2018},
pages={139-147},
publisher={SciTePress},
organization={INSTICC},
doi={10.5220/0008904400002481},
isbn={978-989-758-414-5},
}


in EndNote Style

TY - CONF

JO - Proceedings of the Built Environment, Science and Technology International Conference - Volume 1: BEST ICON,
TI - Analysis of Worker Productivity at Construction Projects in Highlands: A Case Study from the Development of Penanjakan Viewpoint at Bromo Tengger Semeru National Park in East Java
SN - 978-989-758-414-5
AU - Prianto K.
AU - Widiastuti M.
PY - 2018
SP - 139
EP - 147
DO - 10.5220/0008904400002481